DQ1-PHAA-2016-1215 Midfield State 1 PA-Final-BH.pdf
PDF 81 KB Posted
- Attached to
- PHAA, PRAW, Plug & Abandon Midfields State
- Solicitation number
- DQ1 PHAA 2016001215 2
- Issued by
- Yuma County, Denver City, Colorado
About this file
This is a Documented Quotation issued by the Colorado Department of Natural Resources, Oil and Gas Conservation Commission (COGCC) for the plugging and abandonment of the Midfield State #1 well located in Yuma County, Colorado. The project involves the complete abandonment of a vertical well drilled in 1919 with a total measured depth of 3,650 feet, requiring multiple cement plugs to be installed at various depths to stop gas migration, followed by well cellar filling and pad reclamation. The mandatory pre-bid meeting and site showing is scheduled for April 14, 2016 at 11:00 AM at the County Road 22 and well access road intersection, with bidder registration required by April 12, 2016 at 3:00 PM with Steve Jenkins (303-894-2100 x 5104). Bids are due April 20, 2016 at 4:00 PM and must be submitted to the Department of Natural Resources Purchasing Agent Brenda Hannu via mail, facsimile, hand delivery, or email. All contractors must attend the mandatory pre-bid meeting and sign the attendance sheet, as failure to do so will result in bid rejection. Performance time requirements mandate project start and completion between May 20, 2016 and June 10, 2016, with all work and equipment removal completed by June 10, 2016 at 5:00 PM. Award will be made to the lowest responsive and responsible bidder meeting all stated requirements and criteria.
Payment will be made on a lump sum and unit price basis as specified in the Bid Schedule, with payment made only for actual verified quantities. Bid items include Mobilization/Demobilization (lump sum), Plug and Abandon (hourly rate with standby time paid at 75 percent of the hourly rate), Cement Services (per 94-pound sack), Solid Waste Management (lump sum), and Liquid Waste Management (per load, up to 130 barrels per load). The project includes a 5 percent preference for Service Disabled Veteran Owned Small Businesses (SDVOSBs) officially registered with the U.S. Department of Veterans Affairs and a resident bidder preference equal to preferences given by the nonresident bidder's home state. Funding for the project will be paid from the Plugging and Well Reclamation portion of COGCC's Oil and Gas Conservation and Environmental Response Fund. Contractors must submit a completed Bid Schedule, Equipment and Materials Rate Schedule, and List of Equipment Offered with their bid, and must own or have firm arrangements to lease or rent all equipment necessary for project completion. The COGCC Project Manager will supervise all plugging activities during regular business hours (8:00 AM to 5:00 PM on weekdays) to ensure compliance with design specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Midfields State #1 WBD.xlsx | XLSX spreadsheet | |
| POTerms&Conditions1-1-09.pdf | ||
| BID SCHEDULE.pdf | ||
| BIDDER LIST OF EQUIPMENT OFFERED.pdf | ||
| DNR POGeneralConditions 3-17-2015.pdf | ||
| Special Provisions 1-1-09.pdf | ||
| MAP_PRE BID MEETING ON SITE MEET UP LOCATION.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Colorado Department of Natural Resources
DOCUMENTED QUOTATION
Special Conditions and Bid Information
Midfields Oil Company Midfield State #1 Plugging and Abandonment Project
DQ1-PHAA-2016-1215
1.0 GENERAL CONDITIONS
The Colorado Oil and Gas Conservation Commission (COGCC) is bidding this project using an informal Documented Quotation procedure in coordination with the Colorado Department of Natural Resources Purchasing Office. This request for Documented Quotation incorporates the Special Conditions described herein. The attached Wellbore Diagram Drawings, Bid Schedule, General Conditions for Purchase Orders (attached), Purchase Order Terms and Conditions, List of Equipment Offered Form, Special Provisions, and other Contract Documents described in the General Conditions for Purchase Orders are hereby incorporated by reference.
1.1 PROJECT WORK SUMMARY AND LOCATION
The work will include plugging and abandonment of the Midfield State #1 well, located in the SE1/4 of the NW1/4 of Section 14, Township 2 South, Range 43 West, 6th P.M., Yuma County, Colorado. The wellbore configuration and plugging procedure are described in Section 2.0 Project Work Description. Any costs to plug and abandon the Midfield State #1 will be paid from the Plugging and Well Reclamation portion of COGCC’s Oil and Gas Conservation and Environmental Response Fund.
1.2 PRE-BID MEETING AND SITE SHOWING
Bidders shall visit the site and take such other steps as may be reasonably necessary to ascertain the nature and location of the work, including average climatic conditions and the general and local conditions which can affect the work or the cost thereof. Failure to do so will not relieve bidders from responsibility for estimating properly the difficulty or cost of successfully performing the work.
A mandatory pre-bid meeting and site showing will be held on April 14, 2016 at 11:00 AM. All contractors must register for the pre-bid meeting and site showing with Steve Jenkins, COGCC North Central Area Engineer, @ 303-894-2100 x 5104 (or Steve.jenkins@state.co.us) prior to April 12, 2016 at 3:00 PM. The location is not signed. COGCC staff will meet bidders at the intersection of County Road 22 and the access road to the well. The site is located approximately
1.25 miles east of the intersection of County Road LL and County Road 22, in Yuma County, Colorado.
Bids will not be considered from any contractor that does not attend the pre-bid meeting and site showing. A sign-in sheet will be available at the pre-bid meeting for firms to register their attendance. It is the bidder's responsibility to make certain their attendance is recorded on the sign-in sheet. Failure to sign-in as directed by the PROJECT MANAGER will be cause for rejection of a bid. Bidders are cautioned that, notwithstanding any remarks or clarifications given at this meeting and site showing, all terms and conditions of the contract documents remain unchanged unless they are changed by written amendment issued by the OWNER. If the answers to questions or any amendment to the Contract Documents create ambiguities, it is the responsibility of the bidder to seek clarification prior to submitting a bid.
1.3 BID SUBMITTAL
The bid due date for this project is April 20, 2016 at 45:00 PM. Bids will be accepted by mail, facsimile, hand carried or via e-mail as a Word or Portable Document Format (PDF) file attachment and must be sent to the Department of Natural Resources Purchasing Agent:
Brenda Hannu, Purchasing Agent Department of Natural Resources Purchasing Office 1313 Sherman Street #423 Denver, CO. 80203
Phone: (303) 866-3292 X8625 Fax: (303) 866-5575 Email: Brenda.hannu@state.co.us
A responsive bid must include the following:
BID SCHEDULE, properly completed CONTRACTOR’S Equipment, Personnel and Materials Rate Schedule List of Equipment Offered Form
Bids will not be accepted directly by the COGCC. Bids must be submitted to the Department of Natural Resources Purchasing Office, as indicated above.
1.4 LIST OF EQUIPMENT OFFERED
The List of Equipment Offered Form must be returned with each bid. All equipment to be used on the project must be listed on the form or attached to the form. The CONTRACTOR must own, have a current lease for the equipment intended to be used to perform the work, or must furnish a statement of arrangements to rent, or otherwise procure, adequate equipment to perform the work. Inclusion of a piece of equipment on the List of Equipment Offered represents a commitment to devote that piece of equipment to the project work for the entire duration of the project. If several contractors propose to join together to perform the work under this contract, equipment owned or controlled by each should be listed and the PRINCIPAL REPRESENTATIVE identified. A contract will not be awarded to a bidder who in the opinion of the PROJECT MANAGER (a) does not have adequate equipment, or (b) does not have firm and satisfactory arrangements to obtain adequate equipment to perform the work described in this Documented Quotation.
1.5 BID AWARD
Award will be made with reasonable promptness, by written notice to the low responsive and responsible bidder whose bid meets the requirements and criteria set forth in this Documented Quotation. These criteria will include, but not be limited to the lowest GRAND TOTAL PRICE, corrected if necessary for errors in price extension and/or addition, and capability to meet the performance time requirements. In the case of mathematical discrepancies, the unit price shall govern. The GRAND TOTAL PRICE will be used for comparing bids only.
1.6 RESIDENCE BIDDER PREFERENCE
When a contract for commodities or services is to be awarded to a bidder, a resident bidder shall be allowed a preference against a nonresident bidder equal to the preference given or required by the state in which the nonresident bidder is a resident.
1.7 SERVICE DISABLED VETERAN OWNED SMALL BUSINESSES (SDVOSBs)
PREFERENCE
SDVOSBs, who are incorporated or organized in Colorado or maintain a place of business or have an office in Colorado and who are officially registered and verified as a SDVOSB by the Center for Veteran Enterprise within the U.S. Department of Veterans Affairs.
(www.vip.vetbiz.gov) , may receive a 5% preference on their bid. This preference applies only to the price, and the SDVOSBs must still meet all other qualifications required in the bid.
SDVOSBs claiming this preference shall submit documentation of SDVOSB certification issued through the U.S. Department of Veterans Affairs in their response to the solicitation. Bid submissions without this documentation will not be given a preference.
1.8 PURCHASE ORDER CONTRACT
A Purchase order contract will be issued to the awarded bidder. The Purchase Order Contract will include all documents defined in Section 1 of DEFINITIONS of the GENERAL CONDITIONS
FOR PURCHASE ORDERS.
1.9 PERFORMANCE TIME REQUIREMENTS
The project shall be started and completed between May 20, 2016 and June 10, 2016.
CONTRACTOR shall prosecute the work diligently and complete the work and have equipment removed from the project location, as described in this Documented Quotation, no later than June 10, 2016 at 5:00 PM. The time stated for completion shall include cleanup, as defined in Section 27 of the GENERAL CONDITIONS FOR PURCHASE ORDERS, and final inspection by the
PROJECT MANAGER.
1.10 PROJECT OBSERVATION
The PROJECT MANAGER will be at the project site to supervise plugging activities and ensure that each work item is completed and constructed to design specifications. The PROJECT MANAGER will be available during regular business hours (8:00 A.M. to 5:00 P.M.) on weekdays.
Any additional inspections will not be scheduled on weekend days or holidays without prior approval of the PROJECT MANAGER. It is the CONTRACTOR’S responsibility to schedule inspections with the PROJECT MANAGER so as not to delay the work.
2.0 PROJECT WORK DESCRIPTION
The following work description applies to the plugging and abandonment of the Midfield State #1 well in Yuma County, formerly operated by Midfields Oil Company.
The work assumes use of steel pits for circulation and cement returns. If CONTRACTOR intends to use earthen pits for plugging and abandonment, then pits must be lined, and CONTRACTOR will be responsible for permitting, constructing, maintaining, and closing the plugging pits in accordance with COGCC’s 900-series and 1000-series rules.
Global Positioning System well location data will be measured by COGCC staff.
CONTRACTOR will not be responsible for obtaining this data.
2.1 MIDFIELD STATE #1 WELL
2.1.1 DESCRIPTION
PAD: Midfield State #1
LOCATION: SE1/4 of the NW1/4 of Section 14, Township 2 South, Range 43 West, 6th P.M., Yuma County.
WELL: Midfield State #1, API No. 05-125-05051 STATUS: Well drilled, cased, cemented, and abandoned
WELL SUMMARY:
• Vertical well
• Spud in January, 1919
• 16” PVC conductor pipe, uncemented, installed in 2009 by
COGCC.
• 16” surface casing to 120’, unknown cement coverage
• 12-1/2” casing to 1002’ with unknown cement coverage
• 10” casing to 1582’ with unknown cement coverage
• 8-1/2” casing to 2530 with unknown cement coverage
• Total Measured Depth (TMD) = 3650’
OTHER NOTES:
• Well is full of water with gas bubbling up through the water.
2.1.2 MATERIALS
Refer to Section 3.0 – Measurement and Payment.
2.1.3 EXECUTION
1. Contact Steve Jenkins, North Central Area Engineer, to schedule a start date and to coordinate any schedule changes.
2. MIRU.
3. Excavate a small cellar to contain water from well, have Vac truck accessible to remove fluids that come out of the wellbore from the plugging operations.
4. TIH with 2-3/8” tubing to a depth of approximately 1500’. Pump 50 sack plug, WOC 4 hours and tag cement. Note if gas bubbling has subsided.
5. If gas has slowed or stopped install another 50 sack plug directly above the previous plug, WOC 4 hours and tag plug, note if gas migration has stopped.
6. If gas has slowed or stopped install another 50 sack plug at approximately 1000’, WOC 4 hours and tag plug, note if gas migration has stopped.
7. If the above cannot be accomplished, then discuss procedural changes with COGCC Project Engineer. Any procedural changes would require a Change Order.
8. If gas has stopped. TOOH to 200’, fill casing with cement to top of casing, WOC.
Top off, if cement top falls below a depth of 4’ below top of existing wood casing.
9. Fill well cellar. With clean fill dirt.
10. RDMO drill rig and CONTRACTOR equipment.
11. Reclaim pad and any other disturbed areas.
3.0 MEASUREMENT AND PAYMENT
CONTRACTOR shall furnish all labor, materials, tools, equipment, appurtenances, incidentals and all services necessary to perform all work required at the lump sum or unit prices for the items listed below beginning in Section 3.1. These items refer to and are the same items as listed in the Bid Schedule. They constitute all of the pay items for the completion of the work. Each lump sum and unit price bid will be deemed to include an amount considered by CONTRACTOR to be adequate to cover CONTRACTOR’S overhead and profit for each separately identified item.
Quantities of work shall be measured in the field by the CONTRACTOR and verified by the PROJECT MANAGER. CONTRACTOR’S original daily job logs, field notes, computations, and other records for the purpose of measuring quantities shall be furnished to the PROJECT MANAGER within two (2) working days of completion and may be used by the PROJECT MANAGER to the extent necessary in determining the proper amount of payments due to the CONTRACTOR. The CONTRACTOR shall retain a copy of the daily job logs, original notes, computations, and records furnished to the PROJECT MANAGER.
CONTRACTOR’S daily job logs shall include accurate records of the daily progress of the work and shall record the progress on a format acceptable to PROJECT MANAGER. Daily job logs shall include at a minimum the following information:
1. CONTRACTOR name, project name, date of field work
2. Identify by individual, all CONTRACTOR and SUBCONTRACTOR personnel on-Site for the day.
3. Summarize the work completed, including plugging procedures, and the materials used.
4. List the major equipment used to complete the work.
5. Provide an hourly tally for time on-location, including a separate hourly tally for any standby time.
6. Identify all standby time including but not limited to; repairs or maintenance, breakdown, accidents, time spent waiting-on-cement and work stoppage directed by PROJECT MANAGER or OWNER.
7. CONTRACTOR’S superintendent shall sign the completed daily job log upon completion.
Applications for Payment shall be submitted to the PROJECT MANAGER for review and approval at least five (5) working days prior to final submission to OWNER.
Payment will be made for actual quantities at the unit prices listed on the Bid Schedule only when approved and verified by the PROJECT MANAGER. If a change order is approved, which includes work for items not listed in this section, then unit costs listed on CONTRACTOR’S Rate Schedule will be considered by the PROJECT MANAGER when authorizing payment.
3.1 MOBILIZATION/DEMOBILIZATION
3.1.1 DESCRIPTION
This specification covers the CONTRACTOR'S operations for:
1. Payment of premiums for bonds and insurance acquired specifically for this project, including premiums for performance and payment bonds, if any.
2. Obtaining and acquiring any permits necessary to complete this project.
3. Movement of CONTRACTOR'S personnel, equipment, operation supplies, and incidentals to the project site.
4. Establishment of necessary temporary facilities, including sanitation facilities, and any required temporary utilities, at the project site.
5. Preparatory work at the project sites.
6. Demobilization of CONTRACTOR'S equipment and all other facilities, final project clean-up.
7. Any travel time and per diem for CONTRACTOR’S crew or SUBCONTRACTOR’S crew.
3.1.2 EXECUTION
Upon receipt of Notice to Proceed, the CONTRACTOR shall furnish, mobilize, move in and install such temporary works and equipment necessary for the successful completion of the work. CONTRACTOR shall operate and maintain such temporary works and equipment for the duration of work at each project location. CONTRACTOR shall provide for movement of CONTRACTOR’S personnel and supplies to and from each project location on a daily basis. CONTRACTOR shall consider daily lodging and/or meals per diem for the entire project with this bid item. A Change Order for additional per diem may be considered by the PROJECT MANAGER if the actual Plug and Abandon hourly quantity (Section 3.2) exceeds the estimated Plug and Abandon quantity shown on the Bid Schedule by more than twenty (20) percent. Any preparatory work at each project location necessary to move in and position CONTRACTOR’S equipment shall be included as mobilization.
Upon completion of the work under this contract, the CONTRACTOR shall remove all temporary facilities and equipment. The CONTRACTOR shall remove from the vicinity of the work and haul all rubbish, trash, garbage, and debris to a county-approved disposal site. Additionally, the CONTRACTOR shall remove from the vicinity all unused materials, and the like, belonging to the CONTRACTOR or used under the CONTRACTOR'S direction during construction. The contractor shall fill and dress all holes and disturbances made for convenience, and leave all areas in good order and condition, subject to final inspection and approval by the PROJECT MANAGER.
3.1.3 MEASUREMENT AND PAYMENT
Measurement shall be made based on mobilization to and demobilization from the project location or this bid item. Payment at the bid price shall constitute full compensation for all of the CONTRACTOR’S costs of whatever nature to mobilize to and demobilize from the project location.
3.2 PLUG AND ABANDON
3.2.1 DESCRIPTION
This specification covers the CONTRACTOR’S time on-location for labor and equipment required to complete the work specified in Section 2.0 – Project Work Description. Hourly unit costs shall include all costs that the CONTRACTOR deems necessary to complete the work for which payment is not otherwise specifically itemized on the Bid Schedule.
Materials used to complete the work are described in subsequent sections of this Documented Quotation, and therefore are not itemized in this section.
The CONTRACTOR shall provide the following minimum personnel, equipment, and services:
• Provide a Superintendent with whom the PROJECT MANAGER and OWNER can communicate and who will supervise the work and be fully responsible for the performance thereof. The Superintendent shall be present at the project site whenever work is being performed at the project site.
• Provide an experienced crew sufficient to operate CONTRACTOR’S equipment in a safe and diligent manner.
• Provide work over rig with tubing handling tools. Provide the tubing work string. Provide pumps, a power swivel and drill bit(s). Provide drilling fluid additives, and mixing equipment.
• Provide sufficient fresh water to kill the well, pressure test and circulate the well
• Provide two (2) steel pits for drilling fluids, circulated fluid and wash up fluid. Separate payment will not be approved for the installation, monitoring, maintenance, closure, and reclamation of earthen pits. If CONTRACTOR chooses to use a lined earthen pit, rather than a steel pit, then all associated costs for the plugging pit shall be incorporated into the unit cost for this bid item.
• Provide welder services and materials necessary to cut casing strings and weld plates.
Any additional equipment or services that the contractor deems necessary to complete the work specified in Section 2.0 – Project Work Description shall be included in the CONTRACTOR’S List of Equipment Offered, and if these equipment or services are used to complete the work, then the cost for these services shall be incidental to the hourly unit cost for the Plug and Abandon line item on the Bid Schedule.
Daily travel time to and from: 1) CONTRACTOR’S yard/office and the well site location or
2) a lodging location chosen by the CONTRACTOR and the well site is not considered hourly time under this bid item. All crew travel time should be considered with the Mobilization/Demobilization bid item (Section 3.1).
3.2.2 EXECUTION
Refer to Section 2.0 – Project Work Description.
3.2.3 MEASUREMENT AND PAYMENT
The CONTRACTOR shall submit daily job logs to the PROJECT MANAGER to verify hourly quantities for plug and abandon labor, equipment and services for time on location.
Payment will be based on the total number of hours listed on the daily job logs and verified by the PROJECT MANAGER at the bid price, except as noted below. Standby time will be paid at a unit rate equal to seventy-five (75) percent of the bid price for hourly time. Daily travel time and per diem will not be considered as hourly time with this bid item. Payment shall constitute full compensation for all of the CONTRACTOR’S costs of whatever nature to plug and abandon the well.
3.3 CEMENT SERVICES
3.3.1 DESCRIPTION
The CONTRACTOR shall provide cement services, and two hundred and fifty (250) sacks of cement mixed with sufficient water to achieve a density of 15.8 ppg and a yield of 1.15 cu ft yield per sack. The CONTRACTOR shall provide water on location in sufficient quantities to circulate the wellbore and mix the cement. The CONTRACTOR shall also provide a means to transport water to and store water on location.
Cement plugs shall be installed by the CONTRACTOR at various depths, as described in Section 2.0 – Project Work Description. Cement shall be Southwest Portland G common cement without additives. Any changes in the type of cement must be approved by the PROJECT MANAGER. Cement shall be mixed to American Petroleum Institute standards, such that the slurry design will achieve a minimum compressive strength of three hundred
(300) psi after twenty-four (24) hours and eight hundred (800) psi after seventy-two (72) hours measured at ninety-five (95) degrees Fahrenheit and at eight hundred (800) psi.
3.3.2 EXECUTION
3.3.3 MEASUREMENT AND PAYMENT
The CONTRACTOR shall submit daily job logs to the PROJECT MANAGER to verify cement quantities. Cement shall be measured by 94-pound sacks. Payment will be based on the total sacks of cement installed, as listed on the daily job logs and verified by the
PROJECT MANAGER at the bid price. Payment shall constitute full compensation for all of the CONTRACTOR’S costs of whatever nature for cement services, including water.
Water used for circulating and mixing cement shall be considered incidental to the unit cost for cement services.
3.4 SOLID WASTE MANAGEMENT
3.4.1 DESCRIPTION
All solid materials, including materials that solidify from circulated wellbore fluids, or solids that come in contact with wellbore fluids shall be considered oil and gas exploration and production (E&P) solid waste. The CONTRACTOR shall provide a means to temporarily store E&P solid waste on site, and the storage process shall be designed such that the E&P waste shall not come in contact with native soils, surface water, or well pad fill. The CONTRACTOR shall provide a means to handle and transport E&P solid waste to a licensed off-site disposal facility.
3.4.2 EXECUTION
3.4.3 MEASUREMENT AND PAYMENT
Measurement will be based upon 100% completion of solids storage, handling, transportation, and disposal. CONTRACTOR shall provide a disposal certificate from a county-approved disposal facility to the PROJECT MANAGER for solids disposal. Lump sum payment at the bid price shall constitute full compensation for all of the CONTRACTOR’S costs of whatever nature to complete solid waste management.
3.5 LIQUID WASTE MANAGEMENT
3.5.1 DESCRIPTION
All liquids that are circulated from the wellbore shall be considered oil and gas E&P liquid waste. The CONTRACTOR shall provide a means to temporarily store E&P liquid waste on site, and the storage process shall be designed such that the E&P waste shall not come in contact with native soils, surface water, or well pad fill. The CONTRACTOR shall provide a means to handle and transport E&P liquid waste to a licensed off-site disposal facility.
Disposal of any unused circulation fluid is also covered under this item.
3.5.2 EXECUTION
3.5.3 MEASUREMENT AND PAYMENT
Measurement will be per load (up to 130 barrels for each load) of liquids disposal.
CONTRACTOR shall provide a disposal certificate from an approved E&P disposal facility to the PROJECT MANAGER for solids disposal. Payment will be based on the total loads of liquid disposed, as listed on the daily job logs and verified by the PROJECT MANAGER at the bid price. Payment shall constitute full compensation for all of the CONTRACTOR’S costs of whatever nature for E&P liquid disposal.
4.0 LIST OF ATTACHMENTS
DNR General Terms and Conditions for Construction Special Provisions PO Terms and Conditions Bid Schedule List of Equipment Offered Wellbore Diagram – Existing and Proposed Map-pre bid meeting on site meet up location
| 1.2 PRE-BID MEETING AND SITE SHOWING |
| Phone: (303) 866-3292 X8625 |
| 1.9 PERFORMANCE TIME REQUIREMENTS |
| The PROJECT MANAGER will be at the project site to supervise plugging activities and ensure that each work item is completed and constructed to design specifications. The PROJECT MANAGER will be available during regular business hours (8:00 A.M. to 5... |