Design of Birch Creek Debris Basin CSDP 3-4 RFP - Exhibit C Topo Standards.pdf

PDF 173 KB Posted

Attached to
Design of Birch Creek Debris Basin
Solicitation number
PWG126-FLOOD-6139
Issued by
San Bernardino County, California

About this file

This document is a technical standards exhibit from San Bernardino County (SBCO) establishing topographic survey requirements for the Design of Birch Creek Debris Basin CSDP 3-4 project. The exhibit specifies comprehensive surveying methodologies and data collection standards that contractors must follow to ensure consistent quality and compatibility with the County's Civil3D systems. The project requires establishment of centerline control and topographic traverse points using RTK measurements from known bases established through static observation for a minimum of 121 minutes, processed via OPUS or manually to at least 3 CORS sites, with a minimum of two 3-minute RTK measurements per position at least 90 minutes apart. All topographic data collection must be performed via total station rather than RTK, including cross-sections every 50 feet, roadway surveys to specified boundaries (existing right-of-way, fence lines, or 5 feet from edge features), intersection surveys extending 50 feet beyond curve breaks, and documentation of all utility features, man-made structures, vegetation, drainage systems, and infrastructure elements.

The deliverable must be provided in AutoCAD hybrid grid-ground format with ground distances and coordinates referenced to California Coordinate System Zone 5 using NAD83(2011) at epoch 2010.0, with appropriate scale factors and conversion factors documented. The standards include detailed descriptor protocols for labeling survey features in Civil3D-compatible nomenclature, requiring specific formatting with dashes rather than spaces to prevent system import errors. Documentation must include project name, charge code, survey date, benchmark information with NGVD-29 and NAVD-88 elevations, and basis of bearings. Special attention is given to utility vault corners, signal light poles, utility poles with measured diameters, manholes, catch basins with invert elevations, trees measured to center, curb elevations, and other infrastructure elements that support subsequent design and construction phases.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exhibit C - SBCO Topo Standards

Control:

-Centerline control and topo traverse points may be established via RTK measurements from a known base; A “known base” is a position that is established by static observation for a minimum of 121 minutes, processed via OPUS or manually to a minimum of 3 CORS sites.

-A minimum of two (2) 3-minute RTK measurements on each position, a minimum of 90 minutes apart for each measurement.

-If RTK measurements are collected via real-time network, processing manually to a minimum of 3 CORS sites is required. All topo to be collected via total station, not RTK.

Topo:

Topo items to be collected, unless specifically told not to:

1. Establish centerline survey of roadway and cross streets by locating survey control monuments.

a. For ramp only jobs, centerline only needs to be established in directions that are needed to establish the delta of the quadrant the ramp occupies.

2. Cross section every 50-feet.

3. Topo the entire roadway up to either (to be specified by requestor):

a. Existing right-of-way, left and right of centerline

b. Fence line, left and right of centerline

c. 5-feet left or right of EP/Curb/Dike

4. At street intersections, survey up to limits listed above in #3, 50-feet beyond BCR/ECR

5. Pickup FOUR (4) corners of utility vaults/boxes, pull boxes, concrete pads under boxes, FOUR (4) corners of signal light poles/crosswalk push button poles, and diameter of utility poles (measured to center) and valves, manholes (top-center of lid elevation only, unless specifically asked for invert elev. too), bollards, etc.

6. Pickup all man-made features, fences, gates, utilities (vaults, fire hydrants, FOUR (4) corners of water meters, hose bibs, septic clean outs, utility poles, dead man, etc) flow lines, top of curb, gutter lips, ac dike, edge of pavement, concrete gutter lip/flow line and spandrel, catch basins or drainage structure (top of concrete and invert elevations), sidewalks, pipes (with pipe sizes, types, and invert elevations), traffic signs, striping’s, markings, grade breaks, driveways, handicap ramps (minimum of ¼ deltas and top/bottom of ramp x), etc.

7. Pickup all trees (measured to center of tree), bushes, planters, etc.

8. Data to be delivered in AutoCAD hybrid grid-ground format (see standard survey CAD file notes below)

Standard Survey CAD File Notes:

PROJECT NAME/TITLE

PROJECT CHARGE CODE (HXXXXX, F0XXXX, or TXXXXX) Project Job Number

DATE OF SURVEY: XX/XX/XXXX

DISTANCES AND COORDINATES ARE GROUND.

CF = 0.XXXXXXXX

1/CF = 1.XXXXXXXXXX

*NOTE - THIS DRAWING CONTAINS GRID BEARINGS

GRID COORDINATES*, BUT GROUND DISTANCES.

BASIS OF BEARINGS:

CCS83 ZONE 5, NAD83(2011), EPOCH 2010.0

BENCHMARK:

Benchmark description, including reference for description and elevation

NGVD-29 ELEV (NAVD-88) = XXXX.XX’

TO CONVERT TO GRID:

* SCALE PROJECT @ Pt #X (0.XXXXXXXX)

SBCo. Surveyor Descriptor Notes:

• The descriptor that is listed (the base descriptor) needs to be the first thing added EVERY TIME, no exceptions.

o Ex: FENCE-METAL-6’, not METAL-FENCE-6’

• When a descriptor has an asterisk (*) at the end, that descriptor can have anything you want after the main portion of the descriptor.

o Ex: CONC* - CONC1, CONC2, CONC3, etc o Ex: PP* - PP NO NUMBER, PP 123456E

• When a descriptor doesn’t have an asterisk (*), only what is shown on the descriptor list is valid; nothing can be added to this descriptor or it won’t import into Civil3D properly.

o EX: GP – nothing can be added after GP o Most descriptor’s without (*) are meant for single objects, not lines.

• Empty spaces within a descriptor confuse Civil3D. Any time you need to add information to a descriptor or combine descriptors, use a minus sign/dash (-). There are very, very few exceptions to this, so when in doubt, add the (-). A space IS required when starting (\) or ending (/) a line.

o Ex: PP NO NUMBER or PP 123456E, no (-) required o Ex: Tree 1”-6”, no (-) between ‘Tree’ & ‘1’ required o Ex: CLF-6’, (-) is required.

o Ex: SRF-WOOD-6’, (-) is required o CSPA-24”X36”, (-) is required.

o If you don’t add a (-) and instead use a space, Civil3D interprets that as a separate descriptor, so however many spaces you have in the descriptor, that’s how many descriptors Civil3D interprets.

• Topo the four (4) corners of all utility VAULT’s, PLBOX’s, BOX’s, SIGLGT’s, XWALK-BTN o Use VAULT, PLBOX, BOX for the line and use VAULT-*, PBOX-*, BX-* for the center ‘describing’ measurement o Use GB for base of SIGLGT and XWALK-BTN

• Measure to the center of all fire hydrants, guy poles, power poles, signal lights, street lights, trees, crosswalk buttons