Detention Center Boilers Replacement Addendum.pdf
PDF 184 KB Posted
- Attached to
- Boilers Replacement - Detention Center
- Solicitation number
- 2026-068
- Issued by
- Union County, North Carolina
About this file
This addendum modifies Invitation for Bid 2026-068 for the Union County, North Carolina Detention Center Boilers Replacement project. The project involves a complete turn-key replacement of two domestic water boilers at the Union County Detention Center located at 3344 Presson Road, Monroe, North Carolina. The scope of work includes demolition and removal of existing equipment, furnishing and installation of two new condensing domestic-water boilers, all required connections for domestic water, gas, venting, condensate, and electrical systems, testing, startup, training, permits, inspections, and related work. The original bid deadline of October 20, 2026, at 2:00 p.m. EDT has been extended to November 4, 2026, at 2:00 p.m. EST due to insufficient bid submissions received by the initial deadline. Union County received only two bids and requires a minimum of three bids to proceed with awarding the project. A non-mandatory pre-bid site visit was scheduled for October 2, 2026, at 9:00 a.m. EDT. Bids must remain valid for 120 calendar days after submission, and award will be made on a lump sum basis to the lowest responsive and responsible bidder.
Bidders must acknowledge receipt of this addendum in the appropriate space on the bid form, with failure to do so potentially resulting in disqualification. Each bid must include a 5 percent bid deposit in the form of cash, cashier's check, certified check, or bid bond from a North Carolina-licensed corporate surety. Acceptable equipment manufacturers include PVI, AERCO, Lochinvar Armor, and AO Smith, with requests for approved equals requiring written submission by October 9, 2026, at 3:00 p.m. EDT. Compliance with 2018 North Carolina Building Codes is mandatory, with 2024 codes available as an alternate subject to field verification. Contractors must comply with detention center security and access requirements and identify selected subcontractors for HVAC, plumbing, electrical, and general branches on the bid submission form. Insurance requirements include Workers' Compensation statutory limits, Commercial General Liability of $2 million general aggregate, and Commercial Automobile Liability of $1 million combined single limit, plus additional coverages as specified in the IFB. Contractors must provide applicable North Carolina contractor license documentation with their bids.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Detention Center Boilers Replacement.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Invitation for Bid 2026-068 Detention Center Boilers Replacement
ADDENDUM No. 2 ISSUE DATE: October 20, 2026
Responding Offerors on this project are hereby notified that this Addendum shall be made a part of the above named IFB document.
The following items add to, modify, and/or clarify the IFB documents and shall have the full force and effect of the original Documents. This Addendum shall be acknowledged by the Offeror in the IFB document.
Union County, North Carolina Addendum No. 2, IFB 2026-068 IFB Detention Center Boilers Replacement
Notice to Bidder
1. This Addendum is issued pursuant to the conditions of the solicitation and is hereby made part of the contract documents. The addendum serves to clarify, revise, and supersede information in the IFB.
The bidder shall acknowledge receipt of this addendum in the appropriate space on the bid form.
Failure to do so may subject the bidder to disqualification. A list of attachments, if any, is part of this document.
Schedule Revisions
1. The initial bid date was October 20, 2026. Union County received two (2) bid submissions before the initial deadline. Union County requires a minimum of three (3) bids to proceed with awarding the project. Therefore, a rebid date of November 4, 2026, has been set. All bids must be received by 2:00 PM EST on November 4, 2026. Late bids will not be accepted.
End of Addendum No. 2