This document is a Timber Sale Prescription from the Michigan Department of Natural Resources - Forest Resources Division for a timber sale opportunity in Compartment 74 in Crystal Falls, Michigan. The project involves single tree selection harvesting and clearcutting on approximately 312 acres of state forest land in Iron County. The contract work can begin immediately and must be completed by September 10, 2023. The document provides details on the legal description, access, timber marking specifications, cruising requirements, and deliverables. It also includes restrictions on the number of markers and the contractor's work schedule for paint supply from the DNR.
The payment for this timber sale will be based on the estimated 312 acres. The document does not mention any set asides, incumbents, funding requirements or sources. It states that the purpose of the sale is for timber harvesting on state forest land managed by the Michigan DNR Forest Resources Division.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 of 4 R4038 (Rev. 03/16/2022)
Michigan Department of Natural Resources – Forest Resources Division
TIMBER SALE PRESCRIPTION
GENERAL
Forest Resources Division Management Unit
Crystal Falls
Sale Name (or prescription name)
Compartment 74
Timber Sale Number (if applicable)
N/A
LOCAL CONTACT
Name
Ed Rice
Email Address
RiceE1@michigan.gov
Telephone
906 221-0226
TIMELINE
Contract Work Can Begin:
Immediately Date: 10/01/2022 Contract Work Must Be Completed By:
09/10/2023
10/1/LEGAL DESCRIPTION
Town
41N
Range
30W
Section(s)
8, 9 & 10
Description
Sec 8: N1/2, N1/2SW, NWSE; Sec 9: NWNW, N1/2NE; Sec 10: NW1/4
Year of Entry
Compartment(s)
12074
Stand Number(s)
4, 6 & 21
Access
Multiple woods roads through industrial forest land, potentially some private - 4WD pickup and/or ATV. County Road 607
ACREAGE (Payment will be made based on these estimated acres) Estimated Acres
312.0 Source
Inventory GPS Other:
TREATMENT & OBJECTIVE
STAND # / VDU # COVER TYPE ACRES INITIAL BA TREATMENT MANAGEMENT OBJECTIVE
4 M9 221.0 100 Single Tree Selection Northern Hardwood
6 A6 6.0 N/A Clearcut Aspen, Mixed Deciduous
21 M9 85.0 100 Single Tree Selection Northern Hardwood
PRESCRIPTION
Stands 4 & 21: Reduce BA to 70 square feet/acre. Remove in order of priority: High risk trees that likely will not survive until the next cutting cycle (20 years), quality sawtimber/veneer trees 18” at DBH or larger, and if needed thin from below to meet the desired stocking. Favor well-formed hard maple and basswood as residual.
Leave 1 to 2 large canopy maple per acre, where present. Capture value of basswood 18” at DBH or larger, do not remove all basswood.
• The eastern portion of Stand 4 has a heavy component of white ash saplings 10’ tall. This area also has a slightly lower BA ranging 90 to 100.
• Do not mark hemlock, oak, yellow birch, black ash, cedar, or white pine. Do not mark adjacent to these species to avoid logging damage.
• Keep components of all tree species and diameter classes in the residual stand.
• All vernal and lowland hardwood areas may have not been identified within the sale area. If any are found during sale set up, buffer these areas a minimum of one tree length.
• In the event a raptor nest(s) is found, follow DNR buffering guidelines. Dependent upon the stand, a portion of the stand may need to be removed.
Stand 6: Mark one white birch and healthy red maple to leave per cruise point, where available.
• Cruise merchantable aspen, maple, white birch, balsam fir, and spruce. Do not cruise yellow birch, oak, black ash, hemlock, or white pine.
2 of 4 R4038 (Rev. 03/16/2022)
PAINT LINES
This is included in the bid This is not included in the bid
Paint line work to be performed: (See attached map for locations)
TYPE OF LINE WORK TO BE DONE PAINT COLOR
Exterior line against private Blue Other:
Exterior line against state Red Other:
Interior payment unit Yellow Red (Double Paint Slashes)
Other: Green Other:
Exclusions to mark and why:
Exclude perennial and intermittent streams if found – buffer these at least 75 feet on each side. If streams are found, contract the sale administrator.
Standards for marking lines against private land:
Double blue paint dots on sides of tree easily viewable from inside the sale area at least 6 feet high on the bole. Blue paint marks may be no more than ½ chain apart; must be easily visible from last paint mark. Paint must be well marked and bright. Necessary property corners have been established. Any existing blue line from adjacent landowner logging operations must be fully ran and verified before accepting.
BOUNDARY GPS
This is included in the bid This is not included in the bid GPS data files will be provided
FEATURE WORK TO BE DONE NOTES
Volume Determination Unit (VDU)
Payment Unit (PU) Double red paint slashes on both sides of tree
Exclusions
Special Instructions:
All painted boundaries must be GPS’d in MobileMap and the tracks delivered to the DNR.
TIMBER MARKING SPECIFICATIONS
This is included in the bid This is not included in the bid
Total Merchantable Residual BA (Basal Area): 70 (Minimum: 60 to Maximum: 80)
TREATMENT NUMBER SIZE
Regeneration Gaps Per Acre:
Girdled Trees Per Acre:
PRODUCT MARKING SYMBOL MINIMUM DBH TOP DOB
Sawlogs Orange slash 10.6” 10.0”
Pulpwood Orange slash 4.6” 4.0”
TYPE OF WORK WORK TO BE DONE PAINT COLOR
Trees marked to leave Green Other:
Trees marked to cut Orange Other:
Special Marking Instructions:
Bole marks will be a single paint slash well marked on both sides of the tree. Keep bole marks high (approx. 6 feet).
Stump marks must be well marked in order to last several years and intersect the ground. If paint marks are not deemed acceptable to remain distinct over several years, remarking will be required.
3 of 4 R4038 (Rev. 03/16/2022)
TIMBER CRUISING SPECIFICATIONS
This is included in the bid This is not included in the bid Cruise layout file will be provided
TOTAL NUMBER OF CRUISE POINTS ~167 NOTE: FOR EACH VDU, SELECT A BAF THAT AVERAGES 4-8 TREES PER POINT
CRUISE DESIGN (MobileMap)
Stand #4 Stand #21
Plots per acre 1 : 2.3 Plots per acre 1 : 1.3
Management type State Forest Management type State Forest
District WUP District WUP
FMU 12 FMU 12
Compartment 074 Compartment 074
VDU Number 4 VDU Number 21
FCS Key 12074004 FCS Key 12074021
Contract or State Contract Contract or State Contract
Purpose Timber Sale Purpose Timber Sale
Plot Type BAF + resid Plot Type BAF + resid
BAF or Plot Size 10 BAF or Plot Size 10
Sample Type Sample Tree Ratio (STR) Sample Type Sample Tree Ratio (STR)
Sample Tree Ratios All Pulp - 1:5
All Sawtimber - 1:2 Sample Tree Ratios
All Pulp - 1:5 All Sawtimber - 1:2
Status Planned Status Planned
Residual Plot Density 1 : 2 Residual Plot Density 1 : 1.6
Residual BAF 10 Residual BAF 10
Stump Height 0.5 Stump Height 0.5
Stand #6 Stand # / VDU #
Plots per acre 1 : 1 Plots per acre
Management type State Forest Management type
District WUP District
FMU 12 FMU
Compartment 074 Compartment
VDU Number 6 VDU Number
FCS Key 12074006 FCS Key
Contract or State Contract Contract or State
Purpose Timber Sale Purpose
Plot Type BAF Plot Type
BAF or Plot Size 10 BAF or Plot Size
Sample Type Sample Tree Ratio (STR) Sample Type
Sample Tree Ratios All Pulp - 1:10 Sample Tree Ratios
Status Planned Status
Residual Plot Density N/A Residual Plot Density
Residual BAF 10 Residual BAF
Stump Height 0.5 Stump Height
4 of 4 R4038 (Rev. 03/16/2022)
RESTRICTIONS
1. Forest Resources Division must be able to identify who did what on the timber sale.
2. The contractor may not have more than two markers in one cruise unit without prior approval.
3. Each marker should have an assigned area to mark (not strips).
PAINT
4. Call Ed Rice at (906) 221-0226 to make arrangements for paint.
5. Paint will be supplied from Crystal Falls Field Office.
6. Contractor’s work schedule must coincide with the DNR work schedule for paint supply.
7. The DNR will not be available on weekends or evenings.
DELIVERABLES
8. A list of names that marked or cruised each cruise unit.
9. A summary of paint used (in quarts).
10. All data, cruise and GPS, must be uploaded from MobileMap to InventoryManager.
Additional Information