STATEMENT OF WORK

1279 & 1280 (HANGAR 6 & 7) ENTRY/EXIT DOOR PROJECT

PEDESTRIAN DOOR REPLACEMENT, HANGAR 6 & 7, BLDG 1279 &1280

5 May 2021

STATEMENT OF OBJECTIVES: Provide all necessary work to remove the current doors and frames, prepare the area for new frame, install new frame, and install new doors and all required hardware. Provide warranty for door installation and components for one (1) year.

GENERAL: Provide all supervision, plant labor, transportation, equipment, and materials and perform all necessary engineering and operations to accomplish the following.

Furnish and Install BLDG 1279:

• Furnish and install one (1) 16 Ga. Steel Frame with concrete fill in existing location.

• Frame is to be painted matched to existing, brown on the exterior and dark blue on the interior.

• Furnish and installs six (6) stainless steel commercial hinges.

• Furnish and install (2) heavy duty strikes.

• Furnish and install two (2) 18 Ga. metal doors with half view wired glass

• Furnish and install one (1) threshold.

• One (1) 36” x 6’8” Door with, one (1) heavy duty door closer, one (1) bottom sweep, one (1) astragal, and one (1) weather stripping.

• Furnish and install one (1) 36” panic bar with double cylinder deadbolt indicator.

• One (1) 24” x 6’8” Door with two (2) flush bolts, one (1) bottom sweep, and one (1) weather stripping.

• Doors will be paint matched to existing, brown on the exterior and dark blue on the interior.

• Furnish and install eight (8) bolts.

• Furnish and install all required fasteners.

Remove and Demolish BLDG 1279:

• Existing door(s) to be taken down, removed from site and disposed of in accordance with local laws

• Existing frame(s) to be taken down, removed from site and disposed of in accordance with local laws

• Existing hardware to be taken down, removed from site and disposed of in accordance with local laws.

Furnish and Install BLDG 1280:

• Furnish and install one (1) 16 Ga. Steel Frame with concrete fill in existing location.

• Frame is to be painted matched to existing, brown on the exterior and dark blue on the interior.

STATEMENT OF WORK

1279 & 1280 (HANGAR 6 & 7) ENTRY/EXIT DOOR PROJECT

PEDESTRIAN DOOR REPLACEMENT, HANGAR 6 & 7, BLDG 1279 &1280

5 May 2021

• Furnish and installs six (6) stainless steel commercial hinges.

• Furnish and install (2) heavy duty strikes.

• Furnish and install two (2) 18 Ga. metal doors with half view wired glass

• Furnish and install one (1) threshold.

• One (1) 36” x 6’8” Door with, one (1) heavy duty door closer, one (1) bottom sweep, one (1) astragal, and one (1) weather stripping.

• Furnish and install one (1) 36” panic bar with double cylinder deadbolt indicator.

• One (1) 24” x 6’8” Door with two (2) flush bolts, one (1) bottom sweep, and one (1) weather stripping.

• Doors will be paint matched to existing, brown on the exterior and dark blue on the interior.

• Furnish and install eight (8) bolts.

• Furnish and install all required fasteners.

Remove and Demolish BLDG 1280:

• Existing door(s) to be taken down, removed from site and disposed of in accordance with local laws

• Existing frame(s) to be taken down, removed from site and disposed of in accordance with local laws

• Existing hardware to be taken down, removed from site and disposed of in accordance with local laws.