Blackwell Solicitation DOL110RP20840_11-25-2009.pdf
PDF 4 MB Posted
- Solicitation number
- DOL110RP20840
About this file
Solicitation for Blackwell JCC
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions Answers_Amend0002_12102009.pdf | ||
| SF30 for BLACKWELL_Amend0002_12102009.pdf | ||
| Amendment Number 1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
94-0991-1218 510-1000RA
Project Title: RENOVATION OF VARIOUS BUILDINGS AT THE BLACKWELL CIVILIAN CONSERVATION CENTER
The work involves services to design and renovate Buildings 405, 408, 420, 425, 427, 440, 444, 445, 507, and 533 at the Blackwell Civilian Conservation Center. The work in Building 408 is to renovate existing space to accommodate vocational training needs totaling approximately 1,200 gross square feet and will include the demolition of the existing flooring, ceilings and interior partitions as well as the construction of new partitions, installation of a new floor and ceiling finishes. In addition to general construction and demolition work, the modification of heating and ventilation systems, as well as electrical power and lighting systems, will be necessary.
Blackwell Civilian Conservation Center 4155 County Highway H Laona, Wisconsin 54541 (Forest County) Telephone: (715) 674-2311
Scheduled Site Visit: Tuesday, December 1, 2009 at 1:30 CST
VADIM MOLOT (703) 516-2238
PUBLICATION DISCLOSURE
This procurement is being funded under the American Recovery and Reinvestment Act (ARRA), Public Law 11-5 (February 17, 2009). For each such Government contract, DOL is required to post certain details of the contract on DOL's website, which is linked to Recovery.gov via the award number. For contracts over $500,000.00, DOL is also required to post a summary of the contract.
1. SOLICITATION NO. 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES
4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
A. NAME B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12B.)
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 4-85)STANDARD FORM 1442
Prescribed by GSA YFAR (48 CFR) 52.236-1(d)NSN 7540-01-155-3212
SOLICITATION, OFFER
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION, OFFER
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATIONSOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
E-MAIL JOHNNY A. ARNOLD II arnold.johnny@dol.gov
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within 1 calendar days and complete it within 273 calendar days after receiving award, X notice to proceed. This performance period is X mandatory, negotiable. (See _____________________________.)
YES NO
A. Sealed offers in original and 5 copies to perform the work required are due at the place specified in Item 8 by 12/15/2009
(hour) local time 3:00pm EST (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due
B. An offer guarantee is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference
D. Offers providing less than 120 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NOTICE: SET-ASIDE for Total HUBZONE SMALL BUSINESSES
DOL110RP20840 11/27/09 1 OF 126
X
OASAM Office of Procurement Services SEE SECTION L U. S. Department of Labor Suite N-4308 200 Constitution Ave., NW Washington DC 20210
52.211-10
X 10 DAYS
X
14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO.
16. REMITTANCE ADDRESS
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS 0001 Design and renovation of Buildings 405, 408, 420, 425, 427, 440, 444, 445, 507, and 533 at the Blackwell Civilian Conservation Center …………………………………… $____________________
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20B. SIGNATURE 20C. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c) ( )
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation, is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work, requisitions identified award consummates the contract. which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER
TO SIGN
30B. SIGNATURE 30C. DATE 31B. UNITED STATES OF AMERICA
BY
OFFER
AWARD
STANDARD FORM 1442(REV. 4-85)BACK
(Include ZIP Code) (Include area code)
(Include only if different than Item 14)
(Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
(The offeror acknowledges receipt of amendments to the solicitation - give number and date of each)
(Type or print)
(4 copies unless otherwise specified)
(Type or print) (Type or print)
(Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror)
(To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
OASAM Office of Procurement Services U. S. Department of Labor Suite N-4308 200 Constitution Ave., NW Washington DC 20210
OASAM BRANCH OF INVOICE PAYMENTS
Suite S-5526
U.S. DEPARTMENT OF LABOR
200 CONSTITUTION AVENUE, NW
WASHINGTON DC 20210
Table of Contents
PART I - THE SCHEDULE...........................................................................................................A-1
SECTION A - SOLICITATION/CONTRACT FORM................................................................A-1
SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) .....A-1
PART I - THE SCHEDULE........................................................................................................... B-1
SECTION B - SUPPLIES OR SERVICES AND PRICE/COSTS............................................... B-1
B.1 PRICE/COST SCHEDULE................................................................................................ B-1
B.2 DELIVERABLE - AMERICAN RECOVERY AND REINVESTMENT ACT (ARRA)
REPORTING FROM THE PRIME RECIPIENTS…………………………………..……B-2
B.3 DELIVERABLE - RELEASABLE COPIES - FREEDOM
OF INFORMATION ACT………………………………………………………….……..B-2
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK......................C-1
[For this Solicitation, there are NO clauses in this Section]
SECTION D - PACKAGING AND MARKING...........................................................................D-1
[For this Solicitation, there are NO clauses in this Section] ......................................................D-1
SECTION E - INSPECTION AND ACCEPTANCE.................................................................... E-1
E.1 NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCE....... E-1
SECTION F - DELIVERIES OR PERFORMANCE................................................................... F-1
F.1 NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCE....... F-1
F.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
(APR 1984) ALTERNATE I (APR 1984)...................................................................... F-1
F.3 52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEPT 2000) ALTERNATE I
(APR 1984) ...................................................................................................................... F-1
SECTION G - CONTRACT ADMINISTRATION DATA…………………………..……….…G-1
G.1 PRE-CONSTRUCTION CONFERENCE……………………………………..…………G-1
G.2 PERIODIC PROJECT MEETINGS……………………………………..……………….G-1
G.3 SUBCONTRACTS………………………………………………………..……………...G-1
G.4 SHOP DRAWINGS……………………………………………………..………………..G-1
G.5 OPERATIONS, STORAGE AREAS AND SECURITY………………..……………….G-2
G.6 PROJECT SAFETY……………………………………………………..………………..G-3
G-7 DISPOSAL OF REFUSE………………………………………………...……………….G-3
G.8 SCHEDULE OFPROGRESS……………………………………………..……………...G-4
G.9 PAYMENTS TO CONTRACTOR………………………………………..……………...G-4
G.10 FURNISHING INFORMATION AND RECORDS………………………..……………G-5
G.11 WORKERS’ COMPENSATION LAWS…………………………………..…………….G-5
G.12 REQUIRED INSURANCE………………………………………………..……………..G-5
G.13 EQUITABLE ADJUSTMENTS………………………………………….……………...G-7
G.14 WEATHER DELAYS (EXCUSABLE DELAY)………………………….…………….G-9
G.15 TEST RESULTS…………………………………………………………...…………….G-9
G.16 AS-BUILT RECORD OF MATERIALS AND INSTALLATION……..….…………....G-9
G-17 SUBSTANTIAL COMPLETION……………………………………………….……….G-9
i
G-18 CONTRACT CLOSEOUT………………………………………………….…………...G-10
G.19 PRECEDENCE OF PLANS, SPECIFICATIONS, AND CLAUSES……….…………..G-11
SECTION H - SPECIAL CONTRACT REQUIREMENTS........................................................H-1
H.1 52.236-25 REQUIREMENTS FOR REGISTRATION OF DESIGNERS
(JUNE2003)……………………………………………………………………….……..H-1
H.2 DISPOSITION OF MATERIAL………………………………………………….….…....H-1
H.3 HAZARDOUS OCCUPATION ORDERS………………………………………………..H-1
H.4 RIGHTS AND OBLIGATIONS……………………………………………………..….....H-1
H.5 INITIATION OF LIQUIDATED DAMAGES………………………………….....………H-1
PART II - CONTRACT CLAUSES............................................................................................ ...I-1
SECTION I - CONTRACT CLAUSES ........................................................................................ I-1
I.1 NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCE......... I-1
I.2 52.203-15 WHISTLEBLOWER PROTECTIONS UNDER THE AMERICAN RECOVERY
AND REINVESTMENT ACT OF 2009 (MAR 2009) ..................................... I-4
I.3 52.204-11 AMERICAN RECOVERY AND REINVESTMENT ACT—REPORTING
REQUIREMENTS (MAR 2009)........................................................................ I-4 I.4 52.219-3 NOTICE OF TOTAL HUBZONE SET-ASIDE (JAN 1999) ............................... I-7
I.5 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION
(JUNE 2007) ........................................................................................................ I-8
I.6 52.222-39 NOTIFICATION OF EMPLOYEE RIGHTS CONCERNING PAYMENT OF
UNION DUES OR FEES (DEC 2004)............................................................... I-9
I.7 52.225-21 REQUIRED USE OF AMERICAN IRON, STEEL, AND MANUFACTURED
GOODS-BUY AMERICAN ACT-CONSTRUCTION
MATERIALS (Mar 2009) .............................................................................…I-11
I.8 52.227-23 RIGHTS TO PROPOSAL DATA (TECHNICAL)(JUN 1987)………..……..I-14
I.9 52.228-1 BID GUARANTEE (SEP 1996) ....................................................................... I-15
I.10 52.228-15 PERFORMANCE AND PAYMENT BONDS--CONSTRUCTION
(NOV 2006)...................................................................................................... I-15
I.11 52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (OCT 2008). I-16
I.12 52.236-4 PHYSICAL DATA (APR 1984)..................................................................... I-24
I.13 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997)
ALTERNATE I (APR 1984).......................................................................... I-24 I.14 52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)...................................... I-25
I.15 52.249-14 EXCUSABLE DELAYS (APR 1984)………………………………………..I-26
I.16 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)..................... I-27
PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS.................J-1
SECTION J - LIST OF ATTACHMENTS ....................................................................................J-1
DAVIS BACON WAGE RATES (ATTACHMENT J-1)………………………………………J-1
PART IV - REPRESENTATIONS AND INSTRUCTIONS ......................................................K-1
SECTION K - REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF
OFFERORS ............................................................................................................................K-1
K.1 NOTICE LISTING SOLICITATION PROVISIONS INCORPORATED
BY REFERENCE..............................................................................................................K-1 ii
K.2 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2006).......K-1
SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS............... L-1
L.1 NOTICE LISTING SOLICITATION PROVISIONS INCORPORATED
BY REFERENCE ............................................................................................................ L-1
L.2 52.211-1 AVAILABILITY OF SPECIFICATIONS LISTED IN THE GSA INDEX OF
FEDERAL SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM
DESCRIPTIONS, FPMR PART 101-29 (AUG 1998) ..................................................... L-1
L.3 52.216-1 TYPE OF CONTRACT (APR 1984)................................................................ L-1
L.4 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE
EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) ........ L-1
L.5 52.233-2 SERVICE OF PROTEST (SEP 2006) .............................................................. L-3 L.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ............................................... L-3
L.7 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE
(FEB 1998)....................................................................................................................... L-3 L.8 52.252-3 ALTERATIONS IN SOLICITATION (APR 1984) ......................................... L-3 L.9 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)....................... L-3
L.10 PROPOSAL SUBMISSION REQUIREMENTS….……………………………………...L-4
SECTION M - EVALUATION FACTORS FOR AWARD........................................................M-1
M.1 SELECTION CRITERIA………………………………………………………………….M-1
M.2 PRICE EVALUATION……………………………………………………………………M-1
iii
DOL110RP20840 SECTION B
SUPPLIES OR SERVICES AND PRICE/COSTS
B-1
SECTION B - CONTINUATION BLOCK
PART I - THE SCHEDULE
SECTION B - SUPPLIES OR SERVICES AND PRICE/COSTS
B.1 PRICE/COST SCHEDULE
ITEM DESCRIPTION:
Design and renovation of Buildings 405, 408, 420, 425, 427, 440, 444, 445, 507, and 533 at the Blackwell Civilian Conservation Center:
GRAND TOTAL ---$
B.2 DELIVERABLE - AMERICAN RECOVERY AND REINVESTMENT ACT (ARRA)
REPORTING FROM THE PRIME RECIPIENTS
The ARRA requires extensive reporting from the prime contractors on contracts awarded with funds appropriated under ARRA. The contractor is required to provide the reports as deliverables under this contract. These reports will be posted on a website, www.recovery.gov which is accessible by the public.
Three (3) days after contract award the contractor shall register at www.federalreporting.gov. The Contractor shall provide copies of registration confirmations and report confirmations, via e-mail, to the Contracting Officer. The contractor shall complete the reports as required and provide a copy of the reports submitted under this website to the Office of Acquisition Management Services via e-mail to veatch.valerie@dol.gov.
(1) The total amount of ARRA fund received from this agency under this contract;
(2) The amount of ARRA funds received that were expended or obligated to projects or activities under this contract, or which remain unobligated.
(3) A detailed list of all projects or activities for which ARRA funds were expanded or obligated under this contract, including--
(A) The name of the project or activity;
(B) A description of the project or activity;
(C) An evaluation of the completion status of the project or activity;
(D) An estimate of the number of jobs created and the number of jobs retained by the project or activity; and
DOL110RP20840 SECTION B
SUPPLIES OR SERVICES AND PRICE/COSTS
B-2
(4) Detailed information on any subcontracts awarded under this contract using ARRA funds, including the data elements required to comply with the Federal Funding Accountability and Transparency Act of 2006 (P.L. 109-282). Subcontract costs of less than $25,000 may be reported in the aggregate. It is anticipated that this data will potentially be submitted through the governments' Electronic Subcontract Reporting System, however if the system is not available, the reporting requirement will not be waived and all report shall be submitted to the DOL. The minimum required data elements are:
(A) contractor name;
(B) amount of award;
(C) information on the award, including transaction type, funding agency, NAICS code, programs source, and award title descriptive of the purpose of the funding action;
(D) the location of the contractor, and the primary location of contractor performance (city, state, congressional district, country)
(E) a unique identifier for the contract, and its parent, if any;
(F) any other relevant information required by the OMB.
(G) including the data elements required to comply with the Federal Funding Accountability and Transparency Act of 2006 (P.L. 109-282)
In the event the contractor has more than one ARRA funded contract with DOL, the reports may be combined with other DOL ARRA funded reporting. In this event, duplicate copies of the combined report must be submitted to each COTR.
B.3 DELIVERABLE - RELEASABLE COPIES - FREEDOM OF INFORMATION ACT
The Freedom of Information Act (FOIA) permits withholding information under several exemptions, including Exemption 4 which protects "trade secrets and commercial or financial information obtained from a person [that is] privileged or confidential," 5 U.S.C. 552(b)(4). Within 5 business days of contract award, the contractor shall provide a statement that the contract is available for full disclosure under the FOIA or provide a scanned PDF of the redacted copy of the contract identifying the specific potions the contractor believes are covered by the particular exemption requested. Any redactions must be fully supported under the FOIA. In the event the Government notifies the contractor that it does not agree with a proposed redaction, the contractor shall have 5 business days to submit additional information to support the requested redaction. For subcontracts, within 5 business days of the contractor's award of any subcontract over $500,000 the contractor shall provide the Government a scanned PDF copy of the subcontract with a statement that the copy is either available for full disclosure, or identifying the specific portions believed to be covered by the particular exemption requested. Redactions should be limited to those protections provided under the FOIA. Following the procedures above, the Government has the right to notify the contractor of any disagreement with proposed redaction or exemption requests.
DOL110RP20840 SECTION C
DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C-1
ESC: ________________________
CASS: _______________________
APPROVED: _________________
DATE: _______________________
DESIGN-BUILD SCOPE OF WORK
FOR
RENOVATIONS AND ALTERATIONS
OF
BUILDINGS 405, 408, 420, 425, 427, 440, 444, 445, 507, and 533
AT THE
BLACKWELL CIVILIAN CONSERVATION CENTER
LAONA, WISCONSIN
U.S. DEPARTMENT OF LABOR
PREPARED BY:
PBDewberry PROJECT NO. 510-1000RA July, 2009
DBSOW
C-2
TABLE OF CONTENTS
I. GENERAL
II. DESIGN REQUIREMENTS/SPECIFIC INSTRUCTIONS
A. LEGALLY MANDATED STANDARDS
1. Code of Federal Regulations
2. National and State Building Codes
3. Permits and Licenses
B. JOB CORPS GUIDELINES
1. JCH-814: Planning, Design, and Construction Administration Guidelines for
Architects and Engineers
C. OTHER STANDARDS
1. Life Cycle Cost (LCC) Analyses
2. Energy Conservation
3. Environmentally Preferable Products
4. Asbestos-Containing Materials & PCB Fluorescent Light Ballasts - Not applicable
D. SPECIFIC INSTRUCTIONS
1. Center Operation
2. Design-Build Contractor Responsibilities
3. Submittal Requirements
4. Building Design
5. Equipment
6. Optional Provisions
7. Design and Construction Progress Meetings
8. Construction Document Reproduction
III. EXTENT OF WORK
A. SITE IMPROVEMENTS AND UTILITIES
1. Design Objectives
2. Site Improvements
3. Site Utilities
B. GENERAL BUILDING DESIGN REQUIREMENTS
1. Architectural
2. Mechanical/Plumbing
3. Electrical
4. Warranties
IV. construction requirements/specific instructions
A. SPECIFIC INSTRUCTIONS
1. Quality Requirements
2. Temporary Facilities and Controls
V. SKETCHES
C-3
A. VICINITY MAP
B. LOCATION MAP
C. SITE PLAN
D. BUILDING 408 EXISTING FLOOR PLAN
E. BUILDING 408 PROPOSED FLOOR PLAN
VI. PROJECT SCHEDULE
ATTACHMENT 1–DESIGN-BUILD QUICK REFERENCE CHECKLIST………..………….……….44
C-4
DESIGN-BUILD SCOPE OF WORK
PY 2009–RENOVATION OF BUILDINGS
405, 408, 420, 425, 427, 440, 444, 445, 507, and 533
BLACKWELL CIVILIAN CONSERVATION CENTER
PUXICO, WI
GENERAL
The work involves services to design and renovate Buildings 405, 408, 420, 425, 427, 440, 444, 445, 507, and 533 at the Blackwell Civilian Conservation Center. The work in Building 408 is to renovate existing space to accommodate vocational training needs totaling approximately 1,200 gross square feet and will include the demolition of the existing flooring, ceilings and interior partitions as well as the construction of new partitions, installation of new floor and ceiling finishes. In addition to general construction and demolition work, the modification of heating and ventilation systems, as well as electrical power and lighting systems, will be necessary.
Other work in this scope includes improvements to exhaust ventilation in Buildings 420 and 444;
upgrades of the fire alarm systems in Buildings 405 and 440; repair and replacement of the roofs in Buildings 405, 425 and 450; the replacement of the heating and ventilating equipment in Building 405;
and the repair and replacement of interior/exterior doors and frames in Buildings 445 and 507; and radon testing in Buildings 408, 420, 427,440, and 533. The extent of work is more fully described in section III of this scope of work.
“DB Quick Reference Checklist”, Attachment 1, is a required form that identifies a simplified but not all inclusive list of issues that the design-build contractor needs to include as bid documents. The DOL Design Manual - JCH-814 paragraphs shown provide an initial design reference; however, reference to other sources may be required to fully address the issue.
DESIGN REQUIREMENTS/SPECIFIC INSTRUCTIONS
LEGALLY MANDATED STANDARDS
The design/build contractor will conform to:
Code of Federal Regulations
Safety and Health…………………………………… OSHA CFR Part 1926.62 NESHAP 40 CFR 61 Subpart M40 CFR 761
Disability/Accessibility…………………………………………28 CFR Part 36
The facility/project must be in strict conformance with the Uniform Federal Accessibility Standards (UFAS) The design-build contractor shall conduct a thorough research of this
C-5 guideline and, without exception, comply to the fullest extent, including those guidelines pertaining to the visually and hearing impaired.
No deviations from this guideline are allowed. However, if the design/build contractor, at any Design Review Submittal, demonstrates that the requirements would be technically infeasible or it would cause an undue burden as defined by the guidelines, the design-build contractor is obligated to bring this requirement to the attention of the Department of Labor for a decision on such requirements.
Life Safety Code………………………………………………………...NFPA-101
The design-build contractor’s responsibility for safety related requirements extends to all impacted areas and access ways affected by the work.
National and State Building Codes
The design-build contractor shall conform to all applicable construction codes, ordinances, and regulations including the national building code used in the local area, laws and local ordinances. Deviations and interpretations shall be subject to the approval of the Department of Labor. The design shall comply with all state and local codes pertaining to heavy rain and high wind design. All required and/or recommended design and building practices required by Forest County, Wisconsin shall be considered in the design.
Permits and Licenses
The design-build contractor shall research all regulatory, permitting and licensing requirements in accordance with JCH-814 Section 1.5.
The design-build contractor shall not submit plans or specifications to any local or state authority without the prior approval of the DOL/National Office, Job Corps. Since the center is owned by the Federal Government, DOL may be required to seek permits as required by local utility companies prior to them rendering services to the project during construction.
Where required by DOL, the design-build contractor shall submit the plans/specification documents to local agencies for permitting purposes. Any and all regulatory agency comments received as a result of the agency review shall be forwarded to DOL for review and approval prior to their incorporation into the documents. Once approved by DOL, the necessary work to bring the documents into compliance with the comments shall be performed by the design-build contractor as part of this contract including any subsequent re-submittals that may be required.
C-6
It is required that the design-build contractor will need to assess the requirements of the State of Wisconsin and the Forest County Building Codes as well as the Wisconsin Public Service (WPS) company that provides electricity and gas services and all applicable codes with respect to this project.
Written authorization is required from the Department of Labor prior to communications with the city of Forest County and WPS Company. The Department of Labor will assist the design-build contractor in the determination of these requirements through joint coordination.
JOB CORPS GUIDELINES
JCH-814: Planning, Design, and Construction Administration Guidelines for Architects and Engineers
For purpose of this project, any reference to Architects and Engineers shall equate to the design-build contractor.
Job Corps publication JCH-814, "Planning, Design, and Construction Administration Guidelines for Architects and Engineers," is a companion document to this scope of work. The JCH-814 has been developed to ensure consistency and clarity of project documents that form the basis of contracts for the design and construction of Job Corps facilities. It presents the design-build contractor additional design criteria not specifically stated in the scope of work. Where conflicts occur between the requirements of the scope of work and JCH-814, the requirements of the scope of work shall take precedence.
OTHER STANDARDS
Life Cycle Cost (LCC) Analyses
LCC shall be utilized as the basis for recommendations in making the selections of energy sources, systems and equipment, and building materials. However, the design must be consistent and in accordance with the extent of the scope of work. At the 60% Interim Submittal, the LCC analyses for the mechanical systems and fuel shall be submitted with recommendations for review, and shall be approved and revised as necessary as equipment is selected and specified. The LCC's shall be run on NIST's BLCC and Discount software programs. On request, the Department of Labor will furnish this software to the design/build contractor free of charge. The BLCC program shall be run on the OMB A-94 guidelines, using a
2.7 % discount factor.
The BLCC software is also available on the Federal Energy Management Program website at http://www.eere.energy.gov/femp/information/download_blcc.cfm under the heading “BLCC
C-7
4.9-08 (or latest version) & Quick BLCC 2.9-08 (or latest version)” for DOS programs only or “BLCC 5.3-08 (or latest version)” for a Windows version.
Provide a life cycle cost analysis for available types of renewable energy (solar, wind, and biomass). Include any credits available from federal, state, and local sources. Evaluate whether net metering (selling electricity back to the utility) is possible for this project.
Energy Conservation
All new work is to be designed in accordance with energy conservation opportunities and applicable federal directives. In response to energy conservation concerns, all proposed construction shall conform to the current edition of the Model Energy Code of the State of Wisconsin.
It is the Department of Labor’s policy to purchase energy and water consuming products which are in the upper 25% of energy and water efficiency whenever practicable and cost effective.
All work must be designed to meet or exceed the requirements of the Energy Policy Act of 1992 and 2005, Executive Order 13423, Energy Independence and Security Act of 2007 and all other applicable federal, state, and local codes and directives.
The design-build contractor shall evaluate options for the use of energy and water conservation measures in building design, inclusive of solar hot water heating systems, and shall include a description of recommended options in the design narrative for consideration and acceptance by DOL (see JCH-814, paragraph 1.8.2 and 1.8.3 for narrative requirements).
Consider as an option, the use of harvested rainwater, treated wastewater, and air conditioner condensate to be used where feasible for non-potable use and potable use where allowed.
Environmentally Preferable Products
The design-build contractor shall evaluate options for the use of environmentally preferable products and environmentally preferable building design and shall include a description of recommended options in the design narrative (see JCH-814, paragraph 1.8.4 for requirements).
Asbestos-Containing Materials & PCB Fluorescent Light Ballasts - Not applicable
SPECIFIC INSTRUCTIONS
Center Operation
The center shall remain in operation throughout the construction phase. All proposed interruptions to center operations must have prior approval from the Center Director. The design/build contractor, as part of this contract, shall coordinate with the DOL Engineering Support Contractor (ESC) and the center to develop a set of construction documents that will minimize disruption of center operations during construction.
C-8
Design-Build Contractor Responsibilities
An acceptable quality design must provide appropriate functional facilities at the lowest practical construction cost, with due consideration for economy in maintenance and operation.
The specified construction materials must be of quality that is consistent with the intended use of the facility, the center, and reflect local availability and construction skills. Innovative materials and methods should be considered, but only if they provide an economic or functional advantage.
Although this scope of work may identify specific elements of construction, it is the design-build contractor's responsibility to provide any and all elements which are incidental to provide a fully functional facility.
The design-build contractor will also provide sufficient (at least five) high quality photographs in digital and paper format to document the completed work in each building.
Submittal Requirements
This project will require the following submittals after NTP is issued:
The design-build contractor shall provide 15% Schematic Design Submital the includes items required in Section 7.5.1- Schematic Design Submittal (15%), of the Job Corps Handbook (JCH) 814, dated September 2006.
Additionally, the following items shall be addressed in the scope of work:
(i) Verify the location and types of existing utilities, within the limits of construction and as required to provide utility service to the facility.
(ii) Report on electrical infrastructure needs and requirements
(iii) Provide a Schedule of Tests and Inspections requirements.
The design-build contractor shall provide 60% Interim Submittal construction documents based on the schedule. The 60% Interim Submittal construction documents submission shall, at a minimum, contain the following:
Design narrative (All disciplines)
Engineering calculations (All disciplines)
Quality control plan
C-9
Drawings (All disciplines)
Specifications (All disciplines)
The 60% Interim Submittal shall meet the requirements of Section 7.5.3 Construction Documents Progress Submittal (60%) of the JCH -814, Planning, Design and Construction Administration Guidelines for Architects and Engineers, dated September 2006.
The design-build contractor shall provide “Construction Ready” documents (100% design submittal) based on the schedule. The “Construction Ready” documents submission shall, at a minimum, contain the following:
Final design narrative (All disciplines)
Engineering calculations (All disciplines)
Final quality control plan
Drawings (All disciplines)
Specifications (All disciplines)
The final submittal, to include all corrections to the design review comments, shall be submitted one week after the concurrence letter for the “Construction Ready” design review has been received.
Demolition work may start upon 15% design approval and submittal of Schedule of Values and Phasing plan. The remaining work will commence only afterthe “Construction Ready” design that includes all corrections to the design comments is approved.
Submittals for Review
For the submissions identified above, the design-build contractor shall submit six (6) sets of drawings and project documents (drawings shall consist of two full-size sets and four half-size sets), as well as three (3) sets of design calculations, at the 60% Interim Submittal and “Construction Ready” stages to the Department of Labor for review and concurrence. One
(1) set of drawings at the 60% Interim Submittal and “Construction Ready” design stage shall be submitted to the Job Corps Data Center, where applicable.
C-10
Each submittal of drawings shall be incorporated into an AutoCAD (version 2004 or later) compatible electronic format on compact disc and be delivered to DOL by the design-build contractor in addition to the drawing/specification sets required. Complete project specification documents shall also be furnished on a compact disc in electronic format that is Microsoft Word compatible.
The design-build contractor is required to maintain the design-build schedule per the contract, and must indicate to the Department of Labor ways and means to recover lost time due to delays. No additional time will be given to the design-build contractor unless it is determined by DOL that the delay is legitimate and unavoidable and that the design-build contractor has prudently exercised all options within its authority and ability to avert such delays.
The design-build contractor will be responsible for the professional quality, technical accuracy and adherence to the requirements of the scope of work for all plan submittals required under this contract. DOL will perform review of the required submissions within 14 calendar days of receipt of the submittals. The review will be limited to project constructability (e.g. site problems, existing obstructions or proposed utilities, proposed contract time for construction, omissions, discrepancies, known issues that have occurred at the site or with projects of similar scopes, phasing, and coordination problems that could lead to construction difficulties), design (conformance to the negotiated scope of work) and construction quality control procedures.
Unless stated otherwise, review comments and concurrence with the required submissions do not revise the scope or intent of the project and do not constitute a request for change beyond the negotiated scope of work. In the event DOL determines that any required submission is incomplete which precludes a meaningful review, or does not adhere to the scope of work, DOL will advise the design-build contractor of the shortcomings and direct the design-build contractor to revise and resubmit the plan. No time extension will be granted as a result of such action. In the event the design-build contractor believes that any review comment requires a change to the scope of agreed work, the design-build contractor shall first consult the DOL for clarification, and shall provide written notice to the Contracting Officer concerning the reasons why the design-build contractor believes the scope has been changed.
Following concurrence of the design documentation at the “Construction Ready” stage(s), the design-build contractor shall prepare plan sets for use during construction. All review comments shall be resolved in writing by the design-build contractor to the satisfaction of the DOL before the design-build contractor submits the final construction plans. Each plan sheet shall have its last revised date noted on the sheet and clearly marked “Approved for Construction”
C-11
In addition to the review, coordination and specification of interior building finishes, and an interior finishes/colors submittal (color board) is required where applicable. This submittal is required at the 60% Interim Submittal construction document and final “Construction Ready” stages of design. Two copies of the required color board shall be submitted to DOL at each of the identified design submissions.
Building Design
The design-build contractor must be familiar with local construction methods and building materials, and shall provide a design that exemplifies the optimum balance of economy, aesthetics, energy conservation, and safety, ease of maintenance and speed of construction.
b. The design-build contractor will develop a complete set of documents as required for site adaptation, compliance with current code, compliance with established Energy Conservation guidelines contained in Section II, and in accordance with the requirements as described in section IV.
Equipment
The design-build contractor shall clearly differentiate equipment that is a part of the design-build contractor's responsibility from equipment that is the Government's responsibility.
In general, only "fixed" equipment will be part of the contract. DOL will provide the "movable" equipment. The responsibility for the procurement of equipment is discussed in the individual section for each building type in JCH-814 Chapter 4.
Optional Provisions
The design-buildcontractor’s responsibilities shall include interface activities with any, and all, local utility or service providers (i.e. water, electric, gas, fire alarm, etc). The purpose is not for obtaining permits but for informational purposes (design sizing and cost estimates) only. The design-build contractor shall:
Submit the required drawings and specifications to the local utility.
Obtain written approval of the interface design from the utility.
The design-build contractor must comply with all Federal, State and local design and building practices. It is also anticipated that the design-build contractor will need to assess the design and construction requirements of Forest County, the WPS Company with respect to this project.
Written authorization is required from the Department of Labor prior to communications with Forest County, and the WPS Company.
C-12
Design and Construction Progress Meetings
The design-build contractor should plan for a total of (3) three meeting days with DOL and/or its representatives during the course of the design phases of the work in addition to on-board reviews of the 60% and 100% submittals. These meetings will be held in the design-build contractor’s offices.
A DOL ESC representative will visit the site at a minimum once a month during construction.
During this visit, the completed work will be verified by the DOL ESC representative. In preparation for the monthly meeting, the design-build contractor shall prepare a monthly construction progress report. The reports shall include an updated CPM schedule, a minimum of 10 electronic photos of all aspects of the project and a list of open issues.
Construction Document Reproduction
Six (6) sets of the “Approved for Construction” documents and drawings, sealed and dated by the appropriate licensed professionals, shall be reproduced for DOL use.
EXTENT OF WORK
SITE IMPROVEMENTS AND UTILITIES
Design Objectives The work involves providing design/build services for various improvements in numerous existing buildings at the Blackwell Civilian Conservation Center. The work will include, but not be limited to, ACM remediation, demolition, interior renovations and build-outs, installation of associated HVAC systems, electrical power and lighting systems, plumbing systems, roofing replacement; flooring finishes replacement as well as demolition of old doors/frames and their replacements. The work is divided into several parts as described below:
Design services to develop construction drawings and specifications from conceptual to final design for the demolition and new renovation work of the spaces.
To facilitate but not overly burden the security control, carefully plan siting of staging areas required to support construction of the buildings so that students’ activities will be unaffected
The entire design should not adversely impact the relatively quiet and peaceful environment. Any trees and vegetation should be preserved as much as possible to retain a natural buffer that is presently there.
C-13
To a maximum extend feasible, maintain or restore the predevelopment hydrology of the site with regards to temperature, rate, and duration of flow.
Building 405
Provide rigid wire guards to protect two audio/visual fire alarm devices and two manual pull stations in the gymnasium preventing damages to the fire alarm devices. The handles of the pull stations must remain readily accessible. Securely mount the guards to the walls.
Remove the existing entry canopy roofing and building paper. Repair and/or replace roof sheathing and ridge vent where necessary. Provide new drip edge, flashing where needed and 15# building felt. Furnish and install GAF Timberline Prestique Lifetime High Definition® Roofing Shingles (or approved equal) 30-year warranted shingle roofing per the manufacturer’s specifications to withstand a 100 mph wind force.
Provide design build services to replace the existing heating and ventilating system for the gymnasium. Provide packaged HVAC systems mounted on 4” concrete pad (3000 psi, reinforced). Each unit shall have a total cooling capacity of 120 MBH utilizing R-410a refrigerant and a total heat capacity of 180 MBH (minimum efficiency rate of 94%). Run internally insulated back waterproof supply ductwork on the outside of the building up to two runs of spiral wound with drum diffusers angled down to the playing court and bleacher areas. Provide for 100% outdoor air economizer operation. Demolish and dispose old units, ventilation fans and louvers, and debris from the demolition of the existing return air chases.
Modify the existing unit electrical per the manufacturer’s specifications. Provide each unit with programmable thermostat with locking covers.
Replace the damaged acoustic ceiling tiles above basketball court.
Building 408
Provide radon level testing by collecting a minimum of two samples on the lowest occupied level of the building. Send the results of the radon tests to the Engineering Support Contractor upon receipt.
Renovate existing space to accommodate vocational training needs totaling approximately 1,200 gross square feet. The work includes the demolition of the existing flooring, ceilings and interior partitions as well as the construction of new partitions, installation of new floor and ceiling finishes that matches the existing floors and ceiling finishes. In addition to general construction and demolition work, the modification of heating and ventilation systems as well as electrical power and lighting systems will be necessary.
Building 420
C-14
In the lower floor toilet rooms, replace the broken exhaust fans. Energize the fan and connect to the nearest available circuit with adequate capacity in accordance with NEC.
Provide radon level testing by collecting a minimum of two samples on the lowest occupied level of the building. Send the results of the radon tests to the Engineering Support Contractor upon receipt.
Building 425
Remove existing roof and building paper. Repair and/or replace roof sheathing and ridge vent where necessary. Provide new drip edge, flashing where needed and 15# building felt.
Furnish and install GAF Timberline Prestique Lifetime High Definition® Roofing Shingles (or approved equal) 30-year warranted shingle roofing per the manufacturer’s specifications to withstand 100 mph wind force.
Building 427
Provide radon level testing by collecting a minimum of two samples on the lowest occupied level of the building. Send the results of the radon tests to the Engineering Support Contractor upon receipt.
Building 440
Provide audio/visual fire alarm devices in female and male bathrooms. Connect the component to the building's fire alarm system and install all wiring in EMT conduit.
Provide radon level testing by collecting a minimum of two samples on the lowest occupied level of the building. Send the results of the radon tests to the Engineering Support Contractor upon receipt.
Building 444
In all bathrooms, re-configure the exhaust system so that each bathroom is individually exhausted to the outdoors and install a 100 CFM ceiling exhaust fan with integral back draft damper in each duct. Energize from the nearest panel with available capacity per NEC.
Install wall-mounted switch.
Building 445
At the north side wall, replace door and frame with a new 3' W x 7' H commercial grade metal door that meet EnergyStar requirements and metal frame with associated hardware.
C-15
Building 450
Remove existing roof and building paper. Repair and/or replace roof sheathing and ridge vent where necessary. Provide new drip edge, flashing where needed and 15# building felt.
Furnish and install GAF Timberline Prestique Lifetime High Definition® Roofing Shingles (or approved equal) 30-year warranted shingle roofing per the manufacturer’s specifications to withstand a 100 mph wind force.
Building 507
Replace the exterior egress door located on the west façade leading out of the warehouse area with new 3'-0" x 7'-0" commercial grade metal door that meet EnergyStar requirements and metal frame with associated hardware.
Replace the exterior wood door and metal frame at the west wall of the building with new 3'- 0" x 7'-0" commercial grade metal door that meet EnergyStar requirements and metal frame with associated hardware.
Building 533
Provide radon level testing by collecting a minimum of two samples on the lowest occupied level of the building. Send the results of the radon tests to the Engineering Support Contractor upon receipt.
Site Improvements Not applicable.
Site Utilities Not applicable.
GENERAL BUILDING DESIGN REQUIREMENTS
Architectural
Prime and paint all exposed unfinished, visible wood including columns, beams, and trim.
Finish hardware shall be heavy duty, handicapped accessible and shall include, but not be limited to, the following:
Locksets for all exterior entry/exit doors, offices, storage rooms, mechanical and electrical rooms.
Privacy latch sets for all staff toilet rooms.
C-16
Door closers for all exterior entry/exit doors; surface-mounted emergency exit devices for all required exterior entry/exit doors.
Door closers for all fire rated door assemblies.
Proper weather-stripping for all exterior doors.
Kick plates for all exterior entry/exit doors.
Locksets for all dorm rooms that always remain locked from the outside.
Mechanical/Plumbing Domestic water heaters, where applicable, shall be furnished with an extended warranty of ten years at a minimum. The storage tank and all separate expansion tanks shall be provided with extended warranties for a minimum of ten years. Gas-fired furnaces shall be furnished with an extended warranty of five years at a minimum.
The design-build contractor shall evaluate all of the existing HVAC equipment (included in the design) to determine if the specified equipment is of adequate size and will provide the proper cooling and heating to comply with ASHRAE standards for cooling and heating. The design-build contractor shall size all HVAC have and mechanical equipment as required. Bathrooms with windows shall have mechanical exhaust directed to the exterior of the building.
Use Water Sense labeled products and other water conserving products where feasible.
Electrical
Systems provided must include complete electrical distribution, fire alarm, and provisions for data network, cable TV, and telephone systems.
Moisture resistant lighting fixtures must be provided in wet/damp locations.
Romex cable shall not be used in this project.
Do not locate smoke detectors outside of bathroom/shower room doors.
Provide conduits with pull wires for the telephone system from the main telephone room.
Provide conduits with pull wires for a data system from buildings’ main computer rooms.
Provide all necessary block-outs and sleeves in stem walls for data conduits, telephone conduits, and electrical conduits for electrical sub-feed.
C-17
The design-build contractor shall evaluate the existing electrical equipment to determine if the equipment is of adequate size and will provide the proper electrical service to comply with code. The design-build contractor shall coordinate and size all electrical equipment as required.
Warranties
The design-build contractor shall ensure all warranty requirements, including manufacturer’s warranties are clearly identified.