This document is a Contractor Special Conditions requirement for work at Naval Nuclear Power Training Unit (NPTU) Charleston, a Naval Reactors activity located in Goose Creek, South Carolina on Joint Base Charleston-Weapons Station and subject to Executive Order 12344.

Contractors must submit a Plan of Action no later than ten days prior to the work start date detailing procedural steps, service interruptions, energy isolations, required NPTU support, safety hazard mitigation, and environmental concerns, with NPTU approval required before any onsite work begins. Daily coordination is mandatory, with contractors meeting the Site Work Controls Officer (WCO) before commencing work each day and again at day's end to report status and progress; work cannot begin without WCO authorization. Security access requires all contractor personnel to submit visit requests at least five business days in advance, or ten business days for controlled sections of the facility. Personal electronic devices are prohibited within NPTU's security enclosure, with restricted items including cameras, cell phones, personal computers, radioactive materials, classified material, radio transmitters and receivers, personnel monitoring devices, and optical and magnetic media unless prior authorization is granted. Medical emergencies must be immediately reported to NPTU Security at 794-3333 or (843) 794-3095, followed by notification to contractor management and the WCO. In severe weather events such as hurricanes, work will be suspended at least 72 hours prior to projected landfall, and contractors must remove all vehicles, tools, and equipment from the site within that timeframe, with work resumption dependent on storm damage assessment.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NAVAL NUCLEAR POWER TRAINING UNIT (NPTU) CHARLESTON

CONTRACTOR SPECIAL CONDITIONS

Contractors are responsible for compliance with this document and should read it in its entirety

NPTU CHARLESTON 1 of 1 12 Aug 2020

1) Work Site. NPTU Charleston is located in Goose Creek, South Carolina on Joint Base Charleston-Weapons Station (JB CHS-WS). NPTU is a Naval Reactors activity and subject to the requirements of Executive Order 12344.

Site Work Controls Officer (WCO) Cell: (843) 509-6947 Site Operations Group PM Cell: (843) 324-6677

NPTU Security (843) 794-3095 794-3333 (On-site Emergency Only)

2) Required Submittals. No later than ten days prior to Work Start Date, Contractors must provide a Plan of Action document that contains a detailed procedure for the work about to be conducted including the following: Performance of procedural steps, Interruption or use of services, Use of energy isolations, Required NPTU support, Mitigation of safety hazards, and

Environmental Concerns. Further details of each required portion of this document are included below. NPTU must approve the Plan of Action prior to any work being performed onsite.

3) Work Induction and Completion. The contractor shall meet with the WCO prior to commencing work each day, to inform the WCO of contractor personnel on-site and the work planned for the day. Work may not begin until authorized by the WCO. At the end of each workday, the contractor shall contact the WCO to inform them of status and progress of the job.

4) Security. NPTU is a high security facility with its own security force and access requirements. In order to gain authorized access to NPTU, all contractor personnel must submit a visit request at least five business days prior to arriving at NPTU. If it is determined the contractor must work in a controlled section of NPTU, requests should be routed at least ten business days in advance to ensure approval before arrival.

5) Contraband Material. Personal Electronic Devices (PEDs) are prohibited inside of

NPTU’s security enclosure. The following items are restricted (i.e. will be confiscated or denied access) unless prior authorization is granted: cameras and film, cell phones, personal computers and laptops, radioactive materials, classified material, radio transmitters and receivers, personnel monitoring devices, and optical and magnetic media.

6) Medical Emergency Action. Should a serious accident occur, immediately notify NPTU

Security at 794-3333 or (843) 794-3095. Subsequently, notify contractor management and the WCO.

7) Weather Related Incidents. In the event of severe inclement weather (e.g. hurricane), work at NPTU will be suspended at least 72 hours prior to the storm’s projected landfall. The contractor is expected to have all vehicles, tools, and equipment removed from NPTU 72 hours prior to the storm’s projected landfall. Resumption of contractor work will be dependent on the severity of the storm’s damage. Contractors can contact the WCO for an expected time to return to site after the threat of severe weather has passed.