DOME WBS for Schedule Application 09Apr25.xlsx
XLSX spreadsheet 18 KB Posted
- Attached to
- Application to Test in the NRIC DOME Facility
- Solicitation number
- INL-NOO01
- Issued by
-
Department of Energy
About this file
The file is a Work Breakdown Structure (WBS) for the National Reactor Innovation Center's Demonstration of Microreactor Experiments (NRIC-DOME) facility, detailing a comprehensive project lifecycle from reactor design through post-experiment decommissioning. The WBS includes four primary levels of project activities spanning reactor ecosystem development, including reactor design and fabrication, safety authorization, quality assurance, installation, operational transition, readiness, operations, and post-experiment decommissioning.
The associated federal contract opportunity is a Special Notice from the Department of Energy inviting U.S. companies to apply for testing advanced reactors in the DOME facility at Idaho National Laboratory. Key details include: application deadline of June 19, 2025, facility capabilities for testing reactors up to 20MWth using less than 20% enriched fuel, self-funded testing opportunity, and a selection process evaluating applications across categories such as reactor technology maturity, fuel management, testing plans, project scheduling, DOE authorization, and organizational capabilities. Applicants must be U.S.-owned companies or meet specific DOE ownership criteria, with testing availability beginning fall 2026.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| GDE-55115 Rev 1 Dome Scheduling Application.pdf | ||
| GDE-55115 Rev 1 Dome Scheduling Application.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| WBS Level | WBS Description |
| 1 | NRIC DOME Ecosystem |
| 2 | Reactor Experiment |
| 3 | Reactor Design & Fabrication |
| 4 | Reactor Conceptual Design |
| 4 | Reactor Preliminary Design |
| 4 | Reactor Final Design |
| 4 | Final Reactor Design & Data Transmittal to INL |
| 4 | Reactor Fabrication |
| 3 | Safety Authorization (Reactor) |
| 4 | Reactor SDS |
| 4 | Reactor CSDR |
| 4 | Confirmatory Reactor Analysis (INL Performed) |
| 4 | Reactor PDSA |
| 4 | Reactor DSA |
| 3 | Quality Assurance |
| 4 | Developer NQA-1 Program (on INL QSL) |
| 4 | Quality Assurance Plan |
| 3 | Reactor Installation |
| 4 | Receipt & Inspection |
| 4 | Reactor Installation |
| 4 | Reactor Installation Acceptance Commissioning and Testing |
| 4 | Reactor Turnover to Operations |
| 3 | Fresh Fuel Management |
| 4 | Fresh Fuel Fabrication |
| 4 | Fresh Fuel Transportation |
| 4 | Fresh Fuel Receipt and Storage |
| 2 | DOME Operational Transition, Readiness and Operations |
| 3 | DOME Operational Transition |
| 4 | RHS Support During Operations |
| 3 | DOME + Reactor Operational Transition |
| 4 | Reactor-Integrated O&M Procedures |
| 4 | Reactor-Integrated Systems Training |
| 4 | Reactor-Integrated Operations Procedures & OJT |
| 4 | Reactor-Integrated Abnormal Operations Procedures OJT |
| 3 | DOME Readiness |
| 4 | DSA Implementation |
| 4 | MSA (DOME + Reactor) |
| 4 | Contractor Readiness Review (DOME + Reactor) |
| 4 | DOE Readiness Review (DOME + Reactor) |
| 3 | DOME Operations |
| 4 | Reactor Fueling |
| 4 | Reactor Startup |
| 4 | Reactor Operations & Maintenance |
| 2 | Post Experiment Decommissioning |
| 3 | Irradiated Fuel Management |
| 4 | Irradiated Fuel Storage Requirements |
| 4 | Irradiated Fuel Storage Design |
| 4 | Irradiated Fuel Storage Equipment Fabrication |
| 4 | Irradiated Fuel Storage |
| 3 | DOME Post Operations Decommissioning |
| 4 | Decommissioning Plan for Reactor |
| 4 | PIE Plan for DOME Reactor |
| 4 | Final Waste Management Plan |
| 4 | Shield Removal Equipment |
| 4 | Reactor Cooldown in DOME |
| 4 | Reactor Disconnection from DOME |
| 4 | Shield Removal |
| 4 | Reactor Removal from DOME |
| 4 | Transport and Storage at RSWF |
| 4 | Defueling |
| 4 | PIE Sampling |
File details come from the government source that posted it. Updated .