This is a Design-Build Statement of Work (SOW) for a construction project at Columbus Air Force Base, Mississippi to repair the LRS Warehouse offices in Building 158 and add restroom facilities. The project requires complete renovation of the breakroom/office storage space, demolition of existing warehouse offices, construction of new warehouse office space for 8 personnel, addition of men's and women's restrooms, and replacement of a roll-up door. Key requirements include installing a 4-zone ductless mini-split HVAC system, new electrical and plumbing systems, suspended ceilings, LED lighting, and fire suppression modifications.
The contractor must provide all labor, materials and equipment, with a total period of performance of 300 days. The work includes providing temporary facilities and utilities to support displaced warehouse workers during construction. Design submittals are required at 35%, 65%, 95% and 100% completion stages. The contractor must maintain quality control, safety protocols, and environmental protection measures throughout the project. Key personnel requirements include a Project Manager, Site Superintendent, and Quality Control Manager with minimum 5 years relevant experience. The project falls under the Air Education and Training Command at Columbus AFB and requires coordination with base civil engineering, fire department, and security forces for various aspects of the work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| EEPZ239812 Sources Sought Questionnaire.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESIGN-BUILD STATEMENT OF WORK
PROJECT NUIMBER: EEPZ239812
Repair LRS Warehouse Offices, Add Restroom, B158
COLUMBUS AFB, MISSISSIPPI
25 Feb 2025
COLUMBUS AFB, MS PROJECT NUMBER: EEPZ239812
Repair LRS Warehouse Offices, Add Restrooms, B158
TABLE OF CONTENTS
NOMENCLATURE
1.1 ACRONYMS & ABBREVIATIONS
1.2 BASIC TERMS
DESCRIPTION OF PROJECT
2.1 SUMMARY (EXAMPLE BELOW)
2.2 BACKGROUND
2.3 SCOPE OF PROJECT
2.4 GOVERNMENT FURNISHED EQUIPMENT/MATERIALS (DETAILS NOT ALWAYS
NECESSARY, IF NOT, SAY THE GOVERNMENT WILL NOT FURNISH ANYTHING FOR THIS
PROJECT; THIS IS AN EXAMPLE BELOW) ............................................... Error! Bookmark not defined.
2.5 SALVAGE (DETAILS NOT ALWAYS NECESSARY, IF NOT, SAY THE GOVERNMENT WILL
NOT SALVAGE ANYTHING FROM THIS PROJECT; THIS IS AN EXAMPLE BELOW)Error! Bookmark not defined.
DESIGN REQUIREMENTS
3.1 SUMMARY
3.2 NATURE/EXTENT OF DESIGN (CHANGE THIS FOR PROJECT SPECIFICS, EXAMPLE
BELOW) 11
3.3 RESPONSIBILITY
3.4 DESIGN STANDARDS (ADD ANY OTHER RELEVANT UFCs, CODES, AND STANDARDS)11
3.5 DRAWINGS
3.6 DESIGN SUBMITTALS (CHECK DAYS IN RED IN SECTION 3.6.2)
3.7 DESIGN REVIEWS
3.8 CONFERENCES
ADMINISTRATION OF CONSTRUCTION
4.1 PERFORMANCE CAPABILITIES (VERIFY RED TEXT IN THIS SECTION ON EACH PROJECT)
4.2 COMMENCEMENT, PROSECUTION & COMPLETION (PERIOD OF PERFORMANCE IN 4.2.3)
4.3 SCHEDULING
4.4 MANAGING
4.5 MATERIAL SUBMITTALS AND SHOP DRAWINGS
4.6 WORK BY GOVERNMENT
4.7 PRE-FINAL AND FINAL INSPECTION
4.8 WARRANTY
4.9 CONTRACTOR OFFICE
4.10 CONSTRUCTION SITES
4.11 CONSTRUCTION EQUIPMENT
4.12 AVAILABILITY OF UTILITY SERVICES AT JOB SITES
4.13 TEMPORARY UTILITIES
4.14 CONSTRUCTION SECURITY
QUALITY REQUIREMENTS
5.1 QUALITY CONTROL PLAN
5.2 TESTING AND INSPECTION SERVICES
5.3 MANUFACTURERS' FIELD SERVICES
5.4 PRODUCT REQUIREMENTS
5.5 CLOSEOUT PROCEDURES
SAFETY, HEALTH AND ENVIRONMENTAL PROTECTION
6.1 SAFETY AND HEALTH
6.2 GENERAL
6.3 HAZARDOUS MATERIAL
6.4 PROJECT EXECUTION
6.5 HAZARDOUS WASTE GENERATION/DISPOSAL
6.6 RECYCLING
6.7 PROHIBITED MATERIAL/ACTIONS
6.8 SPILLS AND CLEANUP
6.9 AIR CONSIDERATIONS
6.10 AFFIRMATIVE/GREEN PROCUREMENT/BIO-BASED/ENERGY
6.11 ASBESTOS/LEAD BASED PAINT
6.12 DRINKING WATER
6.13 EMS
6.14 HISTORICAL AND CULTURAL ARTIFACTS
6.15 NATURAL RESOURCES
6.16 NOISE
6.17 PESTICIDES/FERTILIZERS
6.18 STORM WATER PROTECTION
6.19 REQUEST FOR CE SERVICE/ACTION/CLEARANCE; AF FORMS 332/813
6.20 TANKS
6.21 LIMITS AND EXCEPTIONS
6.22 LEGAL AUTHORITY
NOMENCLATURE
1.1 ACRONYMS & ABBREVIATIONS
AF Air Force AFI Air Force Instruction AFM Air Force Manual AFUE Annual Fuel Utilization Efficiency AHU Air Handling Unit ATFP Anti-terrorism/Force Protection BCE Base Civil Engineer CAD Computer Assisted (or Aided) Design CAFB Columbus Air Force Base CDs Construction Documents CEPM Civil Engineering Project Manager CES Civil Engineering Squadron cfm cubic feet per minute CFR Code of Federal Regulations CHW Chilled Water CMI 14CES Construction Manager Inspector CO Contracting Officer COR Contracting Officer Representative Comm Communications CPM Contractor’s Project Manager CSS Contractor’s Site Superintendent DP Design Professional EMCS Energy Management & Control System EMI Electromagnetic Interference EPA Environmental Protection Agency ETL Engineering Technical Letter FAR Federal Acquisition Regulation FCU Fan Coil Unit FM Factory Mutual
FOD Foreign Object Debris fps feet per second
ft. foot or feet GFCI Government Furnished Contractor Installed gpm gallons per minute Hazmat Hazardous Materials HMW Hazardous Material or Waste HTW Hazardous and Toxic Waste HVAC Heating, Ventilating and Air Conditioning NEC National Electrical Code NTP Notice to Proceed O&M Operation and Maintenance OSP Originally Specified Product PDF Portable Document Format PE Professional Engineer Ph Phase (electrical) PM Project Manager psi pounds per square inch QCP Quality Control Plan RFP Request for Proposal SOW Statement of Work TI Technical Instruction TL Technical Letter TM Technical Manual UFC Unified Facilities Criteria UPS Uninterruptible Power Supply VAV Variable Air Volume V Volts W Watts
1.2 BASIC TERMS
The following table provides many of the meanings of words or phrases commonly used in this document.
All directives, informative, etc. statements are directed to the Contractor even if the term “contractor” or the contractor name is not included (e.g. “Provide a nail.” is equivalent to “The contractor shall provide a nail.” And “remove” is equivalent to “The Contractor shall remove”). Also, the Contractor shall ably and competently execute all directives including all directly or indirectly related tasks required to safely and legally perform the directive (e.g. “remove debris from CAFB” includes “safe and legal removal, disposal and obtaining all necessary permits, etc.)
A device, equipment or system referred to in the singular (e.g. “the pump”, or “the ___ system”) includes all related devices, elements and components required to Provide (see below in this table) that device, equipment, or system.
The Term Shall Mean (*=Shall in Addition Mean) Approved (by CAFB) *without waiving or suspending the full force of Contractor obligation to fulfill the CDs Aspect Distinct feature or element of the project CAFB Government contracting Authority on Columbus Air Force Base
Construction Documents
Drawings, specifications and their references including all Design Criteria and Design & Construction Requirements for this Project.
Contractor The Design-Build entity holding a current Government contract including all personnel in direct or indirect employ of same entity servicing same contract including partners, consultants, subcontractors, suppliers, and manufacturers.
Design Professional (Abbreviated: DP) Professionals including Architects, Engineers and Landscape Architects licensed to practice in one or more states of the U.S.
Day Calendar day unless noted otherwise.
DP Licensed Design Professional fully responsible for all professional design on this project.
Engineer DP For example (e.g.) One among many possible examples Government Columbus Air Force Base Contracting Officer Including [Includes] Including, but not limited to [Includes, but is not limited to] Provide Furnish and install complete, functional, and ready for use without added government action Provision Furnishing & installation complete, functional, and ready for use without added government action Will, must, shall & similar Terms are mandatory directives whereby ‘Term’ = ‘Term + to CAFB satisfaction’ Work The whole or any part, product, system or subsystem of this project Replace Demolish and dispose of existing element. Provide new element of equal or greater value.
Review Review and, if and when acceptable to the government, approval Subcontractor Subcontractor and all personnel in Subcontractor’s direct or indirect employ on any given
Project including suppliers and manufacturers
DESCRIPTION OF PROJECT
2.1 SUMMARY
The Contractor must provide all plant, labor, equipment, transportation, and tools required to complete the renovation of the breakroom and attached office, the demolition of existing warehouse offices, the construction of new warehouse office, breakroom, and bathroom, and the replacement of roll up door. Temporary utilities and workspace shall be provided by the contractor for the warehouse office workers displaced during performance of work for this contract. Temporary construction fencing shall be utilized by the contractor to separate construction area in warehouse from rest of warehouse as the warehouse is a controlled area. Perform all work according to this Statement of Work (SOW), the Concept Design Drawings, and all related AF requirements and other codes and references.
2.2 BACKGROUND
The Facility serves as the main hub on base for storing and distributing material for the base. The breakroom/office storage space requiring renovation has exceeded its useful life. The existing warehouse office currently has no bathroom facility or breakroom on the same side of the facility. This requires the employees to leave a controlled area to go to the bathroom. The roll up door that is called to be replaced has only manual opening/closing capabilities. Existing personal door was installed after initial installation and does not function as intended with roll up door.
2.3 SCOPE OF PROJECT
Office Storage Room/Breakroom:
2.1 Demolish and remove the existing suspended ceiling in attached document “Conceptual Drawing of Area of interest” in its entirety including, but not limited to, the grid, tiles, diffusers, registers, grilles, ceiling lights, and associated fixture whips back to the nearest junction box. Furnish and install new complete suspended ceiling system including grid and 2’ x 2’ tegular ceiling tiles. Ceiling tiles are not to be vinyl-coated. Install new 2’ x 2’ flat panel LED flat light fixtures with new fixture whips. Install occupancy sensors and new switches along with the wiring conduit and breakers as needed. Install new aluminum diffusers, grilles, and registers with a factory finish to match the new ceiling.
2.2 Furnish and install egress and emergency lighting as required. Remove and store fire alarm and fire suppression components as required. Coordinate all fire alarm work with the government and Emergency Services to ensure proper disconnection and storage of all components. Any damage to fire alarm or fire suppression components caused by Contractor will be fixed or replaced at the Contractor’s expense.
2.3 Strip current furred out walls in the office back to the CMU wall, not including the wall bordering the current breakroom. Construct new furred out walls in this location. Reuse existing conduit where possible. All conduit shall be run behind the finished furred out walls.
2.4 Demolish in its entirety the wallpaper and handrail in the breakroom to in the breakroom to include the hallways as indicated on the drawings. Demolish all abandoned speakers, boxes, etc on the walls in their entirety.
Repair and prepare walls to be painted.
2.5 Prepare and paint the storage room, breakroom, and hallways in area indicated in attached document “Conceptual Drawing of Area of Interest”. Apply 1 coat primer and 2 coats latex-based paint to all walls. Furnish and install new light switches, faceplates, and receptacles in white. Paint color and cove base color will be selected by the CEPM.
2.6 Cabinets that are not mounted on the wall shall be moved and protected until work is completed. Cabinets that are mounted shall be taped off and protected during performance of work. Any damage to cabinets during performance of work shall be at the contractor’s expense.
2.7 Furnish and install receptacle branch circuits in the newly constructed areas, the receptacle count shall at minimum meet the UFC receptacle minimum set for each area.
2.8 Furnish and install new dedicated GFCI circuit to supply a refrigerator in existing break room.
2.9 Demolish the door, doorframe, and the associated hardware in between the office and breakroom. Repair the wall as necessary to prepare for a new door and doorframe to be installed. Furnish and install a new hollow metal utility closet door with louvered bottom, and the associated door frame, lockset, and door stop. The door and doorframe shall be factory finished. Furnish and install office name placard indicating breakroom and storage room according to base standards.
2.10 Demolish all existing carpet in the existing office, breakroom and hallways as indicated to include existing adhesive. Prepare the floors for the new VCT to be installed. Furnish and install new 12”x12”, 1/8” thick VCT flooring and 4” rubber wall base in the office. Furnish and install new transition strip anywhere that two unlike floor types meet. Selection will be made by the CEPM.
2.11 Demolish existing electrical sub panel PB-4 and the “push-pull” breaker panel that is feeding panel PB-4.
Identify and verify existing circuits in Panel PB-4 and the panel feeding PB-4. Replace Panel PB-4 and the “push-pull” breaker panel and consolidate to one new 120/208V Panel.
New Office:
2.12 Demolish existing office location marked on attached concept drawings. Demolish supporting electrical wiring back to the junction boxes. Demolish tile flooring in its entirety to include adhesive. Repair and prepare flooring as necessary to install new tiled floor. Coordinate with the government to remove COMM lines before beginning work.
2.13 Furnish and construct new metal stud and moisture resistant gypsum board office partition walls sized for an eight-person office in the concept drawing. Label the walls as non-load bearing as applicable.
2.14 Furnish and install a new hollow metal office door ad the associated door frame, kickplate, lockset, doorstop, and door closer. The door shall be a half lite glass door. The door and door frame shall be manufactured finished. Furnish and install office name placard.
2.15 Furnish and install single pane, hollow metal frame office windows in marked location on concept drawing.
The window frames shall be factored finished.
2.16 Furnish and install new electrical receptacles, conduit, and associated wiring as necessary to service the office area indicated in the conceptual drawings with 8 decks. Furnish and install new light switches, faceplates, and receptacles in white. Furnish and install 4-port Cat6 faceplate, box, and conduit that will stub-up above the drop ceiling for each desk.
2.17 Provide new 12”x12”, 1/8” thick VCT flooring and 4” rubber cover base on in and outside office walls.
Prepare and paint both inside and outside walls. Apply 1 coat primer and 2 coats latex-based, low VOC paint to all walls. Tile and wall base colors shall be selected by the CEPM.
2.18 Furnish and install new standard 2’x2’ ACT system at 8’ AFF with 2’x2’ LED flat light panels. Install occupancy sensors and new switches along with the wiring conduit and breakers as needed. Furnish and install lay in insulation above the ceiling.
2.19 Furnish and install 4 zone heating and cooling ductless mini split system (Daikin or approved equal).
Incidental to this includes forming and pouring a 4” thick concrete equipment pad outside the northeastern area of the building to provide a mounting surface for the outdoor heating and cooling condenser of the mini split system. If the outdoor unit is able to be securely mounted to the exterior wall of the facility, that is also acceptable. All coolant-carrying piping is to be insulated as necessary.
2.20 The ductless mini split system shall include ambient frost control and is to be designed to provide ample conditioned air for the following four zones: the office, two bathrooms, and the breakroom with the electrical and fire alarm panels. This is to be accomplished with an outdoor condensing unit feeding four indoor units able to condition the required spaces.
2.21 Furnish and install wall and ceiling insulation to support the ductless mini split system in meeting the requirements of the UFC and ASHRA for heating/cooling each of the newly constructed areas.
2.22 One indoor unit is to be placed into each of the four aforementioned zones. The indoor units are to have built-in thermostats to monitor the room temperature and control the unit automatically once the set point temperatures have been set. Wireless remote controllers are not necessary but are acceptable.
2.23 Incidental to the installation of the mini split system includes drilling a hole through each of the four zones to accommodate the conduit to the conduit to run to the wall mounted units. Run conduit over drop ceiling where possible.
2.24 Supple personal trailer with HVAC and power for the duration of the demolition and construction of the office space in the warehouse to support dislocated workers. The contractor shall work with 4-county to connect power to the trailer.
2.25 The contractor shall provide temporary chain link fencing between the construction area and the rest of the warehouse during demolition and construction within the warehouse. The contractor shall have one point of entry to and from the construction area that is secured with a construction core for the duration of the work in this area.
Warehouse Breakroom:
2.26 Furnish and install all materials necessary to create a functional kitchenette counter space with base and wall cabinet storage and sliding drawers. The counter must include a stainless-steel double basin kitchen-style sink with a faucet, and a minimum of four duplex receptacles with GFCI protection spaced along its length. The counter should be solid surface. Cabinets should be made of wood and use raised-panel doors. The work for this new kitchenette includes, but is not limited to, all necessary mechanical and electrical work needed for a fully functional product.
2.27 Furnish and construct new metal stud and moisture resistant gypsum board partition walls in the location identified.
2.28 Furnish and install all rough in plumbing and stub ups required to support one new sink. Provide new hot and cold-water lines, drain lines, and plumbing vents. Connect new hot water lines servicing the sink to water heater in the warehouse. All water lines shall be copper. Water lines servicing the sink must be connected to new thermostatic mixing (anti-scald) valve(s). Provide shutoff valves for hot and cold-water lines above the ceiling tiles.
2.29 Furnish and install a new hollow metal office door and the associated door frame, kickplate, lockset, doorstop, and door closer. The door shall be a half lite glass door. The door and door frame will be prefinished by the manufacturer. Furnish and install office name placard.
2.30 Furnish and install a single pane, hollow metal frame breakroom window. The window frame will be prefinished by the manufacturer.
2.31 Furnish and install new electrical receptacles, conduit, and associated wiring as necessary to supply the room. Furnish and install new electrical receptacles, conduit, and associated wiring as necessary to supply a dedicated GFCI receptacle for a refrigerator. Furnish and install new light switches, faceplates, and receptacles in white. Install GFCI receptacles along countertops.
2.32 Provide new 12”x12”, 1/8” thick VCT flooring and 4” rubber wall base in the breakroom. Apply 1 coat primer and 2 coats latex-based, low VOC paint to all walls. Tile and wall base colors will be selected by the CEPM.
2.33 Furnish and install new standard 2’x2’ ACT system at 8’ AFF with 2’x2’ LED flat light panels. Install occupancy sensors and new switches along with the wiring conduit and breakers as needed. Furnish and install lay in insulation above the ceiling.
Restroom:
2.34 Demolish abandoned boxes and conduit up to the height of the warehouse ceiling and cap it off as applicable in preparation for new restrooms to be installed.
2.35 Furnish and construct new metal stud and moisture resistant gypsum board partition walls to create the new men’s and women’s restrooms as depicted on the conceptual drawings.
2.36 In the women’s restroom furnish and install all rough in plumbing and stub ups required to support one new floor-mounted toilet with manual flush valve and one new wall-mounted bathroom sink with manual faucet in the locations indicated in the attached drawings.
2.37 In the men’s restroom, furnish and install all rough in plumbing and stub ups required to support one new floor-mounted toilet with manual flush valve one new wall-mounted urinal with manual flush valve, and one new wall-mounted bathroom sink with manual faucet in the locations indicated in the attached drawings.
2.38 For each restroom, provide new hot and cold-water lines, drain lines, and plumbing vents. Connect new hot water lines serving sinks to electric water heater in the warehouse. All water lines shall be copper. Toilets and urinals will be Zurn brand (or approved equal) and will not have any offset flanges. Bathroom sink will be Kohler (or approved equal) with Delta faucet (or approved equal). Water lines servicing sinks must be connected to new thermostatic mixing (anti-scald) valve(s). Provide shutoff valves for hot and cold-water lines above ceiling tiles.
2.39 Ensure all aspects of the bathrooms are designed and built to comply with ADA standards.
2.40 Trench and install the piping necessary to connect the restrooms to the sanitary gravity main lines located at a manhole lower in elevation than the restrooms. Once connected, repair the grounds as necessary for a seamless finish to match the existing. Attached map shows water main location in respect to bathrooms to be constructed.
2.41 Furnish and install all rough in plumbing to support one floor drain with trap primer in each of the men’s and women’s restrooms. Repair concrete slab floor sections as required. The contractor will provide a concrete slab with adequate slope for new floor drains servicing each of the restrooms.
2.42 Furnish and install new hollow metal restroom doors and the associated door frames, locksets, and door closers for each restroom. The door and door frame will be prefinished by the manufacturer. The doorframe and door will need to be factory finished. Furnish and install men’s and women’s restroom placards as applicable.
2.43 Furnish and install new electrical wiring, conduit, receptacles, and breakers as necessary. Furnish and install new light switches, faceplates, and receptacles in white.
2.44 Provide new 12”x12”, 1/8” thick VCT flooring and 4” rubber wall base in the restrooms. Apply 1 coat primer and 2 coats latex-based, low VOC paint to all walls. Tile and wall base colors will be selected by the CEPM.
2.45 Furnish and install new standard 2’x2’ ACT system at 8’ AFF with 2’x2’ LED flat light panels suitable for damp locations throughout the restrooms. Install occupancy sensors and new switches along with the wiring conduit and breakers as needed. Incorporate emergency lighting in ceiling IAW NFPA 101. Furnish and install lay in insulation above the ceiling.
2.46 Furnish and install exhaust fans in men’s and women’s restroom. Ensure the exhaust fans and supply airflow (CFM) are adequate for the size of the restroom.
2.47 Furnish and install one new 18”x30” vanity mirror in each restroom. In each restroom, install one hand soap dispenser, one new paper towel dispenser, and one toilet paper dispenser. Soap dispensers, paper towel dispensers, and toilet paper dispensers will be furnished by the government.
2.48 Install a bottle filler water fountain between the men’s and women’s restroom as indicated on the drawings.
Rolling Door:
2.49 Demolish existing rolling door in its entirety on the east wall. This shall include the cutout door in the wall and the associated tracks for both doors.
2.50 Furnish and install a new sliding door on tracks. The new sliding door shall be motorized for raising and lowering. The sliding door shall have a personal door built into it with a safety to ensure the door cannot be raised or lowered while the personal door is open.
2.51 Furnish and install a new branch circuit to feed the motorized door.
Fire Suppression:
2.52 Branch off existing fire suppression system for supplying coverage to the entirety of the bathrooms, office, and breakroom IAW NFPA 13. Include removable escutcheons for each sprinkler head. Extend fire alarms and smoke detectors to include new additions to warehouse.
2.53 Replace all existing sprinkler heads that are part of this system. Sprinkler heads in warehouse shall be rated for use in warehouse.
2.54 Incorporate emergency lighting IAW NFPA 101. Reuse existing components to the maximum extent possible. Reprogram fire suppression controls as necessary.
2.55 If sprinkler heads must be removed, the sprinkler system is to be shutoff and drained with coordination with the government. Any fire alarm components that are removed during this project must be done so following coordination with the government. Reinstall all fire alarm and fire suppression components and verify proper operation with the government and Fire Dept.
DESIGN REQUIREMENTS
3.1 SUMMARY
Design will consist of all site investigations and design work associated with preparing complete contract documents for this project as described in this SOW. The design documents must be developed from the functional and technical data contained in this SOW and include construction drawings, schedules, and design analysis. The Contractor will also be required to submit design documents for review as described in Paragraph 3.6 as well as final contract documents. The Contractor will be required to attend review and conference meetings as needed and requested by the Government.
3.2 NATURE/EXTENT OF DESIGN
This project requires the services of licensed Design Professionals. The project requires structural design and details for the demolition and subsequent reconstruction warehouse office space, and the addition of the breakroom and restroom. The services of a fire protection engineer shall be utilized for the fire suppression work being designed and performed per the statement of work. Professionally sealed drawings are required. Design/shop/coordination drawings, materials and equipment submittals, and final as-built record drawings are required for this project. Contractor must maintain accurate redline As-Builts throughout construction and must submit final As-Built drawings (with any of the redline changes updated on the drawings) upon project completion (see paragraph 4.7.2 for more information). Lighting calculations for all areas shall be provided with the 35% design. HVAC and fire suppression calculations must be provided by the 65% design for the new warehouse areas.
3.3 RESPONSIBILITY
3.3.1 Contractor must perform all services, including travel, required to prepare and to furnish complete design documents consisting of drawings, analysis, and addenda as required, for the construction of the project in accordance with this SOW.
3.3.2 Record drawings (attached) are provided to the Contractor as a courtesy at the discretion of the Government, but their accuracy is not guaranteed. The Contractor is responsible for doing his own field investigations of the utilities, existing conditions, and other items in the area.
3.3.3 The Contractor is responsible for all remaining design and coordination to provide an acceptable final product that meets intent of this SOW. Contractor is responsible for ensuring constructability and code compliance.
3.4 DESIGN STANDARDS
All design and construction must be accomplished in accordance with applicable UFC’s, ETL’s, (UFC’s and ETL’s may be found on-line at www.wbdg.org.) local and national codes, Columbus AFB Installation Facility Standards (IFS) and all Appendices (Special Construction, Mechanical, and Electrical) and other guidance as modified by this SOW. The IFS document may be found at the following location:
http://www.wbdg.org/ffc/af-afcec/installation-facilities-standards-ifs/columbus-afb-ifs. The list of documents includes, but is not limited to, the latest editions of the following
• UFC 1-200-01 DoD Building Code (General Building Requirements)
• UFC 1-200-02 High Performance and Sustainable Building Requirements
• UFC 3-401-01 Mechanical Engineering
• UFC 3-410-01 Heating, Ventilating, and Air Conditioning Systems
• UFC 3-410-02 Direct Digital Control for HVAC and Other Building Control Systems
• UFC 3-410-04 Industrial Ventilation
• UFC 3-501-01 Electrical Engineering http://www.wbdg.org/ffc/af-afcec/installation-facilities-standards-ifs/columbus-afb-ifs
• UFC 3-520-01 Interior Electrical Systems
• UFC 4-010-01 DoD Minimum Antiterrorism Standards for Buildings
• NFPA 101
• NFPA 72
• NEC 70
• ACGIH: Industrial Ventilation Manual
• Columbus AFB IFS
• CAFB Base Standards
The Contractor must submit a written request for approval of any deviations from the Government's established standards. No deviations from the Government's established standards will be permitted unless the Contracting Officer has issued prior written approval of such deviation.
3.5 DRAWINGS
Drawings under this Contract must be well prepared, complete, and accomplished in accordance with the best professional practice to show clearly and concisely the type and extent of work to be performed.
3.5.1 Drawings must be drawn to appropriate scales and dimensioned completely and accurately.
Lettering must be large enough to ensure legible half-size reduction and each dimensioned drawing must have a graphic scale. Use of fractions less than 1/8-inch for building dimensions must be avoided. Use standard building material indications and symbols for architectural items and for mechanical, electrical and plumbing equipment.
3.5.2 The Contractor will use paper sheets, 24" x 36". Each sheet will be numbered consecutively beginning with "1 of (x) Sheets" and continue to the last sheet. Number individual drawing sheets as follows:
Drawing Sheet Subject Notation Additional Sheets
Cover (Title Sheet, Map and Index)
T1 and following
Civil/Site Work C1 and following Demolition D1 and following Landscaping L1 and following Architectural A1 and following Structural S1 and following Plumbing P1 and following Mechanical M1 and following Electrical E1 and following
Note: All sheet subjects above may not be necessary for this project
3.5.3 Drawings must be prepared electronically in both AutoCAD (Release 2020) and PDF formats.
3.6 DESIGN SUBMITTALS
3.6.1 DELIVERY: Deliver two (2) hard copies of each submittal and one (1) digital copy via DoD SAFE containing each drawing sheet in PDF file format directly to the CO, along with AF Form 3000. For uploading to DoD SAFE, the Contractor must request an upload link from the CO and then upload the files using the details in the subsequent email from DoD SAFE. For the final design submittal (As-Builts in most cases), the contractor is to provide, in addition to the hard copies and digital copies via DoD SAFE, containing the PDF file as well as the associated CAD files in AutoCAD (Release 2020) .dwg file format. Hard copy submittals must be delivered to:
14th Contracting Squadron 495 Harpe Blvd, Suite 293 Columbus, MS 39710
3.6.2 SUBMITALS AT INTERMEDIATE STAGES OF DESIGN COMPLETION: To facilitate review and feedback throughout the design process, designs are submitted at various stages of completion as follows:
1) 35% DESIGN SUBMITTAL: Contractor must submit 35% design documents within 21 days after Notice to Proceed (NTP). The 35% design must include complete and thorough detailing to leave no question as to how demolition and construction is intended. All design documents must be clearly annotated (in both title block and revision block of drawings) with “35% REVIEW SET” and the date.
2) 65% DESIGN SUBMITTAL: Contractor must submit 65% design documents within 21 days after receipt of the “Approved” 35% design. The 65% design must include complete and thorough detailing to leave no question as to how demolition and construction is intended. All design documents must be clearly annotated (in both title block and revision block of drawings) with “65% REVIEW SET” and the date.
3) 95% DESIGN SUBMITTAL: Contractor must submit 95% design documents within 21 days after receipt of the “Approved” 65% design. The 95% design (essentially complete design and drawings, pending review and acceptance by Government as the 100% APPROVED CONSTRUCTION SET) must include complete and thorough detailing to leave no question as to how assembly is intended. All design documents must be clearly annotated (in both title block and revision block of drawings) with “95% REVIEW SET” and the date.
4) 100% DESIGN/APPROVED CONSTRUCTION SET: Contractor must submit the 100% DESIGN APPROVED CONSTRUCTION SET within 14 days after Contractor receipt of the “Approved” 95% design. The construction set must incorporate and/or address any Government comments on the 95% design and should leave no question to how demolition and construction will be done. If professionally stamped and sealed drawings are required for this project (paragraph 3.2), the approved construction set must include all stamped drawings. All final design documents must be clearly annotated (in both title block and revision block of drawings) with “APPROVED CONSTRUCTION SET” and the date.
5) For each holiday or extraordinary event in a submittal period, increase the required days for submittal by one day for each day in the event. Deliver no submittals within (before or after): one week of Thanksgiving; two weeks of Christmas; or one week of New Year’s Day. Extraordinary Events include: unscheduled holidays for base personnel; base-wide training exercises; etc. The Government may prohibit work during such events.
3.6.3 PARTIAL SUBMISSIONS: Partial submissions normally will not be accepted. However, under some circumstances, to expedite project execution, the Government may accept design/shop drawings or material submittals for major elements or long-lead-time equipment for review and approvals prior to 95% design submittal. Government approval of such items does not relieve the Contractor of his responsibility to ensure a complete, constructible, code-compliant design.
3.6.4 CONSTRUCTION PRIOR TO 100% DESIGN: Construction may not commence until Government approves the 100% design. Exception: To expedite contract completion, Contractor may petition CO for an Interim Notice to Proceed with specific elements of construction. Government review does not constitute approval or acceptance of any variations from this SOW, the Contractor’s Proposal, or the Contract unless authorized in writing by the CO. The Interim Notice to Proceed, if exercised, will in no way mitigate the responsibility of the Contractor to provide a complete, constructible, code-compliant design.
All drawings, specifications, design analyses and other project materials become the property of the Government.
3.7 DESIGN REVIEWS
3.7.1 DESIGN PHASE REVIEWS: Government review of each XX% design submittal (where XX = 95 or 100 as required per 3.6.2) will require up to fourteen (14) days after Government receipt. The Government will determine the sufficiency of each XX% design submittal as follows:
1) Approved as Submitted. If design is sufficient to proceed without correction to the next phase submittal, one (1) copy of AF FORM 3000 marked "Approved" will be returned to the Contractor.
Contractor must advance to the next stage design submittal.
2) Approved - Except as Noted. Design submittals that have only minor errors or deficiencies will be marked in red to indicate necessary corrections. Marked materials, along with one (1) copy of AF FORM 3000 indicating "Approved - Except as Noted" will be returned to the Contractor.
Contractor must revise the design documents, making the necessary corrections, and advance to the next stage design submittal.
3) Disapproved. Design submittals that are incomplete or require more than minor corrections will be marked in red to indicate necessary corrections. Marked materials, along with one (1) copy of AF FORM 3000 marked “Disapproved” will be returned to the Contractor. Contractor must revise the design documents, making the necessary corrections, and re-submit as the current stage “XX% Design – 2nd (or subsequent) Submittal”.
4) Disapproved – Major Deficiency. Examples include, but are not limited to, design submittals that fall significantly short of indicated level of completion, grossly deviate from or misinterpret the SOW, or contain errors of a nature or quantity that indicate failure of Contractor to review submittals for completeness, correctness, and coordination between trades. For such submittals, the Government will not complete a comprehensive review or provide an exhaustive list of needed corrections. Rather, one (1) copy of AF FORM 3000 marked “Disapproved – Major Deficiency” along with general reason(s) for disapproval will be returned to the contractor. The CO will issue a written warning to the Contractor that any subsequent grossly incorrect/incomplete submittals constitute evidence of inability to complete the project and may result in declaring the Contractor “In Default.” Contractor must correct deficiencies and resubmit as current stage “XX% Design – 2nd (or subsequent) Submittal”.
3.7.2 100% DESIGN REVIEW: The Government will have fourteen (14) days to verify that all review comments have been addressed and no unapproved changes have been made. Upon Government approval of the 100% design documents, the Contractor may begin construction.
3.7.3 IMPACT OF REVIEW ON PERIOD OF PERFORMANCE: Contract completion time includes time for Government review of drawings, specifications, and material submittals. Unless otherwise noted, the Government will use no more than 14 calendar days for review of each design submittal and each subsequent re-submittal of “Disapproved” submittals (paragraph 3.7.1, c or d). There will be no increase in the period of performance for review of re-submittals.
3.7.4 RESPONSE TO REVIEW COMMENTS: The Contractor is required to respond to all review comments and submit their annotated comments as a design analysis appendix in the subsequent design submittal. All comments must either be accepted and incorporated into the next design submittal or satisfactorily rebutted.
3.7.5 DESIGN ACCOUNTABILITY: The Contractor is solely responsible for accurately designing and constructing everything necessary to provide a fully functional product. Government approval of any design or design-related submittal does not waive or remove full liability from the Contractor to provide a design, facility, or final product that meets the intent of this SOW, performs as intended, and adheres to all applicable codes and standards.
3.8 CONFERENCES
3.8.1 PRECONSTRUCTION CONFERENCE: A Preconstruction Conference (Pre-Con) will be held at the Contracting Office as indicated.
3.8.2 COORDINATION/REVIEW CONFERENCES: Coordination/review conferences may be held from time to time as required. The Contractor may request such conferences when it is deemed necessary by both parties to clarify the work or expedite the preparation of plans, specifications or construction.
3.8.3 REVIEW/CONFERENCE MINUTES: The Contractor will be responsible for making memoranda of record of any conversations and minutes of any meeting with Government personnel concerning this project and forward one copy of these memoranda/minutes to each party concerned and one copy to the Contracting Officer within seven (7) days. The final version of the meeting minutes will be approved and filed at the CO’s discretion. Each copy will be numbered consecutively and chronologically.
3.8.4 MEETING LOCATIONS: Meetings will be held in person at Columbus Air Force Base.
Contractor transportation costs for attending all conferences/reviews and meetings must be included in the Contractor’s Proposal. There will be no teleconferences unless permitted otherwise by the Contracting Officer.
End of Design Requirements
ADMINISTRATION OF CONSTRUCTION
4.1 PERFORMANCE CAPABILITIES
4.1.1 One week prior to the start of work under this contract, Contractor must submit in writing to the CO for review and possible approval the names and credentials of Contractor Project Manager, Contractor Site Superintendent, and Quality Control Manager. Subsequent proposed changes of approved personnel must be submitted in writing to and receive prior approval from the CO before working on the project. Each of these personnel may upon CO approval hold additional onsite duties which must not diminish their required performance. Contractor must demonstrate to the Government’s satisfaction that proposed personnel exceed education, technical and experience levels of personnel described in this Contract including the following:
1) Contractor Project Manager (CPM) - Provide management of the prime contract to include subcontract purchasing and administration, review of material submittals and shop drawings. CPM must have full authority to develop cost proposals, negotiate with Government and subcontractors, sign awards and modifications, supervise project superintendents, attend weekly CO/CE/PM Contractor status meetings as well as pre-performance site visits, pre-final and final inspections.
The CPM must have a minimum of 5 years previous experience as primary contract manager or equivalent experience as a primary estimator and negotiator with a contracting firm engaged in similar multi-discipline commercial construction projects. CPM must also have not less than 5 years’ experience managing subcontractors.
2) Contractor Site Superintendent (CSS) - Provide on-site construction superintendent(s) to oversee all work under this contract. Site supervision must be daily (constant throughout each day) and includes submission of detailed weekly progress reports, scheduling and coordination of subcontractors and material suppliers, and attendance at all construction progress meetings, CO site visits, and pre-final and final inspections. Superintendents must have a minimum of 5 years previous experience as a project superintendent (exclusive of time employed as a tradesman or working foreman) for a general contracting firm overseeing one or more multi-discipline commercial construction projects. The superintendent must be available within 15 minutes during all normal working hours, except for such incidental errands as required by his duties. The superintendent must be responsible for the proper coordination and timeliness of the work, and for the proper workmanship of all trades; therefore, his absence from the project site without a suitable substitute Contractor representative must be considered as damaging to the Government.
3) Quality Control Manager (QCM) - Provide quality control management for the project. QCM must continually (constant throughout each day) ensure full compliance with all safety requirements, verification that work and materials in place and stored on site are in accordance with the approved construction documents, shop drawings and material submittals. QCM must submit daily status reports recording activities at each project site, prepare and coordinate material submittal sheets and shop drawing submittals, schedule and coordinate testing procedures, prepare quality control reports for construction progress and other required meetings, and attend all pre-final and final inspections. QCM must have a minimum of five years’ experience in Quality Control Management of multidiscipline construction projects.
4.1.2 Contractor must have additional personnel including management, technical, service, labor or subcontractor, available as necessary to fulfill all construction contract requirements. The Government may restrict employment under this contract of any personnel identified as a potential threat to the health, safety, security, well-being, or operational mission of CAFB and its population.
4.1.3 Contractor must be available by telephone 24-hours a day, 7-days a week and upon 15 minutes’ notice during normal duty hours and 30 minutes’ notice during non-duty hours must meet the CO at a CO designated location.
4.2 COMMENCEMENT, PROSECUTION & COMPLETION
4.2.1 Contractor must start design and various construction phases at times specified by CO issued Notice(s) to Proceed (NTP), prosecute the work, and complete the entire work within the Period of Performance.
4.2.2 Contractor must provide a Submittal Log (Schedule of Material Submittals), Progress Schedules, Progress reports and Status Reports.
1) Submittal Log: See Material Submittals and Shop Drawings below.
2) Progress Schedule: (AF Form 3064) Submit the progress schedule to the CO within 10 days after contract award, unless otherwise specified by the CO. Subdivide total schedule into individual work items. Show completed work percentages at the end of each two-week reporting period. Progress schedule should only be resubmitted during the project duration if there’s an issue with Period of Performance or if deemed necessary by the CO as described in 4.2.2.3.
3) Progress Reports: (AF Form 3065) Submit Project Progress reports to the CO minimum twice per month on the first working day of each month and again on the 15th. Describe the percentage of work completed during the report period. If behind schedule, report in writing what actions will be taken to regain the schedule. If the CO agrees to add days to the contract performance period, Contractor must provide an amended schedule.
4) Status Reports: Submit to the CO daily reports of the work status. In each report, list the tasks accomplished for that day, any deliveries received, equipment currently on-site, weather conditions for that day, and number of personnel working on each area listed by trade. Photos may be included.
4.2.3 Period of Performance: Is the period between the issuance of the NTP and the time all construction is complete, including all punch list items, and final inspection is approved by the Government. The total Period of Performance for this project is 300 days.
4.2.4 Contract Completion: At contract conclusion, vacate all work areas, including: Contractor offices, storage and staging areas, and individual work sites. Restore these areas to their condition prior to Contractor occupancy not more than 14 days from the earlier of: approved final inspection or CO notification.
4.2.5 Coordination and Project Conditions: Schedule and manage submittals, materials, products, equipment, manpower, etc. to control all parts of the work efficiently and orderly. Verify compatibility of existing building utilities with new operating equipment. Coordinate required space, supports, and mechanical and electrical work shown (even if via diagrams) on Drawings. Follow routing shown for pipes, ducts, and conduit; place runs parallel with building lines. Use space efficiently to maximize maintenance and for repair accessibility for other systems. Conceal wiring behind finish surfaces and locate fixtures and outlets with finish elements. Coordinate pre-Substantial Completion clean-up in separate building areas.
After CAFB occupancy, coordinate site access to correct defective (or non-compliant with CDs) to minimize disruption of Government activities.
4.2.6 Cutting and Patching: Only employ skilled and experienced workers to cut and patch. Report in writing to the CO wherever cutting and patching might degrade: safety; appearance, structure, weatherproofing, O&M, or separate Contractor or government construction. Prevent damage to existing or new construction and provide proper surfaces to receive patching and finishing. Match new finishes to existing adjacent surfaces unless noted otherwise. Maintain integrity of existing walls, ceilings, or floors;
completely seal voids. Refinish entire assemblies and continuous surfaces to nearest intersection. Cut, fit, and patch where CDs require e.g.: mechanical and electrical penetrations; integration of new components with one another or with existing construction; removal and replacement of defective and non-conforming elements; remove samples for testing.
4.2.7 Special Procedures: Employ skilled and experienced tradespersons to perform alteration work.
Remove debris from open work areas and concealed spaces. Remove, cut, and patch to minimize damage and provide means of restoring products and finishes to original or specified condition. If a change of plane of 1/4 inch or more is discovered, submit recommendation to the CO for providing a smooth transition.
Patch or replace portions of existing surfaces which are damaged or showing other imperfections. Finish surfaces as specified.
4.2.8 Welding Permits: No cutting or welding will be permitted without first obtaining a permit issued by the Base Fire Department. All fire and safety regulations are to be followed stringently. Contractor’s failure to obtain a cutting or welding permit may not be reason for extending the contract performance period. Any damages incurred while welding work is done without a permit are the responsibility of Contractor.
4.3 SCHEDULING
4.3.1 Contractor must coordinate all work schedules and manage progress of work with the CO and CEPM prior to start of work. Weekly progress meetings will be conducted with the CO, CMI, and Contractor’s team which may require corporate management representation at CAFB discretion.
4.3.2 Contractor must schedule all work. Performance periods must not be established or extended to accommodate insufficient personnel resources. Contractor will not move crews on and off the project while making minimal progress on concurrent projects as this must be construed as having an inadequate work force to fulfill the contract requirements. Contractor’s CPM and CSS must not change more than two (2) times during project construction as this would demonstrate an inadequate management force to fulfill contract requirements.
4.3.3 Before construction begins, Contractor must agree with CO on a sequence of procedures; means of access to premises and buildings; materials and equipment storage space; delivery of materials and use of approaches, corridors, and stairways. Contractor may be required to revise the CD work-phasing schedule.
4.3.4 Interference and inconvenience to Government operations and personnel caused by project work including use and delivery of materials, tools and equipment must be kept to a minimum.
4.3.5 The Government may require that work, so far as practicable, be done in separate phases. Each phase may relate to a different occupied or unoccupied area, in which work in one area must be completed before work in another area may begin. Phased work areas must be clearly delineated and annotated in the CDs.
4.3.6 Hours of Work: Normal work hours will be Monday through Friday from 7:30am to 4:15pm excepting days observed as Federal Holidays as listed below:
New Year’s Day 1 January Martin Luther King’s Birthday Third Monday in January President’s Day Third Monday in February Memorial Day Last Monday in May Juneteenth Day 19 June Independence Day 4 July Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day 11 November Thanksgiving Day Fourth Thursday in November Christmas Day 25 December