DG1330-11-RP-0009 - WCOSS RFP - Draft - Attachment 2 - WCOSS Cost Proposal Template - 20101112.xlsx

XLSX spreadsheet 107 KB Posted

Attached to
DOC NOAA NCEP Weather and Climate Operational Supercomputing System (WCOSS) DRAFT Request For Proposal
Solicitation number
DG1330-11-RP-0009
Issued by

About this file

DRAFT RFP Attachment 2 Cost Proposal Template

View the file

Other files

File Type Posted
DG1330-11-RP-0009 - WCOSS DRAFT RFP.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PrimaryFacility

Note: THIS FORMAT MAY BE TAILORED BY THE CONTRACTOR to include other information to support total cost elements and price.1
Offeror may elect to use tab titled "Sheet 2" and other sheet tabs. Justification for cost to be provided in 'Notes' as necessary for cost evaluation.2
The offeror may not tailor this format to exclude necessary cost information. The offeror may add rows and/or columns.3
CONTRACTOR:DUNS No.:DATE:4
ADDRESS:5
FSS #:for information purposesFSS web site:ODC - Other Direct Cost6
POC:nametitleemailtelephonePOP - Period of Performance7
8
PRIMARY FACILITY - PERIOD OF PERFOMANCE (example: April 2011 - Dec 2011)9
abcdefghIjkl10
Section 1:UNBURDENEDSection 1.1:Fully Burdened11
Direct Laborif applicableDirect Laborif applicable12
LaborLaborExtendedLaborLaborLaborExtendedLabor13
POPCategoryRateHoursLaborNotesPOPCategoryRateHoursLaborNotes14
App mgr125$ - 0$ - 015
$ - 0$ - 016
$ - 0$ - 017
$ - 0$ - 018
$ - 0$ - 019
$ - 0$ - 020
$ - 0$ - 021
TOTAL$ - 0TOTAL$ - 022
23
Section 1.2:Labor Fringe/OHIf applicable,Total Labor24
Labor CategoryFringe BenefitExtendedIAW FAR 31.?Labor CategoryBenefitExtendedIAW FAR 31.?Overhead25
POPor BaseOverhead RateCostNotesor BaseRateCostNotesCost26
$ - 0$ - 0$ - 027
$ - 0$ - 0$ - 028
$ - 0$ - 0$ - 029
$ - 0$ - 0$ - 030
$ - 0$ - 0$ - 031
$ - 0$ - 0$ - 032
$ - 0$ - 0$ - 033
TOTAL$ - 0$ - 0$ - 034
35
Section 2:Vendor/Subcontract Cost36
Vendor NameService or Item DescriptionUnit PriceQuantityExtended CostQuote No., dateNoteIAW PWS paragraph37
$ - 0$ - 038
$ - 0$ - 039
$ - 0$ - 040
$ - 0$ - 041
$ - 0$ - 042
$ - 0$ - 043
$ - 0$ - 044
$ - 0$ - 045
$ - 0$ - 046
TOTAL$ - 0$ - 047
48
Section 3:Travel (in accordance with Joint Travel Regulations)49
POPFrom LocationTo LocationLabor CategoryNumber of employeesTravel CostLodgingOther Travel CostQuote No., DateNotesIAW PWS paragraph50
$ - 051
$ - 052
$ - 053
$ - 054
$ - 055
$ - 056
$ - 057
$ - 058
$ - 059
TOTAL$ - 060
61
Section 4:Other Cost Elements (not previously included above)62
Overhead/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved? Yes/NoNotes63
$ - 064
$ - 0If Applicable:65
$ - 0FAR 30.201:NameTitleAddressPhone66
$ - 0or Administrative Contracting Officer/ACO67
$ - 0Auditor:NameTitleAddressPhone68
$ - 0or Defense Contract Audit Agency69
$ - 070
$ - 0Billing Rates and/or Forward Pricing Rate Agreement may also be provided.71
$ - 072
TOTAL$ - 073
74
Section 5:FCCM (Facility Cost of Money)75
FCCM/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved?NotesOther Information if applicable to Offeror:If applicable, verifiable Audit Results:76
$ - 0Disclosure Statement (FAR 30.202)77
$ - 0Purchasing System (FAR 44.305)78
$ - 0Accounting System ( FAR 42.1)79
$ - 080
TOTAL$ - 081
82
Section 6:General and Administrative (G&A)83
G&AApplicable RateBaseRate X BaseACO/DCAA Approved?Notes84
$ - 085
$ - 086
$ - 087
$ - 088
TOTAL$ - 089
90
Section 7:Profit91
ProfitApplicable RateBaseRate X BaseNotes92
$ - 093
$ - 094
$ - 095
$ - 096
TOTAL$ - 097
98
PRIMARY FACILITYSection 1.1Section 2Section 3Section 4Section 5Section 6Section 7Grand Total99
TOTAL/POP APR2011-DEC2011$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0100
101
102
PRIMARY FACILITY - PERIOD OF PERFOMANCE (example: JAN2012-DEC2012)103
abcdefghIjkl104
Section 1:UNBURDENEDSection 1.1:Fully Burdened105
Direct Laborif applicableDirect Laborif applicable106
LaborLaborExtendedLaborLaborLaborExtendedLabor107
POPCategoryRateHoursLaborNotesPOPCategoryRateHoursLaborNotes108
$ - 0$ - 0109
$ - 0$ - 0110
$ - 0$ - 0111
$ - 0$ - 0112
$ - 0$ - 0113
$ - 0$ - 0114
$ - 0$ - 0115
TOTAL$ - 0TOTAL$ - 0116
117
Section 1.2:Labor Fringe/OHIf applicable,Total Labor118
Labor CategoryFringe BenefitExtendedIAW FAR 31.?Labor CategoryBenefitExtendedIAW FAR 31.?Overhead119
POPor BaseOverhead RateCostNotesor BaseRateCostNotesCost120
$ - 0$ - 0$ - 0121
$ - 0$ - 0$ - 0122
$ - 0$ - 0$ - 0123
$ - 0$ - 0$ - 0124
$ - 0$ - 0$ - 0125
$ - 0$ - 0$ - 0126
$ - 0$ - 0$ - 0127
TOTAL$ - 0$ - 0$ - 0128
129
Section 2:Vendor/Subcontract Cost130
Vendor NameService or Item DescriptionUnit PriceQuantityExtended CostQuote No., dateNoteIAW PWS paragraph131
$ - 0$ - 0132
$ - 0$ - 0133
$ - 0$ - 0134
$ - 0$ - 0135
$ - 0$ - 0136
$ - 0$ - 0137
$ - 0$ - 0138
$ - 0$ - 0139
$ - 0$ - 0140
TOTAL$ - 0$ - 0141
142
Section 3:Travel (in accordance with Joint Travel Regulations)143
POPFrom LocationTo LocationLabor CategoryNumber of employeesTravel CostLodgingOther Travel CostQuote No., DateNotesIAW PWS paragraph144
$ - 0145
$ - 0146
$ - 0147
$ - 0148
$ - 0149
$ - 0150
$ - 0151
$ - 0152
$ - 0153
TOTAL$ - 0154
155
Section 4:Other Cost Elements (not previously included above)156
Overhead/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved? Yes/NoNotes157
$ - 0158
$ - 0If Applicable:159
$ - 0FAR 30.201:NameTitleAddressPhone160
$ - 0or Administrative Contracting Officer/ACO161
$ - 0Auditor:NameTitleAddressPhone162
$ - 0or Defense Contract Audit Agency163
$ - 0164
$ - 0Billing Rates and/or Forward Pricing Rate Agreement may also be provided.165
$ - 0166
TOTAL$ - 0167
168
Section 5:FCCM (Facility Cost of Money)169
FCCM/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved?NotesOther Information if applicable to Offeror:If applicable, verifiable Audit Results:170
$ - 0Disclosure Statement (FAR 30.202)171
$ - 0Purchasing System (FAR 44.305)172
$ - 0Accounting System ( FAR 42.1)173
$ - 0174
TOTAL$ - 0175
176
Section 6:General and Administrative (G&A)177
G&AApplicable RateBaseRate X BaseACO/DCAA Approved?Notes178
$ - 0179
$ - 0180
$ - 0181
$ - 0182
TOTAL$ - 0183
184
Section 7:Profit185
ProfitApplicable RateBaseRate X BaseNotes186
$ - 0187
$ - 0188
$ - 0189
$ - 0190
TOTAL$ - 0191
192
PRIMARY FACILITYSection 1.1Section 2Section 3Section 4Section 5Section 6Section 7Grand Total193
TOTAL/POP JAN2012 - DEC2012$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0194
195
196
PRIMARY FACILITY - PERIOD OF PERFOMANCE (example: JAN2013-DEC2013)197
abcdefghIjkl198
Section 1:UNBURDENEDSection 1.1:Fully Burdened199
Direct Laborif applicableDirect Laborif applicable200
LaborLaborExtendedLaborLaborLaborExtendedLabor201
POPCategoryRateHoursLaborNotesPOPCategoryRateHoursLaborNotes202
$ - 0$ - 0203
$ - 0$ - 0204
$ - 0$ - 0205
$ - 0$ - 0206
$ - 0$ - 0207
$ - 0$ - 0208
$ - 0$ - 0209
TOTAL$ - 0TOTAL$ - 0210
211
Section 1.2:Labor Fringe/OHIf applicable,Total Labor212
Labor CategoryFringe BenefitExtendedIAW FAR 31.?Labor CategoryBenefitExtendedIAW FAR 31.?Overhead213
POPor BaseOverhead RateCostNotesor BaseRateCostNotesCost214
$ - 0$ - 0$ - 0215
$ - 0$ - 0$ - 0216
$ - 0$ - 0$ - 0217
$ - 0$ - 0$ - 0218
$ - 0$ - 0$ - 0219
$ - 0$ - 0$ - 0220
$ - 0$ - 0$ - 0221
TOTAL$ - 0$ - 0$ - 0222
223
Section 2:Vendor/Subcontract Cost224
Vendor NameService or Item DescriptionUnit PriceQuantityExtended CostQuote No., dateNoteIAW PWS paragraph225
$ - 0$ - 0226
$ - 0$ - 0227
$ - 0$ - 0228
$ - 0$ - 0229
$ - 0$ - 0230
$ - 0$ - 0231
$ - 0$ - 0232
$ - 0$ - 0233
$ - 0$ - 0234
TOTAL$ - 0$ - 0235
236
Section 3:Travel (in accordance with Joint Travel Regulations)237
POPFrom LocationTo LocationLabor CategoryNumber of employeesTravel CostLodgingOther Travel CostQuote No., DateNotesIAW PWS paragraph238
$ - 0239
$ - 0240
$ - 0241
$ - 0242
$ - 0243
$ - 0244
$ - 0245
$ - 0246
$ - 0247
TOTAL$ - 0248
249
Section 4:Other Cost Elements (not previously included above)250
Overhead/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved? Yes/NoNotes251
$ - 0252
$ - 0If Applicable:253
$ - 0FAR 30.201:NameTitleAddressPhone254
$ - 0or Administrative Contracting Officer/ACO255
$ - 0Auditor:NameTitleAddressPhone256
$ - 0or Defense Contract Audit Agency257
$ - 0258
$ - 0Billing Rates and/or Forward Pricing Rate Agreement may also be provided.259
$ - 0260
TOTAL$ - 0261
262
Section 5:FCCM (Facility Cost of Money)263
FCCM/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved?NotesOther Information if applicable to Offeror:If applicable, verifiable Audit Results:264
$ - 0Disclosure Statement (FAR 30.202)265
$ - 0Purchasing System (FAR 44.305)266
$ - 0Accounting System ( FAR 42.1)267
$ - 0268
TOTAL$ - 0269
270
Section 6:General and Administrative (G&A)271
G&AApplicable RateBaseRate X BaseACO/DCAA Approved?Notes272
$ - 0273
$ - 0274
$ - 0275
$ - 0276
TOTAL$ - 0277
278
Section 7:Profit279
ProfitApplicable RateBaseRate X BaseNotes280
$ - 0281
$ - 0282
$ - 0283
$ - 0284
TOTAL$ - 0285
286
PRIMARY FACILITYSection 1.1Section 2Section 3Section 4Section 5Section 6Section 7Grand Total287
TOTAL/POP JAN2013 - DEC2013$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0288
289
290
PRIMARY FACILITY - PERIOD OF PERFOMANCE (example: JAN2014-DEC2014)291
abcdefghIjkl292
Section 1:UNBURDENEDSection 1.1:Fully Burdened293
Direct Laborif applicableDirect Laborif applicable294
LaborLaborExtendedLaborLaborLaborExtendedLabor295
POPCategoryRateHoursLaborNotesPOPCategoryRateHoursLaborNotes296
$ - 0$ - 0297
$ - 0$ - 0298
$ - 0$ - 0299
$ - 0$ - 0300
$ - 0$ - 0301
$ - 0$ - 0302
$ - 0$ - 0303
TOTAL$ - 0TOTAL$ - 0304
305
Section 1.2:Labor Fringe/OHIf applicable,Total Labor306
Labor CategoryFringe BenefitExtendedIAW FAR 31.?Labor CategoryBenefitExtendedIAW FAR 31.?Overhead307
POPor BaseOverhead RateCostNotesor BaseRateCostNotesCost308
$ - 0$ - 0$ - 0309
$ - 0$ - 0$ - 0310
$ - 0$ - 0$ - 0311
$ - 0$ - 0$ - 0312
$ - 0$ - 0$ - 0313
$ - 0$ - 0$ - 0314
$ - 0$ - 0$ - 0315
TOTAL$ - 0$ - 0$ - 0316
317
Section 2:Vendor/Subcontract Cost318
Vendor NameService or Item DescriptionUnit PriceQuantityExtended CostQuote No., dateNoteIAW PWS paragraph319
$ - 0$ - 0320
$ - 0$ - 0321
$ - 0$ - 0322
$ - 0$ - 0323
$ - 0$ - 0324
$ - 0$ - 0325
$ - 0$ - 0326
$ - 0$ - 0327
$ - 0$ - 0328
TOTAL$ - 0$ - 0329
330
Section 3:Travel (in accordance with Joint Travel Regulations)331
POPFrom LocationTo LocationLabor CategoryNumber of employeesTravel CostLodgingOther Travel CostQuote No., DateNotesIAW PWS paragraph332
$ - 0333
$ - 0334
$ - 0335
$ - 0336
$ - 0337
$ - 0338
$ - 0339
$ - 0340
$ - 0341
TOTAL$ - 0342
343
Section 4:Other Cost Elements (not previously included above)344
Overhead/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved? Yes/NoNotes345
$ - 0346
$ - 0If Applicable:347
$ - 0FAR 30.201:NameTitleAddressPhone348
$ - 0or Administrative Contracting Officer/ACO349
$ - 0Auditor:NameTitleAddressPhone350
$ - 0or Defense Contract Audit Agency351
$ - 0352
$ - 0Billing Rates and/or Forward Pricing Rate Agreement may also be provided.353
$ - 0354
TOTAL$ - 0355
356
Section 5:FCCM (Facility Cost of Money)357
FCCM/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved?NotesOther Information if applicable to Offeror:If applicable, verifiable Audit Results:358
$ - 0Disclosure Statement (FAR 30.202)359
$ - 0Purchasing System (FAR 44.305)360
$ - 0Accounting System ( FAR 42.1)361
$ - 0362
TOTAL$ - 0363
364
Section 6:General and Administrative (G&A)365
G&AApplicable RateBaseRate X BaseACO/DCAA Approved?Notes366
$ - 0367
$ - 0368
$ - 0369
$ - 0370
TOTAL$ - 0371
372
Section 7:Profit373
ProfitApplicable RateBaseRate X BaseNotes374
$ - 0375
$ - 0376
$ - 0377
$ - 0378
TOTAL$ - 0379
380
PRIMARY FACILITYSection 1.1Section 2Section 3Section 4Section 5Section 6Section 7Grand Total381
TOTAL/POP JAN2014 - DEC2014$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0382
383
384
PRIMARY FACILITY - PERIOD OF PERFOMANCE (example: JAN2015-DEC2015)385
abcdefghIjkl386
Section 1:UNBURDENEDSection 1.1:Fully Burdened387
Direct Laborif applicableDirect Laborif applicable388
LaborLaborExtendedLaborLaborLaborExtendedLabor389
POPCategoryRateHoursLaborNotesPOPCategoryRateHoursLaborNotes390
$ - 0$ - 0391
$ - 0$ - 0392
$ - 0$ - 0393
$ - 0$ - 0394
$ - 0$ - 0395
$ - 0$ - 0396
$ - 0$ - 0397
TOTAL$ - 0TOTAL$ - 0398
399
Section 1.2:Labor Fringe/OHIf applicable,Total Labor400
Labor CategoryFringe BenefitExtendedIAW FAR 31.?Labor CategoryBenefitExtendedIAW FAR 31.?Overhead401
POPor BaseOverhead RateCostNotesor BaseRateCostNotesCost402
$ - 0$ - 0$ - 0403
$ - 0$ - 0$ - 0404
$ - 0$ - 0$ - 0405
$ - 0$ - 0$ - 0406
$ - 0$ - 0$ - 0407
$ - 0$ - 0$ - 0408
$ - 0$ - 0$ - 0409
TOTAL$ - 0$ - 0$ - 0410
411
Section 2:Vendor/Subcontract Cost412
Vendor NameService or Item DescriptionUnit PriceQuantityExtended CostQuote No., dateNoteIAW PWS paragraph413
$ - 0$ - 0414
$ - 0$ - 0415
$ - 0$ - 0416
$ - 0$ - 0417
$ - 0$ - 0418
$ - 0$ - 0419
$ - 0$ - 0420
$ - 0$ - 0421
$ - 0$ - 0422
TOTAL$ - 0$ - 0423
424
Section 3:Travel (in accordance with Joint Travel Regulations)425
POPFrom LocationTo LocationLabor CategoryNumber of employeesTravel CostLodgingOther Travel CostQuote No., DateNotesIAW PWS paragraph426
$ - 0427
$ - 0428
$ - 0429
$ - 0430
$ - 0431
$ - 0432
$ - 0433
$ - 0434
$ - 0435
TOTAL$ - 0436
437
Section 4:Other Cost Elements (not previously included above)438
Overhead/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved? Yes/NoNotes439
$ - 0440
$ - 0If Applicable:441
$ - 0FAR 30.201:NameTitleAddressPhone442
$ - 0or Administrative Contracting Officer/ACO443
$ - 0Auditor:NameTitleAddressPhone444
$ - 0or Defense Contract Audit Agency445
$ - 0446
$ - 0Billing Rates and/or Forward Pricing Rate Agreement may also be provided.447
$ - 0448
TOTAL$ - 0449
450
Section 5:FCCM (Facility Cost of Money)451
FCCM/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved?NotesOther Information if applicable to Offeror:If applicable, verifiable Audit Results:452
$ - 0Disclosure Statement (FAR 30.202)453
$ - 0Purchasing System (FAR 44.305)454
$ - 0Accounting System ( FAR 42.1)455
$ - 0456
TOTAL$ - 0457
458
Section 6:General and Administrative (G&A)459
G&AApplicable RateBaseRate X BaseACO/DCAA Approved?Notes460
$ - 0461
$ - 0462
$ - 0463
$ - 0464
TOTAL$ - 0465
466
Section 7:Profit467
ProfitApplicable RateBaseRate X BaseNotes468
$ - 0469
$ - 0470
$ - 0471
$ - 0472
TOTAL$ - 0473
474
PRIMARY FACILITYSection 1.1Section 2Section 3Section 4Section 5Section 6Section 7Grand Total475
TOTAL/POP JAN2015 - DEC2015$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0476
477
478
PRIMARY FACILITY - PERIOD OF PERFOMANCE (example: JAN2016-DEC2016)479
abcdefghIjkl480
Section 1:UNBURDENEDSection 1.1:Fully Burdened481
Direct Laborif applicableDirect Laborif applicable482
LaborLaborExtendedLaborLaborLaborExtendedLabor483
POPCategoryRateHoursLaborNotesPOPCategoryRateHoursLaborNotes484
$ - 0$ - 0485
$ - 0$ - 0486
$ - 0$ - 0487
$ - 0$ - 0488
$ - 0$ - 0489
$ - 0$ - 0490
$ - 0$ - 0491
TOTAL$ - 0TOTAL$ - 0492
493
Section 1.2:Labor Fringe/OHIf applicable,Total Labor494
Labor CategoryFringe BenefitExtendedIAW FAR 31.?Labor CategoryBenefitExtendedIAW FAR 31.?Overhead495
POPor BaseOverhead RateCostNotesor BaseRateCostNotesCost496
$ - 0$ - 0$ - 0497
$ - 0$ - 0$ - 0498
$ - 0$ - 0$ - 0499
$ - 0$ - 0$ - 0500
$ - 0$ - 0$ - 0501
$ - 0$ - 0$ - 0502
$ - 0$ - 0$ - 0503
TOTAL$ - 0$ - 0$ - 0504
505
Section 2:Vendor/Subcontract Cost506
Vendor NameService or Item DescriptionUnit PriceQuantityExtended CostQuote No., dateNoteIAW PWS paragraph507
$ - 0$ - 0508
$ - 0$ - 0509
$ - 0$ - 0510
$ - 0$ - 0511
$ - 0$ - 0512
$ - 0$ - 0513
$ - 0$ - 0514
$ - 0$ - 0515
$ - 0$ - 0516
TOTAL$ - 0$ - 0517
518
Section 3:Travel (in accordance with Joint Travel Regulations)519
POPFrom LocationTo LocationLabor CategoryNumber of employeesTravel CostLodgingOther Travel CostQuote No., DateNotesIAW PWS paragraph520
$ - 0521
$ - 0522
$ - 0523
$ - 0524
$ - 0525
$ - 0526
$ - 0527
$ - 0528
$ - 0529
TOTAL$ - 0530
531
Section 4:Other Cost Elements (not previously included above)532
Overhead/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved? Yes/NoNotes533
$ - 0534
$ - 0If Applicable:535
$ - 0FAR 30.201:NameTitleAddressPhone536
$ - 0or Administrative Contracting Officer/ACO537
$ - 0Auditor:NameTitleAddressPhone538
$ - 0or Defense Contract Audit Agency539
$ - 0540
$ - 0Billing Rates and/or Forward Pricing Rate Agreement may also be provided.541
$ - 0542
TOTAL$ - 0543
544
Section 5:FCCM (Facility Cost of Money)545
FCCM/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved?NotesOther Information if applicable to Offeror:If applicable, verifiable Audit Results:546
$ - 0Disclosure Statement (FAR 30.202)547
$ - 0Purchasing System (FAR 44.305)548
$ - 0Accounting System ( FAR 42.1)549
$ - 0550
TOTAL$ - 0551
552
Section 6:General and Administrative (G&A)553
G&AApplicable RateBaseRate X BaseACO/DCAA Approved?Notes554
$ - 0555
$ - 0556
$ - 0557
$ - 0558
TOTAL$ - 0559
560
Section 7:Profit561
ProfitApplicable RateBaseRate X BaseNotes562
$ - 0563
$ - 0564
$ - 0565
$ - 0566
TOTAL$ - 0567
568
PRIMARY FACILITYSection 1.1Section 2Section 3Section 4Section 5Section 6Section 7Grand Total569
TOTAL/POP JAN2016 - DEC2016$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0570
571
572
PRIMARY FACILITY - PERIOD OF PERFOMANCE (example: JAN2017-DEC2017)573
abcdefghIjkl574
Section 1:UNBURDENEDSection 1.1:Fully Burdened575
Direct Laborif applicableDirect Laborif applicable576
LaborLaborExtendedLaborLaborLaborExtendedLabor577
POPCategoryRateHoursLaborNotesPOPCategoryRateHoursLaborNotes578
$ - 0$ - 0579
$ - 0$ - 0580
$ - 0$ - 0581
$ - 0$ - 0582
$ - 0$ - 0583
$ - 0$ - 0584
$ - 0$ - 0585
TOTAL$ - 0TOTAL$ - 0586
587
Section 1.2:Labor Fringe/OHIf applicable,Total Labor588
Labor CategoryFringe BenefitExtendedIAW FAR 31.?Labor CategoryBenefitExtendedIAW FAR 31.?Overhead589
POPor BaseOverhead RateCostNotesor BaseRateCostNotesCost590
$ - 0$ - 0$ - 0591
$ - 0$ - 0$ - 0592
$ - 0$ - 0$ - 0593
$ - 0$ - 0$ - 0594
$ - 0$ - 0$ - 0595
$ - 0$ - 0$ - 0596
$ - 0$ - 0$ - 0597
TOTAL$ - 0$ - 0$ - 0598
599
Section 2:Vendor/Subcontract Cost600
Vendor NameService or Item DescriptionUnit PriceQuantityExtended CostQuote No., dateNoteIAW PWS paragraph601
$ - 0$ - 0602
$ - 0$ - 0603
$ - 0$ - 0604
$ - 0$ - 0605
$ - 0$ - 0606
$ - 0$ - 0607
$ - 0$ - 0608
$ - 0$ - 0609
$ - 0$ - 0610
TOTAL$ - 0$ - 0611
612
Section 3:Travel (in accordance with Joint Travel Regulations)613
POPFrom LocationTo LocationLabor CategoryNumber of employeesTravel CostLodgingOther Travel CostQuote No., DateNotesIAW PWS paragraph614
$ - 0615
$ - 0616
$ - 0617
$ - 0618
$ - 0619
$ - 0620
$ - 0621
$ - 0622
$ - 0623
TOTAL$ - 0624
625
Section 4:Other Cost Elements (not previously included above)626
Overhead/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved? Yes/NoNotes627
$ - 0628
$ - 0If Applicable:629
$ - 0FAR 30.201:NameTitleAddressPhone630
$ - 0or Administrative Contracting Officer/ACO631
$ - 0Auditor:NameTitleAddressPhone632
$ - 0or Defense Contract Audit Agency633
$ - 0634
$ - 0Billing Rates and/or Forward Pricing Rate Agreement may also be provided.635
$ - 0636
TOTAL$ - 0637
638
Section 5:FCCM (Facility Cost of Money)639
FCCM/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved?NotesOther Information if applicable to Offeror:If applicable, verifiable Audit Results:640
$ - 0Disclosure Statement (FAR 30.202)641
$ - 0Purchasing System (FAR 44.305)642
$ - 0Accounting System ( FAR 42.1)643
$ - 0644
TOTAL$ - 0645
646
Section 6:General and Administrative (G&A)647
G&AApplicable RateBaseRate X BaseACO/DCAA Approved?Notes648
$ - 0649
$ - 0650
$ - 0651
$ - 0652
TOTAL$ - 0653
654
Section 7:Profit655
ProfitApplicable RateBaseRate X BaseNotes656
$ - 0657
$ - 0658
$ - 0659
$ - 0660
TOTAL$ - 0661
662
PRIMARY FACILITYSection 1.1Section 2Section 3Section 4Section 5Section 6Section 7Grand Total663
TOTAL/POP JAN2017 - DEC2017$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0664
665
PRIMARY FACILITY - PERIOD OF PERFOMANCE (example: April 2018 - Dec 2018)666
abcdefghIjkl667
Section 1:UNBURDENEDSection 1.1:Fully Burdened668
Direct Laborif applicableDirect Laborif applicable669
LaborLaborExtendedLaborLaborLaborExtendedLabor670
POPCategoryRateHoursLaborNotesPOPCategoryRateHoursLaborNotes671
App mgr125$ - 0$ - 0672
$ - 0$ - 0673
$ - 0$ - 0674
$ - 0$ - 0675
$ - 0$ - 0676
$ - 0$ - 0677
$ - 0$ - 0678
TOTAL$ - 0TOTAL$ - 0679
680
Section 1.2:Labor Fringe/OHIf applicable,Total Labor681
Labor CategoryFringe BenefitExtendedIAW FAR 31.?Labor CategoryBenefitExtendedIAW FAR 31.?Overhead682
POPor BaseOverhead RateCostNotesor BaseRateCostNotesCost683
$ - 0$ - 0$ - 0684
$ - 0$ - 0$ - 0685
$ - 0$ - 0$ - 0686
$ - 0$ - 0$ - 0687
$ - 0$ - 0$ - 0688
$ - 0$ - 0$ - 0689
$ - 0$ - 0$ - 0690
TOTAL$ - 0$ - 0$ - 0691
692
Section 2:Vendor/Subcontract Cost693
Vendor NameService or Item DescriptionUnit PriceQuantityExtended CostQuote No., dateNoteIAW PWS paragraph694
$ - 0$ - 0695
$ - 0$ - 0696
$ - 0$ - 0697
$ - 0$ - 0698
$ - 0$ - 0699
$ - 0$ - 0700
$ - 0$ - 0701
$ - 0$ - 0702
$ - 0$ - 0703
TOTAL$ - 0$ - 0704
705
Section 3:Travel (in accordance with Joint Travel Regulations)706
POPFrom LocationTo LocationLabor CategoryNumber of employeesTravel CostLodgingOther Travel CostQuote No., DateNotesIAW PWS paragraph707
$ - 0708
$ - 0709
$ - 0710
$ - 0711
$ - 0712
$ - 0713
$ - 0714
$ - 0715
$ - 0716
TOTAL$ - 0717
718
Section 4:Other Cost Elements (not previously included above)719
Overhead/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved? Yes/NoNotes720
$ - 0721
$ - 0If Applicable:722
$ - 0FAR 30.201:NameTitleAddressPhone723
$ - 0or Administrative Contracting Officer/ACO724
$ - 0Auditor:NameTitleAddressPhone725
$ - 0or Defense Contract Audit Agency726
$ - 0727
$ - 0Billing Rates and/or Forward Pricing Rate Agreement may also be provided.728
$ - 0729
TOTAL$ - 0730
731
Section 5:FCCM (Facility Cost of Money)732
FCCM/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved?NotesOther Information if applicable to Offeror:If applicable, verifiable Audit Results:733
$ - 0Disclosure Statement (FAR 30.202)734
$ - 0Purchasing System (FAR 44.305)735
$ - 0Accounting System ( FAR 42.1)736
$ - 0737
TOTAL$ - 0738
739
Section 6:General and Administrative (G&A)740
G&AApplicable RateBaseRate X BaseACO/DCAA Approved?Notes741
$ - 0742
$ - 0743
$ - 0744
$ - 0745
TOTAL$ - 0746
747
Section 7:Profit748
ProfitApplicable RateBaseRate X BaseNotes749
$ - 0750
$ - 0751
$ - 0752
$ - 0753
TOTAL$ - 0754
755
PRIMARY FACILITYSection 1.1Section 2Section 3Section 4Section 5Section 6Section 7Grand Total756
TOTAL/POP APR2018-DEC2018$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0757
758
759
PRIMARY FACILITY - PERIOD OF PERFOMANCE (example: JAN2019-DEC2019)760
abcdefghIjkl761
Section 1:UNBURDENEDSection 1.1:Fully Burdened762
Direct Laborif applicableDirect Laborif applicable763
LaborLaborExtendedLaborLaborLaborExtendedLabor764
POPCategoryRateHoursLaborNotesPOPCategoryRateHoursLaborNotes765
$ - 0$ - 0766
$ - 0$ - 0767
$ - 0$ - 0768
$ - 0$ - 0769
$ - 0$ - 0770
$ - 0$ - 0771
$ - 0$ - 0772
TOTAL$ - 0TOTAL$ - 0773
774
Section 1.2:Labor Fringe/OHIf applicable,Total Labor775
Labor CategoryFringe BenefitExtendedIAW FAR 31.?Labor CategoryBenefitExtendedIAW FAR 31.?Overhead776
POPor BaseOverhead RateCostNotesor BaseRateCostNotesCost777
$ - 0$ - 0$ - 0778
$ - 0$ - 0$ - 0779
$ - 0$ - 0$ - 0780
$ - 0$ - 0$ - 0781
$ - 0$ - 0$ - 0782
$ - 0$ - 0$ - 0783
$ - 0$ - 0$ - 0784
TOTAL$ - 0$ - 0$ - 0785
786
Section 2:Vendor/Subcontract Cost787
Vendor NameService or Item DescriptionUnit PriceQuantityExtended CostQuote No., dateNoteIAW PWS paragraph788
$ - 0$ - 0789
$ - 0$ - 0790
$ - 0$ - 0791
$ - 0$ - 0792
$ - 0$ - 0793
$ - 0$ - 0794
$ - 0$ - 0795
$ - 0$ - 0796
$ - 0$ - 0797
TOTAL$ - 0$ - 0798
799
Section 3:Travel (in accordance with Joint Travel Regulations)800
POPFrom LocationTo LocationLabor CategoryNumber of employeesTravel CostLodgingOther Travel CostQuote No., DateNotesIAW PWS paragraph801
$ - 0802
$ - 0803
$ - 0804
$ - 0805
$ - 0806
$ - 0807
$ - 0808
$ - 0809
$ - 0810
TOTAL$ - 0811
812
Section 4:Other Cost Elements (not previously included above)813
Overhead/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved? Yes/NoNotes814
$ - 0815
$ - 0If Applicable:816
$ - 0FAR 30.201:NameTitleAddressPhone817
$ - 0or Administrative Contracting Officer/ACO818
$ - 0Auditor:NameTitleAddressPhone819
$ - 0or Defense Contract Audit Agency820
$ - 0821
$ - 0Billing Rates and/or Forward Pricing Rate Agreement may also be provided.822
$ - 0823
TOTAL$ - 0824
825
Section 5:FCCM (Facility Cost of Money)826
FCCM/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved?NotesOther Information if applicable to Offeror:If applicable, verifiable Audit Results:827
$ - 0Disclosure Statement (FAR 30.202)828
$ - 0Purchasing System (FAR 44.305)829
$ - 0Accounting System ( FAR 42.1)830
$ - 0831
TOTAL$ - 0832
833
Section 6:General and Administrative (G&A)834
G&AApplicable RateBaseRate X BaseACO/DCAA Approved?Notes835
$ - 0836
$ - 0837
$ - 0838
$ - 0839
TOTAL$ - 0840
841
Section 7:Profit842
ProfitApplicable RateBaseRate X BaseNotes843
$ - 0844
$ - 0845
$ - 0846
$ - 0847
TOTAL$ - 0848
849
PRIMARY FACILITYSection 1.1Section 2Section 3Section 4Section 5Section 6Section 7Grand Total850
TOTAL/POP JAN2019 - DEC2019$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0851
852
853
PRIMARY FACILITY - PERIOD OF PERFOMANCE (example: JAN2020-DEC2020)854
abcdefghIjkl855
Section 1:UNBURDENEDSection 1.1:Fully Burdened856
Direct Laborif applicableDirect Laborif applicable857
LaborLaborExtendedLaborLaborLaborExtendedLabor858
POPCategoryRateHoursLaborNotesPOPCategoryRateHoursLaborNotes859
$ - 0$ - 0860
$ - 0$ - 0861
$ - 0$ - 0862
$ - 0$ - 0863
$ - 0$ - 0864
$ - 0$ - 0865
$ - 0$ - 0866
TOTAL$ - 0TOTAL$ - 0867
868
Section 1.2:Labor Fringe/OHIf applicable,Total Labor869
Labor CategoryFringe BenefitExtendedIAW FAR 31.?Labor CategoryBenefitExtendedIAW FAR 31.?Overhead870
POPor BaseOverhead RateCostNotesor BaseRateCostNotesCost871
$ - 0$ - 0$ - 0872
$ - 0$ - 0$ - 0873
$ - 0$ - 0$ - 0874
$ - 0$ - 0$ - 0875
$ - 0$ - 0$ - 0876
$ - 0$ - 0$ - 0877
$ - 0$ - 0$ - 0878
TOTAL$ - 0$ - 0$ - 0879
880
Section 2:Vendor/Subcontract Cost881
Vendor NameService or Item DescriptionUnit PriceQuantityExtended CostQuote No., dateNoteIAW PWS paragraph882
$ - 0$ - 0883
$ - 0$ - 0884
$ - 0$ - 0885
$ - 0$ - 0886
$ - 0$ - 0887
$ - 0$ - 0888
$ - 0$ - 0889
$ - 0$ - 0890
$ - 0$ - 0891
TOTAL$ - 0$ - 0892
893
Section 3:Travel (in accordance with Joint Travel Regulations)894
POPFrom LocationTo LocationLabor CategoryNumber of employeesTravel CostLodgingOther Travel CostQuote No., DateNotesIAW PWS paragraph895
$ - 0896
$ - 0897
$ - 0898
$ - 0899
$ - 0900
$ - 0901
$ - 0902
$ - 0903
$ - 0904
TOTAL$ - 0905
906
Section 4:Other Cost Elements (not previously included above)907
Overhead/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved? Yes/NoNotes908
$ - 0909
$ - 0If Applicable:910
$ - 0FAR 30.201:NameTitleAddressPhone911
$ - 0or Administrative Contracting Officer/ACO912
$ - 0Auditor:NameTitleAddressPhone913
$ - 0or Defense Contract Audit Agency914
$ - 0915
$ - 0Billing Rates and/or Forward Pricing Rate Agreement may also be provided.916
$ - 0917
TOTAL$ - 0918
919
Section 5:FCCM (Facility Cost of Money)920
FCCM/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved?NotesOther Information if applicable to Offeror:If applicable, verifiable Audit Results:921
$ - 0Disclosure Statement (FAR 30.202)922
$ - 0Purchasing System (FAR 44.305)923
$ - 0Accounting System ( FAR 42.1)924
$ - 0925
TOTAL$ - 0926
927
Section 6:General and Administrative (G&A)928
G&AApplicable RateBaseRate X BaseACO/DCAA Approved?Notes929
$ - 0930
$ - 0931
$ - 0932
$ - 0933
TOTAL$ - 0934
935
Section 7:Profit936
ProfitApplicable RateBaseRate X BaseNotes937
$ - 0938
$ - 0939
$ - 0940
$ - 0941
TOTAL$ - 0942
943
PRIMARY FACILITYSection 1.1Section 2Section 3Section 4Section 5Section 6Section 7Grand Total944
TOTAL/POP JAN2020 - DEC2020$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0945
946
947
948
949
950
951
952
953
954
955
956
957
958
959
960
961
962
963
964
965
966
967
968
969
970
971
972
973
974
975
976
977
978
979
980
981
982
983
984
985
986
987
988
989
990
991
992
993
994
995
996
997
998
999
1000
1001
1002
1003
1004
1005
1006
1007
1008
1009
1010
1011
1012
1013
1014
1015
1016
1017
1018
1019
1020
1021
1022
1023
1024
1025
1026
1027
1028
1029
1030
1031
1032
1033
1034
1035
1036
1037
1038
1039
1040
1041
1042
1043
1044
1045
1046
1047
1048
1049
1050
1051
1052
1053
1054
1055
1056
1057
1058
1059
1060
1061
1062
1063
1064
1065
1066
1067
1068
1069
1070
1071
1072
1073
1074
1075
1076
1077
1078
1079
1080
1081
1082
1083
1084
1085
1086
1087
1088
1089
1090
1091
1092
1093
1094
1095
1096
1097
1098
1099
1100
1101
1102
1103
1104
1105
1106
1107
1108
1109
1110
1111
1112
1113
1114
1115
1116
1117
1118
1119
1120
1121
1122
1123
1124
1125
1126
1127
1128
1129
1130
1131
1132
1133
1134
1135
1136
1137
1138
1139
1140
1141
1142
1143
1144
1145
1146
1147
1148
1149
1150
1151
1152
1153
1154
1155
1156
1157
1158
1159
1160
1161
1162
1163
1164
1165
1166
1167
1168
1169
1170
1171
1172
1173
1174
1175
1176
1177
1178
1179
1180
1181
1182
1183
1184
1185
1186
1187
1188
1189
1190
1191
1192
1193
1194
1195
1196
1197
1198
1199
1200
1201
1202
1203
1204
1205
1206
1207
1208
1209
1210
1211
1212
1213
1214
1215
1216
1217
1218
1219
1220
1221
1222
1223
1224
1225
1226
1227
1228
1229
1230
1231
1232
1233
1234
1235
1236
1237
1238
1239
1240
1241
1242
1243
1244
1245
1246
1247

DG1330-11-RP-0009 - WCOSS

Cost/Price Template

PROPRIETARY DATA / SOURCE SELECTION SENSITIVE

Page &P of &N &Z&F&A

PROPRIETARY DATA / SOURCE SELECTION SENSITIVE &D

Back-upFacility

Note: THIS FORMAT MAY BE TAILORED BY THE CONTRACTOR to include other information to support total cost elements and price.1
Offeror may elect to use tab titled "Sheet 2" and other sheet tabs. Justification for cost to be provided in 'Notes' as necessary for cost evaluation.2
The offeror may not tailor this format to exclude necessary cost information. The offeror may add rows and/or columns.3
CONTRACTOR:DUNS No.:DATE:4
ADDRESS:5
FSS #:for information purposesFSS web site:ODC - Other Direct Cost6
POC:nametitleemailtelephonePOP - Period of Performance7
8
BACK-UP FACILITY - PERIOD OF PERFOMANCE (example: April 2011 - Dec 2011)9
abcdefghIjkl10
Section 1:UNBURDENEDSection 1.1:Fully Burdened11
Direct Laborif applicableDirect Laborif applicable12
LaborLaborExtendedLaborLaborLaborExtendedLabor13
POPCategoryRateHoursLaborNotesPOPCategoryRateHoursLaborNotes14
$ - 0$ - 015
$ - 0$ - 016
$ - 0$ - 017
$ - 0$ - 018
$ - 0$ - 019
$ - 0$ - 020
$ - 0$ - 021
TOTAL$ - 0TOTAL$ - 022
23
Section 1.2:Labor Fringe/OHIf applicable,Total Labor24
Labor CategoryFringe BenefitExtendedIAW FAR 31.?Labor CategoryBenefitExtendedIAW FAR 31.?Overhead25
POPor BaseOverhead RateCostNotesor BaseRateCostNotesCost26
$ - 0$ - 0$ - 027
$ - 0$ - 0$ - 028
$ - 0$ - 0$ - 029
$ - 0$ - 0$ - 030
$ - 0$ - 0$ - 031
$ - 0$ - 0$ - 032
$ - 0$ - 0$ - 033
TOTAL$ - 0$ - 0$ - 034
35
Section 2:Vendor/Subcontract Cost36
Vendor NameService or Item DescriptionUnit PriceQuantityExtended CostQuote No., dateNoteIAW PWS paragraph37
$ - 0$ - 038
$ - 0$ - 039
$ - 0$ - 040
$ - 0$ - 041
$ - 0$ - 042
$ - 0$ - 043
$ - 0$ - 044
$ - 0$ - 045
$ - 0$ - 046
TOTAL$ - 0$ - 047
48
Section 3:Travel (in accordance with Joint Travel Regulations)49
POPFrom LocationTo LocationLabor CategoryNumber of employeesTravel CostLodgingOther Travel CostQuote No., DateNotesIAW PWS paragraph50
$ - 051
$ - 052
$ - 053
$ - 054
$ - 055
$ - 056
$ - 057
$ - 058
$ - 059
TOTAL$ - 060
61
Section 4:Other Cost Elements (not previously included above)62
Overhead/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved? Yes/NoNotes63
$ - 064
$ - 0If Applicable:65
$ - 0FAR 30.201:NameTitleAddressPhone66
$ - 0or Administrative Contracting Officer/ACO67
$ - 0Auditor:NameTitleAddressPhone68
$ - 0or Defense Contract Audit Agency69
$ - 070
$ - 0Billing Rates and/or Forward Pricing Rate Agreement may also be provided.71
$ - 072
TOTAL$ - 073
74
Section 5:FCCM (Facility Cost of Money)75
FCCM/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved?NotesOther Information if applicable to Offeror:If applicable, verifiable Audit Results:76
$ - 0Disclosure Statement (FAR 30.202)77
$ - 0Purchasing System (FAR 44.305)78
$ - 0Accounting System ( FAR 42.1)79
$ - 080
TOTAL$ - 081
82
Section 6:General and Administrative (G&A)83
G&AApplicable RateBaseRate X BaseACO/DCAA Approved?Notes84
$ - 085
$ - 086
$ - 087
$ - 088
TOTAL$ - 089
90
Section 7:Profit91
ProfitApplicable RateBaseRate X BaseNotes92
$ - 093
$ - 094
$ - 095
$ - 096
TOTAL$ - 097
98
BACK-UP FACILITYSection 1.1Section 2Section 3Section 4Section 5Section 6Section 7Grand Total99
TOTAL/POP APR2011-DEC2001$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0100
101
BACK-UP FACILITY - PERIOD OF PERFOMANCE (example: JAN2012 - Dec 2012)102
abcdefghIjkl103
Section 1:UNBURDENEDSection 1.1:Fully Burdened104
Direct Laborif applicableDirect Laborif applicable105
LaborLaborExtendedLaborLaborLaborExtendedLabor106
POPCategoryRateHoursLaborNotesPOPCategoryRateHoursLaborNotes107
$ - 0$ - 0108
$ - 0$ - 0109
$ - 0$ - 0110
$ - 0$ - 0111
$ - 0$ - 0112
$ - 0$ - 0113
$ - 0$ - 0114
TOTAL$ - 0TOTAL$ - 0115
116
Section 1.2:Labor Fringe/OHIf applicable,Total Labor117
Labor CategoryFringe BenefitExtendedIAW FAR 31.Labor CategoryBenefitExtendedIAW FAR 31.?Overhead118
POPor BaseOverhead RateCostNotesor BaseRateCostNotesCost119
$ - 0$ - 0$ - 0120
$ - 0$ - 0$ - 0121
$ - 0$ - 0$ - 0122
$ - 0$ - 0$ - 0123
$ - 0$ - 0$ - 0124
$ - 0$ - 0$ - 0125
$ - 0$ - 0$ - 0126
TOTAL$ - 0$ - 0$ - 0127
128
Section 2:Vendor/Subcontract Cost129
Vendor NameService or Item DescriptionUnit PriceQuantityExtended CostQuote No., dateNoteIAW PWS paragraph130
$ - 0$ - 0131
$ - 0$ - 0132
$ - 0$ - 0133
$ - 0$ - 0134
$ - 0$ - 0135
$ - 0$ - 0136
$ - 0$ - 0137
$ - 0$ - 0138
$ - 0$ - 0139
TOTAL$ - 0$ - 0140
141
Section 3:Travel (in accordance with Joint Travel Regulations)142
POPFrom LocationTo LocationLabor CategoryNumber of employeesTravel CostLodgingOther Travel CostQuote No., DateNotesIAW PWS paragraph143
$ - 0144
$ - 0145
$ - 0146
$ - 0147
$ - 0148
$ - 0149
$ - 0150
$ - 0151
$ - 0152
TOTAL$ - 0153
154
Section 4:Other Cost Elements (not previously included above)155
Overhead/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved? Yes/NoNotes156
$ - 0157
$ - 0If Applicable:158
$ - 0FAR 30.201:NameTitleAddressPhone159
$ - 0or Administrative Contracting Officer/ACO160
$ - 0Auditor:NameTitleAddressPhone161
$ - 0or Defense Contract Audit Agency162
$ - 0163
$ - 0Billing Rates and/or Forward Pricing Rate Agreement may also be provided.164
$ - 0165
TOTAL$ - 0166
167
Section 5:FCCM (Facility Cost of Money)168
FCCM/ Cost Element TitleApplicable RateBaseRate X BaseACO/DCAA Approved?NotesOther Information if applicable to Offeror:If applicable, verifiable Audit Results:169
$ - 0Disclosure Statement (FAR 30.202)170
$ - 0Purchasing System (FAR 44.305)171
$ - 0Accounting System ( FAR 42.1)172
$ - 0173

This is the start of the file's text. The full file is on GovTribe.