DOT-RFP-27-6203LS - Addendum #1.pdf

PDF 53 KB Posted

Attached to
Districtwide Public Strategic Communications Consulting Services on Misc Construction Projects FDOT
Solicitation number
RFP-17161
Issued by
Miami-Dade County, Florida

About this file

This addendum to Request for Proposal DOT-RFP-27-6203LS issued by the Florida Department of Transportation, District Six, modifies key dates and requirements for districtwide public strategic communications consulting services on miscellaneous construction projects in Miami-Dade County. The Final Selection Meeting and Posting of Intended Award have been rescheduled to January 11, 2027, at 10:00 AM in the District Auditorium, and the maximum number of attendees permitted for the oral presentation has been revised to seven individuals. Technical proposals remain due October 28, 2026, at 10:00 AM. The contract is structured as an indefinite-quantity agreement with a three-year base term (January 2027 through January 2030) and options for up to three additional one-year renewals. Required staffing includes a Strategic Communications Project Manager (minimum 20% availability), a Construction Crisis Communications Manager, and a Senior Community Outreach Specialist (100% availability), with the latter assigned full-time (Monday through Friday, 8:00 AM to 5:00 PM) to the SR 907/Alton Road project scheduled from April 5, 2027, through July 17, 2030.

Compensation is based on hourly billing rates within Department-established ranges: Strategic Communications Project Manager and Construction Crisis Communications Manager at $93.00–$98.00 per hour; Senior Community Outreach Specialist at $83.00–$98.00; Community Outreach Specialist at $78.00–$83.00; Assistant Community Outreach Specialist at $48.00–$53.00; Audio/Visual Technician/Videographer/Editor/Social Media Specialist at $68.00–$73.00; and Graphic Designer at $53.00–$58.00. All rates are all-inclusive with no escalations permitted for renewal years or annual adjustments. The Department will cover pre-approved reimbursable expenses including printing, paid social and digital advertising, event venues, signage, giveaways, and audiovisual rentals but does not provide funds for mileage, tolls, parking, or fuel. The incumbent contractor is HML; however, this is classified as a new contract with no staff transition. No set-asides for disadvantaged business enterprises, minority-owned businesses, or small businesses apply. The contract maximum ceiling is $1.5 million with $400,000 currently approved and encumbered. All proposers must maintain an operational office in Miami-Dade, Monroe, or Broward County and register in MyFloridaMarketPlace prior to proposal submission.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Transportation

RON DESANTIS

GOVERNOR

1000 N.W. 111 Avenue Miami, Florida 33172

JARED W. PERDUE, P.E.

SECRETARY

www.fdot.gov | www.fdotmiamidade.com

ADDENDUM NO. 1

DATE: October 05, 2026

TO: PROPOSERS

FROM: Ileen Zamora, Supervisor, Procurement Office, District Six

REF: Questions received from Prospective Proposers and Department responses

Advertisement No.: DOT-RFP-27-6203LS

Financial Project No.: 434868-6-62-01

Counties: Miami-Dade

Work Description: Districtwide Public Strategic Communications Consulting Services on Miscellaneous Construction Projects for the Florida Department of Transportation

(FDOT)

I. The date for the Final Selection Meeting and Posting of Intended Award was changed.

The new date for the Final Selection meeting is January 11, 2027, at 10:00am in the

District Auditorium. The Posting of Intended Award will be January 11, 2027. The Request for Proposal has been updated to reflect the change.

II. Section 28.2 of the Request for Proposal has a revision. The total maximum number of attendees required for the Oral Presentation has been changed to seven (7).

III. QUESTIONS AND ANSWERS TO THE REQUEST FOR PROPOSAL

Question 1: For the Strategic Communications Project Manager prerequisite in Exhibit A, please clarify whether experience managing communications/outreach, staff, budgets and tasks for Intelligent

Transportation Systems (ITS) projects qualifies as “managing outreach efforts of other staff members handling transportation outreach efforts,” provided the proposer documents at least five years of that experience and the individual’s specific responsibilities.

Answer 1: It is preferred that in addition to what is stated, the candidate has a few years of outreach experience with a high-profile projects. Some examples are the Golden Glades Interchange, I-395, Okeechobee or the SW 8 Street bridge. The chosen person should have a more traditional transportation communication experience.

Question 2: The RFP states that oral presentation attendance is limited to a “maximum of five (7) members,” then identifies seven required classifications and also states that one additional attendee/presenter may be included. Please clarify the maximum number of attendees permitted at the oral presentation and whether all seven listed classifications are required to attend.

www.fdot.gov | www.fdotmiamidade.com

Answer 2: Seven is the limit. It is necessary for all classifications to attend.

Question 3: Does the contract require a locally based team or specified onsite staffing?

Answer 3: The vendor must be locally based team.

Question 4: Exhibit A, Staffing, states that the Project Manager cannot be a subconsultant. May the

Senior Community Outreach Specialist (100% availability on the S.R. 907/Alton Road project) and the

Construction Crisis Communications Manager be provided by a subconsultant?

Answer 4: Yes.

Question 5: For the trilingual (English/Spanish/Creole) preference for the Senior Community Outreach

Specialist, and the requirement that materials be prepared in all three languages, may the language capability be met across several team members rather than by one individual?

Answer 5: Yes.

Question 6: The prime must have an office in Miami-Dade, Monroe, or Broward County. Must subconsultant firms also have an office in those counties, or is it enough that their assigned outreach staff are stationed locally?

Answer 6: Subconsultant may work remotely.

Question 7: Exhibit C's Grand Total is used for price scoring, but no estimated hours are shown. Is the

Grand Total the unweighted sum of the seven hourly rates, or will the Department apply estimated hours per classification?

Answer 7: Hours are estimated per Task Work Order. Strategic Communications Project Manager must provide a minimum of 20% availability.

Question 8: Does this contract carry a DBE, MBE, or small business participation goal, or any evaluation credit for certified minority-owned subconsultants?

Answer 8: There is no DBE, MBE or Small Business requirement for this contract.

Question 9: How many consultants does the Department expect to award, and what is the expected split of hours across classifications in year one beyond the full-time Senior Community Outreach Specialist on

S.R. 907/Alton Road?

Answer 9: One consultant firm will be chosen.

Question 10: Are the Table-1 rate ranges fixed for the full term? The base term is 3 years plus up to three 1-year renewals. Are escalations or annual adjustments allowed in renewal years, given "costs for renewal may not be charged" in the Standard Agreement?

Answer 10: No. The base term is final. There are no escalation or annual adjustments.

Question 11: Is the all-inclusive rate truly all-inclusive? Please confirm there are no reimbursables, including mileage, tolls, parking, translation or interpreting vendors, printing, paid social/digital ad spend, event venues, signage, giveaways, and AV rentals. If any are pass-through, how are they billed and approved?

Answer 11: The Department does not provide monetary funds for mileage, tolls, parking, or fuel.

Printing, paid social/digital ad spending, event venues, signage, giveaways and AV rentals will be covered by the Department as long as it pertains to the project. It must be pre-approved by the

Project Manager.

Question 12: Are overtime, evening/weekend event hours, and on-call or standby time billable, and at what rate? Definitions say offsetting hours "may be required," which suggests they are not.

Answer 12: Overtime, evening/weekend event hours, on-call or standby time is not billable, but the hours maybe offset.

Question 13: Can a flat rate at the top or bottom of a range be proposed? Are rates outside the range always non-responsive?

Answer 13: Anything outside of the rate range from within the table in Exhibit C will be found Non-

Responsive.

Question 14: Can one person be proposed in the Crisis Communications Manager / Senior Community

Outreach Specialist "duo role"? If so, does that person need 100% availability, and how does that affect the org chart and resume requirements?

Answer 14: Yes. Person needs to meet requirement per position as mentioned in the position description in the scope of work.

Question 15: What does "100% availability" mean for the Senior Community Outreach Specialist? Is the person dedicated full-time (M-F, 8-5) and billed only for hours worked, or must they be physically stationed somewhere? Please confirm the work location: the Alton Road project is in Miami Beach and the District Six Construction office is in Doral.

Answer 15: The person is expected to work M-F 8 a.m. to 5 p.m. Consultant firm can bill for hours worked. An office will be stationed near the project in Miami Beach, and the chosen Senior

Community Outreach Specialist is expected to be present at the office. There may be some occasions where the person may work remotely.

Question 16: Is trilingual (English/Spanish/Creole) required or only "strongly desired" for the Senior

Outreach Specialist? The Community Outreach Specialist description reads as a requirement. Does it apply to any other positions?

Answer 16: The Senior Community Outreach Specialist is required to speak and write in English and Spanish. Creole translations can be provided by an additional team member or outside vendor is needed.

Question 17: Who is the incumbent, and what are historical hours and spend by classification? Is this a re-procurement, and will there be a transition from current staff?

Answer 17: HML is the incumbent. The hours are minimum 20 % availability from the Strategic

Communications Project Manager and 100% availability from the Senior Community Outreach

Specialist for this contract. There will be no transition from current staff. This is not a re-procurement. It is a new contract.

Question 18: Can the Department share details on the SR 907/Alton Road project (429193-1)? Useful details include construction start and end dates, phasing, and the current stakeholder and communications baseline.

Answer 18: Project starts April 5, 2027, with a last date allowed date of July 17, 2030. Please make a formal public request for outreach communication items. The Consultant firm should be well versed in Miami Beach prior to contending for the contract.

Question 19: How will work be distributed among multiple awardees? The Department may award to more than one consultant. Is it rotation, competitive quotes per Task Work Order, or Department discretion? How many awards are anticipated?

Answer 19: The Department will award only one consulting firm.

Question 20: What are the on-call and emergency expectations? Is Crisis Communications 24/7? Do the

1-hour phone and 2-hour on-site response times apply 24/7, and to which positions? What is expected during hurricane activations?

Answer 20: On-call and emergency expectations may occur on an as needed basis. The time used maybe offset, but it will not be paid additionally.

Question 21: Does the Department have a policy on AI tools (e.g., ChatGPT) for content creation, given they are named in the A/V position description?

Answer 21: FDOT’s Artificial Intelligence Policy establishes standards for responsible AI use, emphasizing human oversight, transparency, privacy, and security while enabling innovation across transportation operations.

Question 22: Which "annual mandatory training" is required, how long is it, and is the time billable?

Answer 22: Mandatory training in Fire safety and Cyber Security is required. It is not billable.

Question 23: Is DOT-RFP-27-6203LS intended to supplement, replace, or operate concurrently with

DOT-RFP-26-6198LS?

Answer 23: DOT-RFP-27-6203LS replaces DOT-RFP-21-6175LZ.

Question 24: How many active District Six strategic communications consulting contracts currently exist, and what are their expiration dates?

Answer 24: Construction has seven contracts.

BEB06- Expires 10/12/2027

BEG33-Expires 10/26/2028

BE329-Expires 9/22/2027

BEC61-Expires-4/25/2027

BEK58-Expires-5/28/2029

BEG89-Expires 9/12/2027

BEJ94- Expires 2/2/2031

Question 25: Are there transportation-specific past-performance minimums for the prime contractor, or can comparable public outreach and communications experience qualify?

Answer 25: Comparable public outreach and communications experience may qualify.

Question 26: Are media buying, radio advertising, community publication placements, and multilingual outreach allowable billable activities under this contract?

Answer 26: Yes.

Question 27: Are specialized subcontractors permitted, and what approvals or limitations apply?

Answer 27: Yes. they must be approved by the Project Manager.

Question 28: Does FDOT anticipate issuing task orders that separately address community outreach and public awareness, rather than full-service communications management?

Answer 28: Yes. Task Work Orders will be issued.

All other documents of the subject project remain unchanged.

Failure to file a Protest within the time prescribed in Section 120.57(3), Florida Statutes, or failure to post the bond or other security required by law within the time allowed for filing a bond shall constitute a waiver of proceedings under Chapter 120, Florida Statutes.

File details come from the government source that posted it. Updated .