Gulfport SF30 Amendment 1 to RFP J09UA00024 7-31-08.doc

DOC document 150 KB Posted

Attached to
Operation Of The Gulfport Job Corps Center
Solicitation number
DOLJ09UA00024
Issued by

About this file

Gulfport Job Corps Center Amendment 1 to RFP J09UA00024

View the file

Other files

File Type Posted
GULFPORT JCC RFP - Center 7-10-08 Final for posting.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

J09UA00024 GULFPORT JCC

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE
PAGE OF PAGES

2. AMENDMENT/MODIFICATION NO.

Amendment 01

3. EFFECTIVE DATE

See Block 16C

4. REQUISITION/PURCHASE REQ. NO.
5. PROJECT NO. (If applicable)

6. ISSUED BY

CODE

U.S. Department of Labor

Office of Assistant Secretary For Administration and Management(OASAM) 61 Forsyth Street, SW, Room 6B36 Atlanta, Georgia 30303

7. ADMINISTERED BY (If other than Item 6)

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

POTENTIAL OFFERORS - FOR GULFPORT JOB CORPS CENTER - JOB CORPS PROGRAM

9A. AMENDMENT OF SOLICITATION NO.

J09UA00024

9B. DATED (SEE ITEM 11)

July 31, 2008

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE
FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

x The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers __ is extended X is not extended

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning ________ copies of the amendment; X (b) by acknowledging receipt of this amendment on each copy of the offer submitted; or (c) by separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATE (If required)

13.

THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

( )
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office)ADVANCE \x46 SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. ADVANCE \x46THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. ADVANCE \x46OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor X is not,__is required to sign this document and return N/A copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

1. This amendment is issued to amend the RFP, provide potential offerors the questions and responses and other pertinent information from the Pre-Proposal conference held July 17, 2008. All potential offerors not in attendance at the Pre-proposal conference who require copies of the attachments, to this amendment must request this information in writing to the contracting officer.

Remove

Replace Comments

Section L.7, 5a, 9. G.7 N/A The reference to contractors proposing a fee for invalid placements is not applicable and no longer a requirement. Section G-G.6 Liquidated Damages for Placements Found to be

Invalid establishes the fee for invalid placements.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or Print)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

LYNN D. OWENS, Contracting Officer

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. Date Signed
16B. UNITED STATES OF AMERICA

BY ______________________________________________

(Signature of Contracting Officer) 16C.Date Signed

NSN 7540-01-152-8070

30-105

STANDARD FORM 30 (REV. 10-83)

PREVIOUS EDITION UNUSABLE

Prescribed by GSA -FAR (48 CFR) 53.243

2. The government brought the following to the attention of the attendees:

· Please refer to the RFP for the exact format needed for submitting proposals.

· All related procurement activities are administered by the Office of Assistant Secretary for Administration and Management (OASAM) on behalf of the Office of Job Corps.

· Proposals are to be delivered at the address indicated on the SF-33; cover of the solicitation and not to the Regional Office of Job Corps.

Questions

1
Reference Section L.7.B.5.a.9, Page 131: This section requests the provision of Liquated Damages for placements found to be invalid, and to enter the proposed per placement amount (G7) on a diskette or CD. Since Section G.6 on page 32 of the RFP shows $750 per invalid placement, is it still necessary to provide this information to the Regional Office on a diskette or CD?
No, offerors will not be required to propose an invalid placement amount. Section – G.6 Liquidated Damages for Placements Found to be Invalid is the correct information. The amount of $750 per placement has been established by the Office of Job Corps as indicated in Section G.6. Note- Section L.7.B.5a.9. G.7, page 131 will be deleted from the RFP.
2
Does the Government intend to construct a new male dormitory?
Yes
3
Can the Government provide a site plan which includes former/existing buildings with their associated number?
Yes we can, but we will not as it is not relevant to this RFP. A new center is being built, and a plan view of the new center is being provided.
4
In the 1st year of operations the CTT offering has a CNA program. But in the second year it is gone is this true?
As with any start-up operation, changes are expected. The regional office will solicit recommendations from the operator regarding the continuation of specific career tech offerings after the first year of operation. This CTT offering will have the same number of health occupations slots from the interim center phase to the final reconstructed center phase.
5
This would mean you would have to hire someone to train CNA the 1st year and terminate their employment the 2nd.
See answer to question 4 above.
6
In the 2nd thru the 5th year of the center operations CTT offerings of a Licensed Practical / Vocational Nurse is stated this is normally a post secondary program offered at a local community college. Is this to be set up as a center run program at the center? This not a easy program to get established from the state to allow a program to be started will it be a advanced program able to draw from the other center if it is to be a center run program? Has the state been contacted to allow this to happen? Can the program be run thru the local college under some dedicated slots to the LPN program?

It is to be set up as a center run program and not an advanced program. Offerors are free to propose alternatives methods of delivering the training should they desire. It is the government’s intent to establish a health occupations curriculum with increasing opportunities for advancement to higher levels of learning for students.

7
Are there design drawings available for the new buildings?
Some renderings have been provided as handouts at the pre-proposal conference.
8
Can the Government provide a site plan which includes former/existing buildings with their associated number?
No. The center is being built new from the ground up. The old site plan is not relevant to this requirement.
9
Has a site plan been developed as to the location of the new buildings?
A site plan will be provided.
10
Can we be provided with the names of those in attendance at this pre-proposal conference?
Yes – a list of attendees is included as part of this amendment.
11
Will the successful offeror be responsible for the purchase of equipment for the temporary buildings?
Yes
12
Have any energy saving features and energy efficient mechanical equipment been put into the re-constructed center?
Yes
13
Are contractor’s allowed to propose their own version of the GSA fleet for the center as well as the estimated phase-in of the vehicles?
Yes. This may be an option, but vehicle distribution will be based on GSA availability.
14
Is Bricklayer/Masonry an NTC taught trade?
Yes
15
The listings of Career Technical Training offerings for Contract Year 1 on page 13 shows Nursing Assistant/Home Health Aide under Health Occupations but it is not listed under Health Occupations in the table for Contract Years 2-5. Is this an error or is this offering to be eliminated after the first year of the contract?
It is to be set up as a center run program and not an advanced program. Offerors are free to propose alternatives methods of delivering the training should they desire. It is the government’s desire to establish a health occupations curriculum with increasing opportunities for advancement to higher levels of learning for students.
16
As to Health Occupations, does the Government have expectations on how the slots should be divided between the trade offerings?
Offerors are free to propose options.
17
Is the Emergency Medical Technician considered the concurrent Vocational Training Program as indicated on page 14 of the RFP? If not, what is considered the concurrent Vocational Training Program?
No. Emergency Med Tech is not necessarily considered to be a concurrent voc training program. Concurrent programs involve linkages to be developed between local educational institutions and the center with the intent being to establish reciprocal educational activities between the center and the institution.
18
The trade, Advanced Manufacturing-20 slots, is not defined in the RFP. Under the TAR listing released June 8, 2008, Advanced Manufacturing cluster consists of three training programs, Manufacturing Technology, Machining and Welding. All three of these trades are listed as 30 slot programs. Since welding is listed as a separate offering, which of the remaining training programs does Advanced Manufacturing represent? By having only 20 slots allocated to this training program an indication that it is a center specific trade? If so, what is the trade?
The trade to be offered is manufacturing technology.
19
The trade indicated as Medical Office Support is not longer identified as a DOL Job Corps offering and has been replaced with Medical Administration. Does the Government intent for Medical Office Support to be Medical Administration?
Medical office support is the name of the trade. The TAR includes medical admin, med transcriptionist, insurance claim processor, and health unit coordinator. Med admin is the basic program; the others are more specialized areas which are options for the offerors to propose, and/or consider as the center’s vocational offerings evolve.
20
Does the Government have a contract with the Mississippi Gulf Coast Community College to provide training for the 15 allocated slots? (RFP: Page 14).

No. The operator would have to establish a contract/agreement.

21
Bricklayer is not footnoted as a National Training Contractor; however, it is indicated that training will be provided by the Homebuilders Institute. Should Bricklayer be footnoted? (RFP: Page 13)

Yes. Bricklaying will be offered by an NTC.

22
The first contract year ends March 31, 2010; the increase in design capacity begins May 1, 2010. For the first month of the second contract year, April 2010, is the design capacity 68 males; 68 females for a total of 136 students as outlined for the first contract year? (RFP: Page 3,6,7)

Yes. Some flexibility will be needed on the part of the operator as we cannot exactly specify when the re-construction will be completed.

23
Does the Government expect the contractor to be fully staffed as of May 1, 2010 to operate the center as if it were operating at full design capacity of 280 students? (RFP: Page 3,6,7)

Yes. It is anticipated that the re-constructed center will be ready for occupation by June 2010, which is our best estimate at this time. This interim period between the interim/modular operation and the re-constructed center operation can be used to fill the remaining staff positions and provide training.

24
Beginning or May 1, 2010, can the Government provide the estimated design capacity for female residential students; male residential students; female non-residential students; and male non-residential for the build-up months of May 2010; June 2010; July 2010; August 2010; September 2010; October 2010; November 2010; and December 2010? (RFP: Page 6)

Given the volatility of a start-up center operation, inconsistent termination rates, and differing programmatic designs, it is expected that the student input schedule will be closely coordinated between the center operator and the OA provider to achieve a smooth OBS build-up. It is our expectation that the center will reach capacity by December 2010.

25
Is the Incentive Fee applicable to Year 1?
No

End of Q&A

PRE-PROPOSAL ATTENDEE LIST

The following is in response to the question to provide a list of all the attendees (POC) at the Pre-proposal Conference.

Dynamic Educational Systems, Inc. – Ralph Rockow, President

8433 N Black Canyon Hwy. Suite 184

Phoenix, AZ 85021

(602)995-0116

Education and Training Resources – Rett Dallas, Executive Vice-President/CFO

2422 Airway Drive

Bowling Green, KY 42103

(270)793-0607

Jackson Pierce Public Relations – Edna Jackson, President/CEO

817 West Peachtree Stree, Suite A-140

Atlanta, GA 30308

(404)584-2717

IRDUS – Gulf Coast Housing Resource Center – Lori West, Executive Director 1223 30th Ave.

Gulfport, MS 39501

(228)864-6677

Management & Training Corporation – Lynette Greenwell, Vice President, Development

500 North Marketplace Drive Centerville UT 84014

(801)693-2600 Minact, Inc. – Sam Devore, Executive Vice President

5220 Keele Street

Jackson, MS 39206

(601)362-1631

Odle Management Group, LLC – Lisa Odle, President/CEO

7127 E. Sahuaro Drive, Suite 203

Scottsdale, AZ 85254

(480)992-1027

Science Applications International Corporation – Ted Stevenson, Deputy Business Development Program Manager

6723 Odyssey Drive

Huntsville, AL 35806

(256)705-8588

Strategic Resources, Inc. – Robert Rummel, DOL Job Corps Capture/Proposal Development

Suite 600 W

McLean, VA 22102

(703)749-3040

End