Summary
This Request for Quote (RFQ) is issued by the Massachusetts Department of Energy Resources (DOER) for a comprehensive impact analysis of the state's Fossil Fuel-Free Demonstration Program. The procurement seeks a qualified contractor to develop and evaluate the impacts of municipal fossil fuel-free building construction and renovation requirements on housing production and affordability, with specific focus on effects for low- and moderate-income households. The analysis will address research questions concerning housing production changes, residential construction costs, housing development feasibility, housing affordability impacts, and attribution of observed changes to the demonstration project. Two reports are required: a draft report due July 16, 2027, with final submission by September 30, 2027, and a second draft report due July 14, 2029, with final submission by September 30, 2029. The contract is anticipated to begin in January 2027 and conclude on September 30, 2029. The RFQ response deadline is December 16, 2026, at 4:00 PM EST, with the question deadline of December 2, 2026, and anticipated contract award on January 13, 2027.
The maximum contract funding is $250,000 for the full project duration, with pricing to be submitted on a project-based approach rather than hourly rates. The selected contractor must demonstrate expertise in housing economics, quantitative policy evaluation, residential construction costs, building energy systems, and affordable housing development, with a multidisciplinary team led by a housing economist or housing policy researcher. The contract is subject to Statewide Contract PRF76 (Management Contractors, Program Coordinators, and Planners Services) terms and conditions. DOER reserves the right to extend the contract for two additional one-year periods if needed and may increase funding with mutual written agreement for expanded scope. All work, deliverables, and associated documents become the full property of the Commonwealth of Massachusetts.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
THE COMMONWEALTH OF MASSACHUSETTS
EXECUTIVE OFFICE OF ENERGY AND
ENVIRONMENTAL AFFAIRS
DEPARTMENT OF ENERGY RESOURCES
ELIZABETH MAHONY, COMMISSIONER
100 Cambridge Street, 9th Floor Boston, MA 02114
Request for Quote (RFQ)
Document Title: Fossil Fuel-Free Housing Impact Analysis
COMMBUYS Bid Number: BD-27-1041-ENE01-ENE01-135514
Agency Document Number: RFQ-ENE-2027-014
Issued: November 18th, 2026
Please Note: This is a single document associated with a complete Bid (also referred to as Solicitation) that can be found on www.COMMBUYS.com. All Bidders are responsible for reviewing and adhering to all information, forms and requirements for the entire Bid, which are all incorporated into the Bid. Bidders may also contact the COMMBUYS Helpdesk at COMMBUYS@state.ma.us or the COMMBUYS Helpline at 1-888-MA-STATE. The Helpline is staffed from 8:00 AM to 5:00 PM Monday through Friday Eastern Standard or Daylight time, as applicable, except on federal, state and Suffolk County holidays.
http://www.commbuys.com/ mailto:COMMBUYS@state.ma.us
Massachusetts Department of Energy Resources – RFQ-ENE-2027-014
TABLE OF CONTENTS
I. INTRODUCTION
A. Massachusetts Department of Energy Resources B. Green Communities Division
II. BACKGROUND
C. Fossil Fuel-Free Demonstration Program
II. PROCUREMENT AND CONTACT INFORMATION
A. Type of Procurement B. RFQ Distribution Method C. Massachusetts Public Records Law D. No Guarantee of Resulting Contract E. Questions and Answers F. Contact Information G. Procurement Calendar
III. SCOPE OF WORK
A. Background and Proposed Activities
IV. CONTRACT INFORMATION
A. Funding availability/duration of contract B. Contract Expansion C. Contractor’s responsibility and invoicing D. The Commonwealth’s responsibility
PROPOSAL REQUIREMENTS
E. Applicant Qualifications and Experience F. Budget
V. PROPOSAL EVALUATION
I. INTRODUCTION
A. Massachusetts Department of Energy Resources
The Massachusetts Department of Energy Resources (DOER) develops and implements policies and programs aimed at ensuring the adequacy, security, diversity, and cost-effectiveness of the Commonwealth's energy supply to create a clean, affordable, equitable, and resilient energy future for all residents, businesses, communities, and institutions.
B. Green Communities Division The DOER Green Communities Division provides grants, technical assistance, and local support from the Regional Coordinators to assist municipalities in reducing energy use and costs by implementing clean energy projects in municipal buildings, facilities, and schools. The Green Communities Division also manages the Fossil Fuel-Free Demonstration Program (FFF Program), inclusive of monitoring its implementation and reporting results.
II. BACKGROUND
C. Fossil Fuel-Free Demonstration Program In 2022, An Act Driving Clean Energy and Offshore Wind was enacted, which included a provision requiring DOER to establish a Fossil Fuel Free (FFF) Demonstration Program for up to ten (10) cities and towns. The statute establishes a reporting requirement to monitor the program impacts on “emissions, building costs, operating costs, the number of building permits issued and other criteria as set by the department in consultation with participating cities and towns and the secretary of housing and economic development.”
The statute also requires the selection of “comparable communities” to better understand the impact of the ordinance. Both participating and comparable communities are required to report annually by June 30th under the associated DOER regulation (225 CMR 24.00). Additionally, the legislation requires electric and gas utilities to submit data annually to DOER on energy consumption and costs for new construction and major renovation projects in these communities.
The department is required to submit biannual reports to the legislature with findings compiled from this data. The first such report was submitted in September 2025, with the second one due in September 2027.
The September 2025 report continued limited content since it was produced shortly after the communities started enforcing their FFF regulations. The DOER expects to have a more robust data set for the 2027 report and will attempt to complete the required housing analyses. DOER has neither capacity nor specific subject expertise to evaluate those datasets and develop an appropriate approach to satisfy the statute mandated housing analyses.
The DOER is seeking a qualified contractor under Statewide Contract PRF76 to conduct a multi-year assessment of the impacts of the Municipal Fossil Fuel-Free Building Construction and Renovation Demonstration Project on housing production and housing affordability, including impacts on low- and moderate-income households and affordable housing development.
https://malegislature.gov/Laws/SessionLaws/Acts/2022/Chapter179 https://www.mass.gov/doc/225-cmr-2400-finalclean/download https://www.mass.gov/doc/municipal-fossil-fuel-free-demonstration-program-report/download
The DOER seeks a qualified contractor with demonstrated expertise in housing economics, quantitative policy evaluation, residential construction costs, building energy systems, and affordable housing development. The selected contractor must demonstrate the technical capacity to conduct an objective, evidence-based assessment of the impacts of fossil fuel-free building requirements on housing production and housing affordability. Such assessment shall be replicable and updated every two years as part of the mandated reporting of DOER.
The selected contractor should consist of a multidisciplinary team led by a housing economist or housing policy researcher, supported by specialists in building construction costs, statistical analysis, and affordable housing development and reporting.
Please see section III A. Scope of Work for more information.
II. PROCUREMENT AND CONTACT INFORMATION
A. Type of Procurement The contract (Contract) will be a Fee for Service subject to 801 CMR 21 and Statewide Contract PRF76: Management Contractors, Program Coordinators, and Planners Services.
B. RFQ Distribution Method This RFQ has been distributed electronically using the COMMBUYS system. It is the responsibility of every potential respondent to check COMMBUYS for any addenda or modifications to an RFQ to which they intend to respond. The Commonwealth of Massachusetts and its subdivisions accept no liability and will provide no accommodations to respondents who fail to check for amended RFQs or submit inadequate or incorrect responses.
Respondents may not alter RFQ language or any RFQ component files. Those submitting a proposal must respond in accordance with the RFQ directions and complete only those sections that prompt a respondent for a response. Modifications to the body of this RFQ, specifications, terms and conditions, or which change the intent of this RFQ, are prohibited. Any unauthorized alterations will disqualify a response.
PRF 76: Management Contractors, Program Coordinators, and Planners Services, Work awarded as a result of this RFQ is pursuant to Statewide Contract PRF76 – Management Contractors, Program Coordinators, and Planners Services. As such, all terms, conditions, contract rules, and pricing established in PRF76 shall apply. Additional information concerning PRF76 can be found in the User Guide: PRF76 - Statewide Contract User Guide
C. Massachusetts Public Records Law All proposals and information submitted in response to this RFQ are subject to the Massachusetts Public Records Law, M.G.L., Chapter 66, Section 10, and to Chapter 4, Section 7, and Subsection
26. Any statements in submitted proposals that are inconsistent with these statutes shall be disregarded.
https://www.statewidecontractuserguide.mass.gov/CUG/Guide/PRF76
D. No Guarantee of Resulting Contract The Commonwealth makes no assurance that any services will be purchased from any contract resulting from this RFQ.
E. Questions and Answers All questions must be submitted through COMMBUYS.
F. Contact Information Responses to this RFQ will be received by:
Procurement Contact: Kira Moodliar Department of Energy Resources 100 Cambridge Street, 9th Floor Boston, MA 02114 E-mail: kira.moodliar@mass.gov RFQ Name: Fossil Fuel-Free Housing Analysis RFQ File Number: RFQ-ENE-2027-014
G. Procurement Calendar
Milestone Date DOER Issues RFQ November 18, 2026 Deadline for Submitting Questions December 2, 2026 DOER Answers Questions December 9, 2026 RFQ Response Due December 16, 2026 at 4:00PM EST Selection of Winning Response* January 13, 2027 Execution of Contract with DOER* January 27, 2027
* Dates after RFQ Response Due date are anticipated dates. All dates are subject to change.
mailto:kira.moodliar@mass.gov
III. SCOPE OF WORK
A. Background and Proposed Activities
The DOER Green Communities Division is seeking a contractor (Contractor) to develop and to evaluate the impacts of the Municipal Fossil Fuel-Free Building Construction and Renovation Demonstration Project (Demonstration Project) on housing production and housing affordability, including impacts on low- and moderate-income households and affordable housing development.
The Contractor shall conduct an independent, objective, evidence-based analysis to determine whether implementation of the Demonstration Project has resulted in measurable changes in housing production, housing construction costs, housing affordability, or housing costs for low-and moderate-income households.
The Contractor shall prepare two reports documenting the analysis, findings, and conclusions:
• Report 1: Draft due to DOER by July 16, 2027
• Report 2: Draft due to DOER by July 14, 2029
The analysis shall determine whether impacts have occurred, their direction and magnitude where measurable, and the extent to which any observed changes can reasonably be attributed to the Demonstration Project.
Task 1 — Develop Analytical Methodology
The Contractor shall develop a comprehensive analytical methodology for evaluating the impacts, of the local Fossil Fuel Free bylaw on housing production and affordability that addresses the following research questions:
A. Housing Production Has implementation of the local Fossil Fuel Free bylaw affected housing production in participating municipalities, including the number, type, and timing of residential developments?
B. Housing Affordability Has implementation of the local Fossil Fuel Free bylaw affected housing affordability, including residential construction costs, housing development feasibility, housing prices, rents, and household energy and operating costs?
C. Affordability with respect to Low- and Moderate-Income Households Has implementation of the local Fossil Fuel Free bylaw affected housing affordability for low- and moderate-income households, including the production and financial feasibility of affordable housing developments and the total housing costs borne by residents?
D. Attribution of Impacts To what extent can any identified changes reasonably be attributed to the local Fossil Fuel Free bylaw rather than other factors affecting housing production and affordability?
The Contractor shall:
1. Identify appropriate quantitative and qualitative analytical methods to address the research questions.
2. Establish criteria for selecting a representative sample of participating municipalities, comparable municipalities, and residential developments.
3. Identify appropriate measures and indicators of housing production and affordability.
4. Develop an approach for comparing conditions before and after implementation of the
Demonstration Project, where supported by available data.
5. Identify and account for relevant external factors, including housing market conditions, interest rates, zoning requirements, construction costs, and other building code requirements.
6. Develop methods for assessing the reliability and comparability of construction cost data.
7. Identify approaches for evaluating impacts on low- and moderate-income households and affordable housing development.
8. Assess whether available data is sufficient to support statistically reliable conclusions or causal inferences.
9. Identify data limitations and appropriate methods for addressing uncertainty.
The Contractor shall consider the use of statistical and econometric methods, including comparison-group and quasi-experimental approaches, where appropriate and feasible. The proposed methodology shall be sufficiently rigorous to support credible findings while remaining proportionate to the available data, evaluation period, and project budget. Any use of generative artificial intelligence must be declared whether in developing, enacting or describing the methodology, as in line with commonwealth policy. The methodology shall be designed to support both the 2027 and 2029 reports and permit meaningful comparisons of findings over time.
Deliverable 1: Analytical Methodology and Evaluation Plan, including research questions, proposed data sources, analytical methods, evaluation indicators, assumptions, limitations, and project schedule. The Contractor shall obtain DOER approval of the methodology before undertaking the principal analytical work.
Task 2 — Review and Assess Available Data
DOER anticipates providing available housing production, building energy consumption, and construction cost data associated with the Demonstration Project. The Contractor shall review the available data to determine their completeness, reliability, consistency, and suitability for the proposed analysis.
The Contractor shall:
1. Review housing production and permitting data for participating and comparable municipalities.
2. Review available residential building energy consumption data.
3. Assess the accuracy and reliability of available construction cost information.
4. Identify data gaps, inconsistencies, and limitations.
5. Determine whether supplemental research or data collection is necessary.
6. Recommend appropriate methods for addressing identified data deficiencies.
Because the accuracy of certain construction cost information may be uncertain, the Contractor shall conduct targeted validation and supplemental research as necessary to support reasonable estimates of incremental construction costs attributable to the Demonstration Project. The Contractor shall distinguish between verified data, estimated values, modeled results, and information obtained through stakeholder interviews.
Deliverable 2: Data Assessment and Validation Memorandum documenting data quality, identified gaps, recommended supplemental research, and any proposed adjustments to the analytical methodology.
Task 3 — Conduct Housing Production and Affordability Impact Analysis
Using the approved analytical methodology, the Contractor shall evaluate the impacts, if any, of the Demonstration Project. The analysis shall address:
A. Housing Production Impacts The Contractor shall evaluate whether the Demonstration Project has affected residential permitting, housing starts, housing completions, development timing, housing types, or overall housing production.
B. Construction Cost and Housing Affordability Impacts The Contractor shall evaluate whether the Demonstration Project has affected residential construction costs, housing development feasibility, housing prices, rents, or household energy and operating expenses. The analysis shall distinguish incremental costs associated with fossil fuel-free requirements from costs associated with other building code requirements and broader construction market conditions.
C. Affordability Impacts on Low- and Moderate-Income Households The Contractor shall evaluate whether the Demonstration Project has affected housing affordability for low- and moderate-income households, including affordable housing development costs, financing feasibility, and household energy and housing expenses.
D. Evaluation of Findings The Contractor shall determine whether the available evidence indicates positive impacts, negative impacts, no measurable impacts, or insufficient evidence to reach a reliable conclusion. Where impacts can be estimated, the Contractor shall identify their approximate magnitude, uncertainty, and significance. The Contractor shall distinguish observed impacts from projected or potential impacts and shall explain the limitations of any causal conclusions.
Task 4 — Prepare Report to the Legislature by September 30, 2027
The Contractor shall prepare an initial report evaluating the impacts of the Demonstration Project on housing production and affordability based on data available during the initial evaluation period. The Contractor shall submit a complete draft report to DOER sufficiently in advance of the final deadline to allow for review and revisions.
Deliverable 3: Draft 2027 Report.
Deliverable 4: Final 2027 Report, including executive summary and supporting analytical documentation.
Task 5 — Update Analysis and Prepare Second Report Due August 1, 2029
Following completion of the 2027 report, the Contractor shall update and expand the analysis using additional housing production, energy burden, construction cost, and other relevant information that becomes available. The Contractor shall:
1. Review and incorporate additional data available after completion of the 2027 report.
2. Update the analysis of housing production in participating and comparable municipalities.
3. Reassess construction cost impacts using additional information from residential developments, where available.
4. Update the analysis of housing affordability, including construction and operating costs.
5. Reevaluate impacts on low- and moderate-income households and affordable housing developments.
6. Determine whether additional evidence strengthens, modifies, or contradicts the findings presented in the 2027 report.
7. Assess whether the additional evaluation period permits stronger conclusions regarding impacts attributable to the Demonstration Project.
8. Update conclusions and recommendations as appropriate.
The Contractor shall use a consistent analytical framework across both reporting periods to facilitate comparison of findings. Any methodological changes shall be clearly documented and justified. The Contractor shall submit a complete draft of the second report to DOER sufficiently in advance of the final deadline to allow for review and revisions. The Contractor shall incorporate DOER comments and submit the final report to DOER prior to September 30, 2029.
Deliverable 5: Draft 2029 Report.
Deliverable 6: Final 2029 Report, including executive summary, updated findings, comparison with the 2027 report, and supporting analytical documentation.
Task 6 — Project Management and Coordination
The Contractor shall provide overall project management and coordination throughout the contract period. Responsibilities shall include:
• Developing and maintaining a project schedule;
• Coordinating with DOER staff and relevant stakeholders;
• Managing data requests and supplemental research activities;
• Coordinating the work of the Contractor's technical specialists and subcontractors;
• Participating in periodic project status meetings;
• Identifying and communicating project risks, data limitations, and schedule concerns;
• Ensuring quality control and consistency of analytical methods;
• Managing the preparation, review, and timely submission of both required reports.
The Contractor shall designate a project manager to serve as DOER's primary point of contact.
The Contractor shall provide periodic progress updates and maintain sufficient project documentation to support continuity between the 2027 and 2029 reporting periods.
The Contractor understands that all work, deliverables, and associated documents included in this project are owned in full by the Commonwealth of Massachusetts and shall further hold all information gathered as confidential.
IV. CONTRACT INFORMATION
A. Funding availability/duration of contract The maximum amount of funding for any contract resulting from this RFQ is two hundred and fifty thousand dollars ($250,000). It is anticipated that the contract will begin in January 2027 and end on September 30, 2029. The contract is subject to available funding. DOER reserves the right to hire a Contractor for a limited scope of work if necessary to meet the budget parameters. DOER may also opt to extend the contract for two one-year periods.
B. Contract Expansion If additional funds become available during the contract duration period, DOER reserves the right to increase the maximum obligation to the contract executed as a result of this RFQ, with related additional tasks to be determined by mutual written agreement consistent with the terms of statewide contract PRF76.
C. Contractor’s responsibility and invoicing The selected Contractors will be responsible for the timely completion of the requirements described above and as directed by DOER. The selected Contractor shall assume overall responsibility for coordinating and completing all deliverables contained in the resultant contract.
All invoices must be submitted to DOER on a schedule and in a format to be agreed upon by DOER and the selected Contractor. The selected Contractor will submit invoices, no more frequently than monthly. Invoices shall include sufficient back-up documentation to support the amount being invoiced.
D. The Commonwealth’s responsibility DOER’s Project Manager will be responsible for overseeing and managing all tasks undertaken by the selected Contractor, including but not limited to developing a Statement of Work and schedule; reviewing, commenting on, and approving deliverables; coordinating with DOER and other program staff; and approving invoices promptly.
PROPOSAL REQUIREMENTS
Respondents to this RFQ-ENE-2027-014 must respond via the COMMBUYS web portal by 4:00 P.M. EST on December 16th, 2026. Late proposals will not be accepted. Faxed proposals will not be accepted. Only electronic proposals will be accepted. Unnecessary attachments beyond those sufficient to present a complete, comprehensive, and effective response will not influence the evaluation of the proposal. Each page of the proposal should state the name of the bidder and the page number.
Respondents must provide the following sections in their proposal. The proposal must not exceed ten (10) pages, not including resumes, schedule of activities/deliverables, or budget proposal.
E. Applicant Qualifications and Experience
• List the applicant organization (name, address, contact person), any partner organization(s) (name, address, contact person), and key individuals who are part of the team and will be working on this project. Resumes for individual team members should be attached to an appendix and do not count toward the page limit.
• For each organization and key individual team member, a description of the activities to be performed and relevant experience.
• Descriptions of relevant projects on which the applicant and, if appropriate, key individuals have worked on in the past.
• Contact information for person(s) whom DOER can contact regarding the applicant’s and, if appropriate, key individuals past performance on relevant projects.
F. Budget
• A budget, broken out by task, staff person, and hourly rate. Respondents must provide project‐based pricing instead of the maximum billing rates established in PRF76.
Respondents must include any and all ancillary services in the project price. DOER under no circumstance will pay additional invoices related to project‐based procurement. Proposals that include partnerships must designate one party as the lead Contractor and identify the team of subcontractors (collectively referred to as subcontractors).
V. PROPOSAL EVALUATION
The selected Contractor shall demonstrate the technical capacity to conduct an evidence-based assessment of the impacts of fossil fuel-free building requirements on housing production and housing affordability demonstrate the experience, ability, and skills to complete projects of this type on time and within budget.
All proposals received by the due date and meeting the requirements established in this RFQ will be reviewed and evaluated by DOER. The evaluation will include, but will not be limited to, the following criteria:
Required qualifications:
1. Housing Economics and Policy Analysis: Demonstrated experience analyzing residential housing production, housing supply, development feasibility, housing costs, and affordability, preferably in Massachusetts or comparable housing markets.
2. Quantitative Research and Program Evaluation: Demonstrated experience conducting statistical analysis, comparative policy evaluation, and analysis of longitudinal datasets.
Experience with quasi-experimental methods, including difference-in-differences analysis or comparable approaches, is desirable.
3. Residential Construction Cost Analysis: Demonstrated expertise evaluating residential construction costs, including the ability to assess the accuracy and comparability of cost estimates and distinguish incremental costs associated with specific building requirements.
4. Affordable Housing Development and Finance: Knowledge of affordable housing development, financing structures, operating costs, and the financial circumstances of low-and moderate-income households.
5. Research Reporting: Demonstrated experience preparing comprehensive analytical reports for public agencies, including documentation of methodologies, assumptions, data limitations, and policy implications.
6. Project Management: Demonstrated ability to manage multidisciplinary research assignments, coordinate with public agencies and external stakeholders, and complete major deliverables within established deadlines.
7. Effectiveness of the proposed approach: The Respondent’s proposed approach demonstrates an understanding of the tasks and a logical approach. Respondent demonstrates understanding and a sound approach to the proposed Scope of Work.
8. Likelihood of proposal to achieve outcomes: Respondent’s proposal, hours allocated to each task, and team composition suggest the likelihood of the proposal to achieve outcomes and produce deliverables on schedule.
9. The extent to which the proposed budget demonstrates the best value to the Commonwealth, including consideration of total cost and hourly rates for team members.
| I. INTRODUCTION |
| A. Massachusetts Department of Energy Resources |
| B. Green Communities Division |
| II. BACKGROUND |
| C. Fossil Fuel-Free Demonstration Program |
| II. PROCUREMENT AND CONTACT INFORMATION |
| A. Type of Procurement |
| B. RFQ Distribution Method |
| C. Massachusetts Public Records Law |
| D. No Guarantee of Resulting Contract |
| E. Questions and Answers |
| F. Contact Information |
| G. Procurement Calendar |
| III. SCOPE OF WORK |
| A. Background and Proposed Activities |
| IV. CONTRACT INFORMATION |
| A. Funding availability/duration of contract |
| B. Contract Expansion |
| C. Contractor’s responsibility and invoicing |
| D. The Commonwealth’s responsibility |
| PROPOSAL REQUIREMENTS |
| E. Applicant Qualifications and Experience |
| F. Budget |
V. PROPOSAL EVALUATION