Responses_to_Questions_DOL-15OCIOCIONAT-0172.docx
DOCX document 14 KB Posted
- Attached to
- APC Power Supply Services
- Solicitation number
- DOL-15OCIOCIONAT-0172
About this file
Responses to questions
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Responses to Questions:
1. How many PM visits per year are requested?
Response: Request 2 PM visits per year.
2. Both units are 80KVA and semiannual or quarterly service is recommended. Please let me know which service is applicable.
Response: Both 80 KVA semi-annual is recommended.
3. How many battery modules?
Response: Battery modules combined total = 128.
4. Battery replacement included?
Response: Battery replacement is not included. A PM must be performed after the contract is in place.
5. Who's responsible for battery replacement?
Response: OCIO/OSHA will be responsible for battery replacement. The request and estimate will be sent to OCIO for approval after the PM have been performed.
File details come from the government source that posted it. Updated .