Darien Lift Station Relocation _ Advertisemen.pdf
PDF 211 KB Posted
- Attached to
- Lift Station Relocation
- Solicitation number
- PE-66435-NONST-2027-000000003
- Issued by
- Long County, Georgia
About this file
This is a Notice of Competitive Solicitation issued by the City of Darien, Georgia (Bid #2604) for the relocation and replacement of an existing lift station. The project involves furnishing all labor, equipment, materials, and appurtenances to replace the lift station located below the Darien River Bridge as part of a larger bridge replacement initiative. Scope of work includes construction of a new lift station and valve vault with odor control measures, installation of 8-inch C900 DR18 force main piping totaling 530 linear feet (293 LF open cut and 237 LF directional bore), rerouting 300 linear feet of existing 12-inch gravity sewer main, and abandonment and demolition of the existing lift station after activation of the new facility. A non-mandatory pre-bid conference is scheduled for 10 a.m. on Thursday, September 17, 2026, at City Hall (702 North Way, Darien, GA 31305). Sealed bids must be submitted and received at City Hall no later than 10 a.m. on Thursday, October 1, 2026, with bids typed or printed in ink and marked "SEALED BID" with the applicable bid number on the outside.
All bids must be accompanied by a bid bond in an amount not less than five percent (5%) of the bid amount, or alternatively, a cashier's check or certified check. The successful bidder will be required to furnish performance and payment bonds equal to one hundred percent (100%) of the contract amount. Payment terms provide for monthly compensation within 30 days following receipt and approval by the Owner's Representative of a valid invoice for services rendered. The technical contact for the project is Rusty Lovett Roberts of Roberts Civil Engineering, LLC (rulovett@robertscivilengineering.com). The City of Darien reserves the right to waive all technicalities, reject any or all bids, and make the award in its best interest.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Darien Lift Station Relocation _ Project Manu.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF DARIEN, GEORGIA
NOTICE OF COMPETITIVE SOLICITATION
BID # 2604
DATE: Thursday, September 3, 2026
PROJECT TITLE:
City of Darien, Lift Station Relocation
PROJECT:
The City of Darien, hereinafter referred to as “Owner”, is currently requesting proposals to furnish all labor, equipment, materials, and other appurtenances to replace the existing lift station located below the Darien River Bridge in conjunction with the larger bridge replacement project. The construction of a new lift station, valve vault with odor control measures, installment of 8” C900 DR18 force main piping (±293 LF open cut and ±237 LF of directional bore), and rerouting ±300 LF of existing 12” gravity sewer main.
The project will also include the abandonment and demolition of the existing lift station and necessary components after the new lift station is activated.
NON-MANDATORY
PRE-BID CONFERENCE:
10 a.m., Thursday, September 17, 2026, at the City of Darien City Hall located at 702 North Way, Darien, GA 31305
BID OPENING DATE:
10 a.m., Thursday, October 1, 2026, at the City of Darien City Hall located at 702 North Way, Darien, GA 31305
SUBMISSION OF BIDS: Bids must be typed or printed in ink. Bids submitted must include the "Bidders Response Schedule" and be returned in a sealed envelope marked, "SEALED BID" with the applicable "BID NUMBER" on the outside. It is the responsibility of the bidder to have the sealed bids at the City of Darien, City Hall prior to 10AM, on Thursday, October 1, 2026.
BID BOND:
All bids must be accompanied by a bid bond in an amount not less than five percent (5%) of the amount bid. A cashiers or certified check may be submitted in lieu of a bid bond.
PERFORMANCE/
PAYMENT BONDS:
The successful Bidder, if awarded this contract, will be required to furnish performance and payment bonds in the amount of one hundred percent (100%) of the contract amount.
PAYMENT TERMS:
The successful Bidder will receive monthly payments within 30 days after receipt and approval by the Owner’s Representative of a valid invoice for those services rendered.
TECHNICAL CONTACT:
Rusty Lovett Roberts Civil Engineering, LLC rulovett@robertscivilengineering.com
THE OWNER RESERVES THE RIGHT TO WAIVE ALL TECHNICALITIES, REJECT ANY OR ALL BIDS