DEP.BWR.RFQ.2023.WETO1.PRF77.CATA3.D4.REOPENED.2nd.rev.procure.cal..4.21.23.docx
DOCX document 286 KB Posted
- Attached to
- DEP-BWR-RFQ-2023-WETO1-PRF77-CAT A3 & CAT D4
- Solicitation number
- BD-23-1045-BWR00-BWR01-83149
- Issued by
- Massachusetts
About this file
This document is a Request for Quotes (RFQ) issued by the Massachusetts Department of Environmental Protection (DEP) Bureau of Water Resources, Wetlands Program. The RFQ is for off-contract services under OSD Statewide Contract PRF77 in two specific categories: Category A3 - Media Assessments - Ecological/Wetland Assessment and Category D4 - Permitting and Reporting - Wetlands, Waterways and Resource Areas. The RFQ has a deadline for quotes/bid responses of May 5, 2023, with an estimated contract execution and work start date of May 19, 2023.
The RFQ is focused on "No Net Loss of Carbon in Wetlands in Massachusetts" and the services requested may include wetlands assessments, permitting, and reporting. Pricing terms, set asides, incumbents, funding requirements and sources, and other salient information are not explicitly provided in the document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
executive office of energy & environmental Affairs
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Request for Quotes (RFQ)
Off of OSD Statewide Contract PRF77 Category A3 - Media Assessments – Ecological/Wetland Assessment (PO-22-1080-OSD03-SRC3-25025) or Category D4 -Permitting and Reporting – Wetlands, Waterways and Resource Areas (PO-22-1080-OSD03-SRC3-25040)
Document Title: No Net Loss of Carbon in Wetlands in Massachusetts
Agency Document Number:
BWR- RFQ-2023-WET01
2nd REVISION TO UPDATE PROCURE CALENDAR
April 21, 2023
Massachusetts Department of Environmental Protection Bureau of Water Resources, Wetlands Program
2.0 ESTIMATED PROCUREMENT SCHEDULE – UPDATED APRIL 21, 2023
| Event |
| Date |
| RFQ Published in COMMBUYS |
| April 5, 2023 |
| Deadline for Submission of Questions |
| April 14, 2023 |
| Official Answers Published |
| April 21, 2023 |
| Bid Amendment Deadline. Bid documents will not be amended after this date. |
| April 21, 2023 |
| Deadline for Quotes/Bid Responses / Bids Due |
| May 5, 2023 |
| Notification of Apparent Successful Bidder(s) (Estimated) (posted on COMMBUYS) |
| May 12, 2023 |
| Estimated Contract Execution / Work Start |
| May 19, 2023 |