Responses to Questions:

1. How many PM visits per year are requested?

Response: Request 2 PM visits per year.

2. Both units are 80KVA and semiannual or quarterly service is recommended. Please let me know which service is applicable.

Response: Both 80 KVA semi-annual is recommended.

3. How many battery modules?

Response: Battery modules combined total = 128.

4. Battery replacement included?

Response: Battery replacement is not included. A PM must be performed after the contract is in place.

5. Who's responsible for battery replacement?

Response: OCIO/OSHA will be responsible for battery replacement. The request and estimate will be sent to OCIO for approval after the PM have been performed.