DOME WBS for Schedule Application 09Apr25.xlsx

XLSX spreadsheet 18 KB Posted

Attached to
Application to Test in the NRIC DOME Facility
Solicitation number
INL-NOO01
Issued by

About this file

The file is a Work Breakdown Structure (WBS) for the National Reactor Innovation Center's Demonstration of Microreactor Experiments (NRIC-DOME) facility, detailing a comprehensive project lifecycle from reactor design through post-experiment decommissioning. The WBS includes four primary levels of project activities spanning reactor ecosystem development, including reactor design and fabrication, safety authorization, quality assurance, installation, operational transition, readiness, operations, and post-experiment decommissioning.

The associated federal contract opportunity is a Special Notice from the Department of Energy inviting U.S. companies to apply for testing advanced reactors in the DOME facility at Idaho National Laboratory. Key details include: application deadline of June 19, 2025, facility capabilities for testing reactors up to 20MWth using less than 20% enriched fuel, self-funded testing opportunity, and a selection process evaluating applications across categories such as reactor technology maturity, fuel management, testing plans, project scheduling, DOE authorization, and organizational capabilities. Applicants must be U.S.-owned companies or meet specific DOE ownership criteria, with testing availability beginning fall 2026.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

WBS LevelWBS Description
1NRIC DOME Ecosystem
2Reactor Experiment
3Reactor Design & Fabrication
4Reactor Conceptual Design
4Reactor Preliminary Design
4Reactor Final Design
4Final Reactor Design & Data Transmittal to INL
4Reactor Fabrication
3Safety Authorization (Reactor)
4Reactor SDS
4Reactor CSDR
4Confirmatory Reactor Analysis (INL Performed)
4Reactor PDSA
4Reactor DSA
3Quality Assurance
4Developer NQA-1 Program (on INL QSL)
4Quality Assurance Plan
3Reactor Installation
4Receipt & Inspection
4Reactor Installation
4Reactor Installation Acceptance Commissioning and Testing
4Reactor Turnover to Operations
3Fresh Fuel Management
4Fresh Fuel Fabrication
4Fresh Fuel Transportation
4Fresh Fuel Receipt and Storage
2DOME Operational Transition, Readiness and Operations
3DOME Operational Transition
4RHS Support During Operations
3DOME + Reactor Operational Transition
4Reactor-Integrated O&M Procedures
4Reactor-Integrated Systems Training
4Reactor-Integrated Operations Procedures & OJT
4Reactor-Integrated Abnormal Operations Procedures OJT
3DOME Readiness
4DSA Implementation
4MSA (DOME + Reactor)
4Contractor Readiness Review (DOME + Reactor)
4DOE Readiness Review (DOME + Reactor)
3DOME Operations
4Reactor Fueling
4Reactor Startup
4Reactor Operations & Maintenance
2Post Experiment Decommissioning
3Irradiated Fuel Management
4Irradiated Fuel Storage Requirements
4Irradiated Fuel Storage Design
4Irradiated Fuel Storage Equipment Fabrication
4Irradiated Fuel Storage
3DOME Post Operations Decommissioning
4Decommissioning Plan for Reactor
4PIE Plan for DOME Reactor
4Final Waste Management Plan
4Shield Removal Equipment
4Reactor Cooldown in DOME
4Reactor Disconnection from DOME
4Shield Removal
4Reactor Removal from DOME
4Transport and Storage at RSWF
4Defueling
4PIE Sampling