This Data Item Description (DID) details the requirements for a First Article Qualification Test Plan and Procedures document. The document, numbered DI-NDTI-81307A and approved on 21 NOV 2006, provides instructions for contractors to develop a comprehensive test plan for first article qualification. The plan must include specific elements such as the purpose of the test, applicable documents, description of units to be tested, detailed test procedures with step-by-step instructions, test equipment specifications, and inspection criteria defining minimum performance requirements for government acceptance. The test plan should cover worst-case scenarios for prime power input, signal levels, timing inputs, and outputs, and may include drawings, schematics, or photographs of non-commercial testing fixtures.

View the file

Other files

File Type Posted
Item Description Report.pdf PDF
Transportation Data Report.pdf PDF
FA812125Q0021.pdf PDF
Packaging Requirement.pdf PDF
Contract Data Requirements List (CDRL) Report.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DATA ITEM DESCRIPTION

Title: First Article Qualification Test Plan and Procedures

Number: DI-NDTI-81307A Approval Date: 21 NOV 2006 AMSC Number: 7649 Limitation: N/A DTIC Applicable: No GIDEP Applicable: No Office of Primary Responsibility: NS/I522 Applicable Forms: N/A

Use/relationship:

To establish test procedures, test equipment, and the inspection criteria that will be used by the contractor for first article qualification.

This Data Item Description (DID) contains the format and content preparation instructions for the data product generated by the specific and discrete task requirement as delineated in the contract.

This DID supercedes DI-NDTI-81307.

Requirements:

1. Reference documents. None.

2. Format:

The plan shall be in the contractor’s format.

3. Content:

This test plan shall include the following:

a. Purpose of test.

b. Applicable documents.

c. Description of units to be tested.

d. Test description to include the following:

(1) Step-by-step procedures which are to be followed by the operator when performing each test.

(2) Define readings to be taken, settings to be used, and description of the test equipment, including commercial identification.

DI-NDTI-81307A

(3) Drawings, schematics, photographs, etc, of noncommercial fixtures and testers necessary for test evaluation.

e. Inspection criteria that defines the minimum performance requirements that the unit under test must meet in order to be considered acceptable to the Government. This shall include, as a minimum, worst case prime power input, worst case signal level and timing inputs, and signal level and timing outputs.

4. END OF DI-NDTI-81307A