DNR Central UP Trail Dust Control Pricing Schedule B.docx
DOCX document 36 KB Posted
- Attached to
- Central UP ORV Trail dust control contract
- Solicitation number
- RFP-751-190000001761-1
- Issued by
- Michigan
About this file
This is a pricing schedule (Schedule B) for the Michigan Department of Natural Resources (DNR) RFP #190000001761 for dust control product application on ORV trails and railroad grades in the Central Upper Peninsula. The bid submission deadline is May 8, 2019, at 3:00 p.m. local time. The contract includes the application of three types of dust control products: Penetrating Emulsion Prime (PEP) with an estimated quantity of 18,642 gallons, Calcium Chloride (CC) with 15,048 gallons, and Magnesium Chloride (MC) with 25,050 gallons over a three-year contract term. The service component includes application across 8.55 miles.
Pricing must be submitted through Michigan's SIGMAVSS system (www.michigan.gov/sigmavss) and must include all costs, including one-time charges, set-up fees, and potential costs. Quick payment terms are encouraged, excluding processing time for payment receipt. Contractors must certify that their prices were determined independently without consultation with other contractors. The pricing structure requires unit prices per gallon for each dust control product and a per-mile rate for application services, including all labor, equipment, and miscellaneous charges.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| DNR Central UP Dust Control SOW Schedule A.doc | DOC document | |
| RFP 19-1761 DNR Central U.P. Trail Dust Control.docx | DOCX document | |
| Standard Contract Terms.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Enter company name here.
STATE OF MICHIGAN
Application of Dust Control Product on ORV Trails and Railroad Grades – Central Upper Peninsula
RFP #190000001761
Bids Due: Wednesday, May 8, 2019 at 3:00 p.m. Local Time
SCHEDULE B
PRICING
This Exhibit is provided for informational purposes only. Price quotes must be entered and submitted through www.michigan.gov/sigmavss
1. Price proposals must include all costs, including but not limited to, any one-time or set-up charges, fees, and potential costs that Contractor may charge the State.
2. The Contractor is encouraged to offer quick payment terms. The number of days must not include processing time for payment to be received by the Contractor's financial institution.
3. By submitting its proposal, the Contractor certifies that the prices were arrived at independently, and without consultation, communication, or agreement with any other Contractor.
| Description |
| Unit of Measure |
| Estimated Qty for 3-yr Contract |
| Unit Price |
| Extended Price |
| Penetrating Emulsion Prime; (PEP) Price Per gallon |
| Gallon |
| 18,642 |
| $ |
Per gallon
| Calcium Chloride, (CC) Price Per Gallon |
| Gallon |
| 15,048 |
| $ |
Per gallon
| Magnesium Chloride, (MC) Price Per Gallon |
| Gallon |
| 25,050 |
| $ |
Per gallon
| Application Services; price per mile for all labor, equipment, misc. charges for applying PEP, CC, or MC at the rates specified in the Statement of Work. |
| Mile |
| 8.55 |
| $ |
Per mile
| Total for Contract Term |
| $ |
Version 1 Revised Date: 7/28/2017
File details come from the government source that posted it. Updated .