Cape Horn Substation Upgrades
Solicitation number
240145
Issued by
Skagit County, Washington

About this file

This is a bid solicitation document issued by Public Utility District No. 1 of Skamania County, Washington, for the Cape Horn Substation Upgrades project. The project consists of the expansion and renovation of an existing 115kV to 12.47kV substation located at 682 Canyon Creek Rd., Washougal, Washington, using a two-phase construction approach designed to avoid extended outages of existing feeders. The invitation to bid opened on November 3rd, 2026, at 1:30 PM PST, with a mandatory pre-bid meeting and site visit scheduled for November 25th, 2026, from 9:00 AM to 11:00 AM PST at the PUD's office located at 1492 Wind River Highway, Carson, Washington. Attendance at both the mandatory pre-bid meeting and the Cape Horn Substation site visit is required to qualify for bid submission. The deadline for submitting questions is December 1st, 2026, at 5:00 PM PST, and sealed bids are due by December 15th, 2026, at 2:00 PM PST. Bids must be submitted in sealed envelopes addressed to Melanie Sharp at the PUD's office or mailing address (P.O. Box 500, Carson, Washington 98610) and must include one flash drive containing all electronic documents.

The solicitation document does not provide specific pricing information, contract term details, funding amounts, or information regarding set-asides, incumbents, or renewal options. Contractors should refer to the complete Contract Documents referenced in the solicitation for detailed scope specifications, pricing requirements, and contract terms.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cape Horn Substation Upgrades

Nov 3rd 2026, 1:30PM PST - Dec 15th 2026, 2:00PM PST

Table of Contents

Contents Page #

Project Details 3

1. Bid Submittal 5

Project Details

Project Cape Horn Substation Upgrades

Ref. # 240145

Type ITB

Description This Project consists of the expansion and renovation of an existing 115kV to 12.47kV substation, Cape Horn Substation, located at 682 Canyon Creek Rd., Washougal, WA. The project consists of a two-phase construction approach to be performed without extended outage of existing feeders. The scope of contractor supply and construction are outlined in the Contract Documents.

Open Date Nov 3rd 2026, 1:30PM PST

Questions Due Date Dec 1st 2026, 5:00PM PST

Close Date Dec 15th 2026, 2:00PM PST

Events

Event Name Duration Description

Open Date Nov 3rd 2026, 1:30PM PST Posting date for the Opportunity

Mandatory Pre-Bid Meeting

Nov 25th 2026, 9:00AM PST

- Nov 25th 2026, 11:00AM

PST

A mandatory pre-bid meeting will be held on Wednesday, November 25th, 2026 @ 9:00 AM PDT at the Public Utility District No. 1 of Skamania County located at 1492 Wind RiverHighway, Carson, WA, 98610, to be followed by a mandatory Cape Horn Substation site visit, located at 682 Canyon Creek Rd., Washougal, WA 98671.Interested bidders must attend both the mandatory pre-bid meeting and site visit and sign attendance sheet at both locations to qualify to submit a bid.

Questions Due Date Dec 1st 2026, 5:00PM PST Deadline to submit Questions

Event Name Duration Description

Close Date Dec 15th 2026, 2:00PM PST Deadline for Submissions

1. Bid Submittal

Bids must be submitted in sealed envelopes in accordance with the Instructions to Bidders and identified as “Bid

#240145 - Cape Horn Substation Upgrades”.

Sealed Bids must be hand-delivered or mailed to the OWNER.

Attention: Melanie Sharp

Public Utility District No. 1 of Skamania County

(physical) 1492 Wind River Highway, Carson, WA 98610

(mailing) P. O. Box 500, Carson, WA 98610 Sealed bids must be received no later than 2:00 p.m. PDT, on Tuesday, December 15, 2026.

Sealed Bids must include one flash drive with all electronic documents.

Sealed Bids will be opened at 2:00 p.m. PDT on Tuesday, December 15, 2026 in the PUD’s headquarters office.

Cape Horn Substation Upgrades
Table of Contents
Project Details
Events
1. Bid Submittal