Attachment_D.__Submittal_Log.pdf
PDF 138 KB Posted
- Attached to
- Gila Knob Phase 1 Transmission LIne Rebuild
- Solicitation number
- DE-SOL-0011107
About this file
ATTACHMENT D: SUBMITTAL LOG
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract Title: GILA-KNOB 230-KV
TRANSMISSION LINE
REBUILD, PHASE I
(STRUCTURES 4/7 TO
5/2)
Contract No.:
Award Date:
NTP:
Completion Date:
Western Location Location
Submittal In In
# Submittal Item WAPA Standards Project Specifications Date Due
STANDARD 1 STANDARD 1
1 Energized Work and Helicopter Program Division 1.E.1
2 Construction Schedule 1.1.4.1. Division 1.H.2 (see project spec)
3 Survey Plan 1.1.5.2.(1) 30 day prior to work
4 Survey Notes 1.1.5.5. & 1.1.5.7. Immed. upon completing
5 Survey Data Collector Dump & Computer Printout 1.1.5.6. Immed. upon completing
6 Survey Field Book 1.1.5.7. Immed. upon completing
7 Breakdown of Contract Prices 1.1.6.1. NLT 30-days after NTP
8 Electrical Equipment & Steel Purchase Orders 1.2.3.1.
NLT 10-working-days after
PO award
9 Cable Location Plan w/Print of Locations 1.3.4.2 & 1.4.5.2 Prior to starting excavation
10 Acknowledgement When Stringing Over Energized Lines 1.3.5.3. Prior to starting stringing
11 Safety and Health Program 1.4.1.5. Division 1.H.4 NLT 30-days prior to start of construction
12 Copies of Certifications, Test Records & Technical Data 1.4.1.10. 30 days Prior to use
13 - Load Performance Tests 1.4.1.10.(1) 30 days Prior to use
14 - Crane & Aerial Lift Equipment Annual Inspection Records 1.4.1.10.(2) 30 days Prior to use
15 - Brake Performance Test 1.4.1.10.(3) 30 days Prior to use
16 - Test Results of Protective Ground Leads 1.4.1.10.(4) Division 1.I.5 30 days Prior to use
17 - Material Safety Data Sheets 1.4.1.10.(5) 30 days Prior to use
18 - Manufacturer's Load Rating For Hoists and Grips 1.4.1.10.(6) 30 days Prior to use
19 - Certification of Fabricated Lifting and Rigging Devices 1.4.1.10.(7) & 1.4.11 30 days Prior to use
SUBMITTAL LOG
Western Location Location
Submittal In In
# Submittal Item WAPA Standards Project Specifications Date Due
20 - Medical Examiner's Certificate 1.4.1.10.(8) & 1.4.3.3 30 days Prior to use
21 - Data For Excavation Protective System 1.4.1.10.(9) & 1.4.5.5 30 days Prior to use
22 Assurance of Competency in Equipment Operation 1.4.3.4. 30 days Prior to use
23 Respiratory Protection Program 1.4.4.8 30 days Prior to use
24 Blasting Plan 1.4.6.2. 30 days Prior to blasting
25 Structure Erection Plan 1.4.8.1.
30 days Prior to structure erection
26 Suspended Work Cart Work Procedure 1.4.12 30 days Prior to use
27 Helicopter Operations and Safety Program 1.4.13 Division 1.E.1 NLT 15-days prior to helicopter operations
28 Protective Ground Lead Test Results & Certification 1.4.14.3. Division 1.I.5 30 days Prior to use
29 Clearance, Hot Line Order & Special Work Permit Requests 1.4.15.3.
NLT 10-working-days prior to starting work
30 Stringing Plan 1.4.17.3. 30 days Prior to stringing
31 HLO/Clearance Approval or Denial From Other Utilities 1.4.17.4.(3) 1) 30 days Prior to stringing
32 Transmission Line Removal Plan 1.4.18 30 days Prior to removal
STANDARD 3 STANDARD 3
33 Concrete Testing Laboratory 3.1.1.2.(1) & 3.1.1.3.
NLT 20-days prior to concrete placement
34 Concrete Mix Design 3.1.1.2.(2) & 3.1.1.5. NLT 10-days prior to use
35 Flyash For Concrete 3.1.1.2.(5) & 3.1.1.4. NLT 20-days prior to use
36 Admixtures and Curing Compound 3.1.1.2.(6) & 3.1.1.4. NLT 10-days prior to use
37 Batch Certificates 3.1.1.2.(7) Provide at delivery
38 Test Reports 3.1.1.2.(8) Immed. upon completing
39 Void Forming Material 3.1.1.2.(9) & 3.1.1.4. &
3.1.4.2.
30 days Prior to use
40 Non-shrink Grout 3.1.1.2.(10) 30 days Prior to use
41 Drawings & Data For Electrical Equipment Foundation Design 3.2.1.2. 30 days Prior to installation
42 Approval Drawings For Precast Cable Trench 3.2.1.3. 30 days Prior to precasting
43 Approval Drawings For Precast Concrete Pull Boxes 3.2.1.4. 30 days Prior to precasting
44 Final Drawings For Precast Cable Trench & Pull Boxes 3.2.1.5.
30 daysPrior to material shipment
STANDARD 9 STANDARD 9
# Submittal Item WAPA Standards Project Specifications Date Due
45 Contractor On-site Test Personnel 9.1.2.2.(2) 30 days Prior to working on-site
46 Electrical Test Reports & Documents 9.1.2.2.(3) NLT 7-days after testing
47 Continuity & Megohmmeter Testing Personnel 9.1.2.2.(7) 30 days Prior to testing
48 Infrared Inspection Tape 9.1.2.2.(15) NLT 48-hours after testing
Equipment Installation Drawings Including Seismic Qualification
Report Table 9-1 & 9.1.3.2. NLT 60-days after NTP
50 Equipment Informational Drawings & Data Table 9-1 & 9.1.3.3. NLT 60-days after NTP
51 Equipment Final Drawings Table 9-1 & 9.1.3.4.(1) NLT 21-days prior to equip.
installation
52 Equipment Parts Identification Lists & Bills of Materials Table 9-1 & 9.1.3.4.(2) NLT 21-days prior to equip.
installation
53 Manufacturer's Operation & Maintenance Instructions Table 9-1 & 9.1.3.4.(3) NLT 21-days prior to equip.
installation
54 Equipment & Oil Test Reports Table 9-1 & 9.1.3.5.
30 days Prior to shipping equipment
55 Equipment Insulating Liquid PCB Certification Table 9-1 & 9.1.3.6.
30 days Prior to delivery of oil or equip.
56 Insulated Conductor Data Table 9-1 & 9.1.3.7. NLT 60-days after NTP
57 Revised Wiring Diagrams Table 9-1 & 9.1.3.9.
NLT 60-days after receipt of drawings
58 Contractor's As-Built Equipment Drawings Table 9-1 & 9.1.3.10.(1) NLT 60-days after equip.
checkout
59 As-built Western Drawings Table 9-1 & 9.1.3.10.(2) NLT 60-days after equip.
checkout
60 Test Reports For Ground Tests 9.2.1.3.
NLT 15-days after completion of testing
STANDARD 10 STANDARD 10
Catalog Data Sheets of Accessories & Hardware Used In
Conductor & Overhead Ground Wire Installation 10.2.2.
NLT 40-days prior to material installation
Drawings of Insulator & Overhead Groundwire Assemblies and
Details 10.2.2.
NLT 40-days prior to material installation
63 Complete Material List 10.2.2.
NLT 40-days prior to material installation
64 Conductor Insulator Assembly Test Reports 10.2.3.1. & 10.3.3.
NLT 40-days prior to material installation
65 Conductor Test Reports 10.2.3.2. & 10.6.1.2.
NLT 40-days prior to material installation
# Submittal Item WAPA Standards Project Specifications Date Due
66 Overhead Ground Wire Test Reports 10.2.3.3. & 10.6.2.2.
NLT 40-days prior to material installation
67 Overhead Ground Wire Assemblies Test Reports 10.2.3.4. & 10.4.3.
NLT 40-days prior to material installation
68 Ground Resistance Measurements 10.2.3.5. & 10.5.3.
NLT 40-days prior to material installation
69 Vibration Damper Test Reports 10.2.3.6. & 10.6.4.3.
NLT 40-days prior to material installation
70 Conductor Spacer Damper Test Reports 10.2.3.7. & 10.6.6.2.
NLT 40-days prior to material installation
71 Optical Overhead Ground Wire Test Reports 10.2.3.8. & 10.6.3.2.
NLT 40-days prior to material installation
Assembly & Installation Instructions For Conductor Insulator
Assemblies 10.3.4
NLT 2-weeks prior to installation
Optical Overhead Ground Wire Suspension Clamp Attachment
Assemblies
10.4.2.3. 30 days Prior to use
STANDARD 13 STANDARD 13
74 Recycled Materials Quantity Report 13.2.1. & 13.7.2. Immed. upon completing
75 Products Containing Recovered Materials Report 13.2.2. & 13.8.3. Immed. upon completing
76 Spill Prevention Notification & Cleanup Plan 13.2.5. & 13.11.2.
30 days Prior to working on-site
77 Asbestos Licenses or Certificates 13.2.10. & 13.15.
30 days Prior to working on-site
78 Lead Paint Notices 13.2.11. & 13.16. Immed. upon completing
79 Water Pollution Permits 13.2.12. & 13.17.2.
30 days Prior to working on-site
80 PCB Test Reports 13.2.13 & 13.18.2 Immed. upon completing
81 Oil & Oil-Filled Electrical Equipment Receipt 13.2.14. & 13.18.5. Immed. upon completing
82 Cleanup Work Management Plan 13.2.16. & 13.19.2. Immed. upon completing
83 Post Cleanup Report 13.2.17. & 13.19.7. Immed. upon completing
STANDARD 15 STANDARD 15
84 As-Built Drawings 15.2.6. Immed. upon completing
*Submittal required if item is used in the performance of the contract.
"T"= Submit transmittal sheet only.
"NLT"= No Later Than "NTP"= Notice To Proceed "ASAP"= As Soon As Practicable