RFI.pdf

PDF 1 MB Posted

Attached to
Vehicle Barrier System
Solicitation number
D-27-DA-0008
Issued by

About this file

This is a Request for Information (RFI) issued by the Drug Enforcement Administration (DEA), Office of Acquisition, for market research and acquisition planning regarding replacement of an active vehicle barrier system at the Dallas Field Division facility located at 10160 Technology Blvd East, Dallas, Texas 75520. The RFI Notice Number is D-27-DA-0008.

The Government seeks information on industry capabilities, available solutions, technical approaches, and methods for meeting the anticipated requirement outlined in the accompanying Draft Statement of Work (SOW). Interested companies must submit information/capabilities packages via email to Jose Marin, Contract Specialist (jose.l.marin@dea.gov), no later than 10:00 a.m. Eastern Time, December 8, 2026, with "Response to Vehicle Barrier System" in the subject line. Required submissions include company overview and capabilities, UEI and CAGE code, GSA Schedule/Contract number if applicable, applicable NAICS codes and business size, relevant past performance and experience, technical approach and proposed solutions, estimated pricing information, and recommendations or feedback regarding the draft requirement. This is a voluntary market research effort with no obligation to issue a solicitation or award a contract; the Government will not reimburse response costs, responses will not be returned, and all submissions become government property. Respondents should identify any proprietary information in their submissions.

The Draft SOW requires removal of the existing vehicle barrier system and provision of a complete, operational M30/P1 active vehicle barrier system (achieving ASTM F2656/F2656M rating for impact by a 15,000-pound truck at 30 mph with penetration not exceeding 1 meter) including two independently operable, powered wedge-type barrier assemblies (one per lane), two new powered traffic arm assemblies, red STOP and green GO LED traffic signal assemblies per lane, common supervisory control and individual lane control, civil work, electrical power, wiring, controls, safety equipment, integration, commissioning, and restoration. The scope includes all engineering, supervision, labor, materials, equipment, excavation, concrete, reinforcing steel, anchors, drainage, electrical feeders and branch circuits, raceways, conductors, communications cabling, disconnects, controls, hydraulic components, safety devices, finishes, testing, training, permits, and disposal. The Contractor must retain and protect existing perimeter gates, fences, masonry columns, building systems, and unrelated equipment, and coordinate barrier operation with retained gate operators and existing access control systems. The Government will finalize critical project parameters before solicitation, including facility and work limits, verified lane widths, applicable ASTM edition, required approvals and listings, available electrical source and feeder route/length, access control interface and point list, normal operating cycle time, emergency fast operation and deployment time requirements, power-loss position and recovery sequence, backup duration and powered cycle count, operating temperature range, approved work hours and outage durations, temporary protection requirements, completion period, and warranty response times. Deliverables include a manufacturer-authorized startup representative, qualified licensed electrical personnel, professional engineering design where required by law or contract, coordinated installation package with product data, crash-test documentation, site plan, foundation drawings, one-line and point-to-point diagrams, controls architecture, sequence of operation, safety hazard analysis, and commissioning plan; construction schedule, traffic and pedestrian control plan, temporary security plan, outage and cutover plan, waste management plan, installer qualifications matrix; at least four hours onsite training for operators and maintenance personnel; searchable electronic operation and maintenance manuals, as-built drawings, electrical diagrams, equipment serial numbers, inspection and test reports, maintenance intervals, recommended spare parts, warranties, and service contacts; and minimum one-year warranty covering furnished equipment, workmanship, programming, and integration with critical-outage response times and local service capability identified. Optional additional one-year maintenance periods shall be separately priced. A baseline schedule must be submitted within ten business days of notice to proceed, and the Contractor shall maintain daily work and test records while protecting facility information and complying with access, escort, photography, and personnel vetting requirements.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Vehicle Barrier System

Request for Information (RFI)

Notice Type: Request for Information

Notice Number: D-27-DA-0008

Requirement Title: Replacement of Active Vehicle Barrier System

Agency and Contracting Activity: The Drug Enforcement Administration (DEA), Office of Acquisition

Program Office/Requiring Activity: Dallas Field Division

This notice is issued solely for market research and acquisition planning purposes. It is not a request for proposals, proposal abstracts, quotations, or bids, and it does not constitute a solicitation or commitment by the Government. The requested information will be used to assess industry capabilities and practices, technical and operational feasibility, market conditions, potential barriers, and other considerations that may inform requirements development and acquisition planning.

This Request for Information (RFI) does not constitute an obligation by the Drug Enforcement Administration (DEA) to enter into a contractual agreement. This RFI does not constitute a commitment, implied or otherwise, that the DEA will issue a solicitation in the future. Submission of any information in response to this market survey is purely voluntary, and the government assumes no financial responsibility for any costs incurred to respond. All submissions become government property and will not be returned.

Background

The Government is seeking information regarding industry capabilities, available solutions, technical approaches, and potential methods of meeting its anticipated requirement to provide the service stated on the below Draft Statement of Work (SOW).

Requested Information

Interested companies are requested to provide:

- Company overview and capabilities.

- UEI and CAGE code.

- GSA Schedule/Contract number (if applicable)

- Applicable NAICS codes and business size.

- Relevant past performance and experience.

- Technical approach and proposed solutions.

- Estimated pricing information, if applicable.

- Any recommendations or feedback regarding the draft requirement.

Vehicle Barrier System

Submission Instructions

Information/Capabilities packages shall be submitted (via e-mail) to the POC listed below not later than 10:00 am, Eastern Time, December 8, 2026. Any questions concerning this announcement shall be in writing (e-mail) to the POC listed below. No telephone calls will be accepted. POC: The Point of Contact is Jose Marin, Contract Specialist, jose.l.marin@dea.gov In the subject line of your email, state: "Response to Vehicle Barrier System" No responses will be accepted by mail or fax. Submittals will not be returned.

Telephonic responses will not be honored.

Disclaimer

This RFI is issued for market research and preliminary acquisition planning purposes only and does not constitute a solicitation. The Government is not requesting proposals, quotations, or bids at this time.

Participation is voluntary. The Government will not reimburse respondents for any costs associated with preparing or submitting a response. Responses will not be returned.

Submission of a response does not guarantee that a respondent will receive additional information regarding any future acquisition and does not confer any preference, priority, or entitlement to participate in a future procurement.

The Government may use information received through this RFI to inform requirements development and acquisition planning. Respondents should clearly identify any proprietary information contained in their submissions.

The Government is under no obligation to issue a solicitation or award a contract as a result of this RFI. If a solicitation is subsequently issued, it will be announced separately in accordance with applicable acquisition requirements.

mailto:jose.l.marin@dea.gov

Barrier System Replacement | Page 1

Statement of Work Removal and Replacement of Active Vehicle Barrier System

DRAFT FOR PROJECT REVIEW | November 17, 2026

Dallas Field Division/DEA 10160 Technology Blvd East, Dallas, Texas 75520 Project number: 1

The Contractor shall remove the existing vehicle barrier system and provide a complete, operational M30/P1 active vehicle barrier system, including civil work, electrical power, wiring, controls, safety equipment, integration, commissioning, and restoration. This draft uses the two-lane arrangement visible in the Government-provided photographs as its scope basis. Photographs do not establish dimensions, utility conditions, existing ratings, or equipment serviceability.

1 Scope and project basis Provide two independently operable, powered wedge-type vehicle barrier assemblies, one per existing vehicle lane, two new powered traffic arm assemblies, and one red STOP and green GO traffic signal assembly per lane. Provide common supervisory control and individual lane control. Maintain existing usable lane widths unless the Government approves a revised layout. Final barrier widths, foundations, roadway elevations, equipment locations, and impact orientation shall be established by field survey and approved design.

Provide all engineering, supervision, labor, materials, equipment, excavation, concrete, reinforcing steel, anchors, drainage, electrical feeders and branch circuits, raceways, conductors, communications cabling, disconnects, controls, hydraulic components where applicable, safety devices, finishes, testing, training, permits, and disposal necessary for a complete system. No operational component shall be omitted solely because it is not individually listed.

Retain and protect existing perimeter gates, fences, masonry columns, building systems, and unrelated equipment. Coordinate barrier operation with the retained gate operators and existing access control system.

Replace existing barrier equipment, traffic arms, associated controls, and associated power and control wiring within the project limits. Existing equipment or raceways may be reused only where specifically identified in approved submittals and verified suitable.

2 Requirements to finalize before solicitation The Government shall complete the following project schedule before solicitation. These entries establish bidding requirements and shall not be left to differing bidder assumptions: facility and work limits; verified lane widths; applicable ASTM edition; required Government or agency approvals and listings; available electrical source and approximate feeder route and length; access control interface and point list; normal operating cycle time; emergency fast operation requirement and deployment time, if required; power-loss position and recovery sequence; backup duration and powered cycle count; operating temperature range; approved work hours and outage durations; temporary protection requirements; completion period; and warranty response times.

This draft specifies M30/P1. The Government security authority shall confirm the penetration limit, barrier placement, stand-off, approach conditions, and continuity of adjacent vehicle resistance before solicitation.

Emergency fast operation and any safety-device override shall be explicitly defined by the Government and reviewed in the project safety design. Ordinary warning arms, fencing, and existing yellow posts shall not be credited with crash resistance without supporting documentation.

3 Codes qualifications and design Comply with the code editions adopted by the authority having jurisdiction and the editions expressly incorporated into the contract. Applicable requirements include NFPA 70 for electrical installations, NFPA 70E for electrical work practices, OSHA construction safety requirements, applicable building and fire codes, and manufacturer installation instructions. Apply UL 325 and ASTM F2200 to gate or operator equipment where within their scope. Apply agency criteria, including UFGS 34 75 13.13 and applicable UFC provisions, only where expressly incorporated by the contract.

Barrier System Replacement | Page 2

Provide manufacturer-authorized barrier installation and startup personnel and qualified, appropriately licensed electrical personnel. Provide civil, structural, and electrical design by appropriately licensed professional engineers where required by law or the contract. The Contractor remains responsible for coordination among trades and for a complete design compatible with the tested barrier configuration.

Obtain required excavation, electrical, and construction permits and inspections. Submit conflicts among code requirements, tested configuration, manufacturer instructions, and contract requirements for resolution before procurement or affected work. Government review does not relieve the Contractor of design, code compliance, or workmanship obligations.

4 Survey and submittals Before demolition, survey and document lane dimensions, slopes, pavement and slab conditions, gate movements, drainage, underground utilities, foundations, equipment, wiring routes, and existing control interfaces. Perform utility locating, including private utilities, and nondestructive investigation as needed. Verify source voltage, phase, frequency, grounding arrangement, panel capacity, available fault current, and service condition. Do not infer these values from photographs.

Submit a coordinated installation package before procurement: product data and model numbers; crash-test documentation; site plan and barrier layout; foundation and reinforcement drawings; anchorage and soil assumptions; drainage details; demolition and restoration limits; power one-line diagram; load and voltage-drop calculations; equipment short-circuit ratings; panel and circuit schedules; grounding details; conduit and cable schedules; point-to-point wiring and termination diagrams; controls architecture; interface point list; sequence of operation; safety hazard analysis; and commissioning plan.

Include proposed normal, emergency, maintenance, fault, communications-loss, and power-loss sequences;

sensor locations and coverage; warning timing; interlocks; command priority; manual operation; and power restoration behavior. Identify all departures from the crash-tested configuration, proposed reuse, exclusions, and required outages. Obtain Government approval before procurement and affected installation.

Submit a construction schedule, traffic and pedestrian control plan, temporary security plan, outage and cutover plan, waste management plan, installer qualifications, and manufacturer maintenance requirements. Provide a clear responsibility matrix for barrier, electrical, gate, and access control work.

5 Temporary protection and removal Do not disable or remove the existing barriers until the Government approves the temporary security measures and work sequence. Maintain emergency access, safe pedestrian routes, and controlled vehicle access. Provide temporary barriers and traffic management appropriate to the Government-approved protection requirement.

Cones and warning tape alone shall not be represented as anti-ram protection.

Coordinate and obtain authorization for outages. Isolate all electrical, hydraulic, pneumatic, battery, and stored-energy sources; apply lockout and tagout; and verify safe isolation. Drain and contain fluids before removal.

Protect adjacent active systems and maintain required access throughout construction.

Remove the existing two barrier assemblies, traffic arms, operators, dedicated obsolete cabinets, pumps or hydraulic units, hoses, associated wiring, and abandoned accessories within the approved demolition limits.

Remove incompatible foundations and anchors as necessary for the new system. Remove abandoned conductors back to the approved source or termination point; disconnect, label, and make safe any retained circuit portions.

Offer identified salvage to the Government before disposal. Legally remove remaining debris and fluids from the site. Do not discharge fluids into soil or drains. Stop affected work and notify the Government upon discovery of suspect hazardous materials, unidentified utilities, or concealed conditions requiring a changed design. Repair Contractor-caused damage at no additional cost.

6 Crash performance and barrier equipment Each active barrier assembly shall achieve an ASTM F2656/F2656M M30/P1 rating: impact by a nominal 15,000-pound medium-duty truck at 30 miles per hour, with measured penetration not exceeding 1 meter.

Provide an independent full-scale crash-test report identifying the standard edition, actual impact conditions, penetration result, tested width, orientation, foundation, anchorage, and installation configuration.

Barrier System Replacement | Page 3

The furnished system shall match the configuration supporting the specified rating. Product-family claims, sales literature, or an unspecified M30 designation alone are insufficient. Any variation in width, foundation, reinforcement, anchorage, soil support, or configuration shall be identified and supported by qualified engineering analysis and accepted by the Government security authority before procurement. Engineering analysis shall not substitute for the required base full-scale crash test.

Provide new equipment suitable for outdoor service and the specified traffic volume, vehicle loading, climate, corrosion exposure, and duty cycle. Provide slip-resistant traffic surfaces, visible reflective markings, protected moving components, accessible maintenance points, positive position sensing, and lockable service access.

Provide manufacturer-approved manual recovery and stored-energy isolation provisions.

Provide new hydraulic equipment, piping, hoses, fittings, fluid, leak containment, and isolation provisions where a hydraulic system is selected. Protect exposed lines from traffic and physical damage. Provide temperature control and environmental protection required by the selected equipment and site conditions.

7 Foundations drainage and restoration Provide foundations, reinforcement, embeds, and anchorage consistent with the crash-test documentation and approved site-specific engineering. Verify soil bearing and support assumptions. Do not reuse existing foundations solely because the replacement fits the existing opening. Protect nearby structures and utilities during excavation; provide shoring and dewatering as required.

Provide pavement cuts, excavation, bedding, backfill, compaction, and concrete placement. Inspect reinforcement and embeds before concrete placement. Perform required concrete strength and compaction testing. Do not operate or load the installation until required concrete strength and manufacturer conditions are achieved.

Provide positive drainage of barrier pits, equipment areas, and raceways. Provide an approved drainage connection or engineered sump arrangement where gravity drainage is unavailable. A sump system shall include power, controls, maintainable access, and high-water alarm. Obtain approval for discharge; do not connect to a drainage system without authorization.

Restore pavement thickness and loading capacity, curbs, sidewalks, landscaping, striping, stop lines, and markings disturbed by the work. Match adjacent grades and finishes and eliminate trip hazards, unacceptable roadway projections, and standing water. Maintain safe pedestrian access and applicable accessibility requirements.

8 Complete electrical installation Provide a complete electrical installation from the approved facility distribution connection through every barrier, traffic arm, controller, detector, signal, heater, sump, power supply, and accessory. Include required source breakers, feeder and branch wiring, transformers where required, conduit, trenching, duct banks, pull boxes, supports, disconnects, overcurrent protection, grounding, bonding, surge protection, terminations, testing, and identification.

The electrical engineer shall establish voltage, phase, conductor sizes, protection, raceway sizes, burial depth, and circuit configuration from verified conditions, equipment loads, motor starting requirements, route length, ambient conditions, and applicable code. Include all simultaneous and standby loads. Do not assume existing circuits or panel spaces have adequate capacity. Identify source limitations before procurement; obtain approval for any required distribution modification.

Provide listed equipment where required and equipment ratings suitable for the available fault current and exposure. Provide properly coordinated overcurrent and motor overload protection. Install lockable disconnecting means at locations required by code and manufacturer instructions, with required working clearances and permanent source identification. Update panel directories and provide required electrical hazard labels.

Provide copper conductors with insulation and cable types suitable for the circuit, wet locations, outdoor exposure, temperature, and installation method. Provide complete raceway systems, traffic-rated boxes where exposed to vehicle loads, required expansion fittings, physical protection at risers, sealed building penetrations, and underground warning identification. Locate pull and junction boxes for safe maintenance; prohibit concealed inaccessible splices.

Barrier System Replacement | Page 4

Separate power, control, safety, and communications circuits as required by code and manufacturer instructions. Use shielded or twisted-pair cable where required; terminate shields according to the approved design. Provide listed wet-location splicing systems where permitted, strain relief, watertight entries, and permanent identification at both ends of every conductor and cable. Seal raceways to limit water, gas, and pest migration.

Bond barriers, cabinets, raceways, operators, and associated conductive equipment to the facility grounding system through an approved equipment grounding path. Ground rods shall not substitute for required equipment grounding conductors. Provide coordinated surge protection for power and exposed control or communications circuits, compatible with the connected equipment.

Provide outdoor electrical and control enclosures rated at least NEMA 4, with NEMA 4X where corrosive exposure requires it. Provide condensation control and heating or cooling as necessary, without compromising enclosure ratings. Protect all wiring from moving parts, sharp edges, vandalism, and vehicle impact.

Provide a manufacturer-approved backup arrangement sized to the Government-established duration and required powered cycles. Identify separately whether backup supports controls only or also barrier movement, traffic arms, warnings, and essential auxiliaries. Submit sizing and load calculations. Provide protected manual recovery during extended outages. Do not connect to facility emergency power without approved capacity verification and authorization.

Replace barrier-related power, control, detector, and interface wiring within the approved work limits. Reuse an existing raceway only after inspection, sizing, continuity or bonding verification as applicable, and confirmation that it is clear, sound, correctly routed, and compliant. Replace unsuitable raceways. Provide new final connections to retained gate and access control equipment.

9 Controls integration and safety Provide local maintenance controls and operator controls at the Government-designated security position.

Provide individual lane selection, normal raise and lower commands, barrier up and down status, movement indication, fault indication, power-loss or backup status, emergency stop, and authorized reset. Clearly label controls and distinguish barrier functions from traffic arm functions.

Provide all interface modules, relays, isolated contacts, power supplies, cabling, programming, and coordinated support necessary to integrate the new system with retained gates and the existing access control system.

Verify interface compatibility and avoid unapproved modifications to listed equipment. Do not add wireless, remote vendor access, cloud services, or network connections without Government approval. Apply agency cybersecurity requirements to any authorized network connection.

Provide an approved safety scheme including vehicle-presence detection, monitored safety devices where required, warning signals, and additional obstruction or entrapment protection identified by the hazard analysis.

Position detection zones to cover the barrier hazard area. Provide red and green lane signals and audible or visual movement warnings consistent with the approved sequence and site requirements.

10 Stop and go traffic lights Provide one complete red STOP and green GO LED traffic signal assembly for each of the two vehicle lanes, including signal heads, visors, mounting poles or brackets, foundations or anchors, controllers, relays, power supplies, surge protection, conduit, conductors, terminations, programming, and all accessories. Position each assembly for clear visibility to approaching drivers without ambiguity between lanes. Submit signal locations, mounting heights, aiming, brightness control, and applicable traffic-control compliance for Government approval.

Provide equipment suitable for continuous outdoor operation and the specified site environment.

Interlock each lane signal with that lane’s barrier, traffic arm, and retained gate. Display red STOP whenever the barrier is raised, moving, not confirmed fully lowered, or unavailable for passage. Display green GO only after a valid vehicle-release command and positive confirmation that the barrier is fully lowered, the traffic arm and gate are in their approved passage positions, and all required passage permissives are satisfied. Prevent simultaneous red and green indications. Return to red before initiating a normal closing or barrier-raising sequence, using the approved warning and clearance timing.

On a detected position disagreement, communications fault, or control fault, inhibit green and provide red STOP when power is available. Include the signal controls and red indication in the approved backup-power load

Barrier System Replacement | Page 5 calculations. Loss of signal power shall not result in a green indication or authorize vehicle release. Establish a controlled stop procedure for a dark or failed signal. Require deliberate operator reset after fault clearance or power restoration in accordance with the approved sequence.

During acceptance testing, verify each lane’s red and green indications through normal passage, barrier and traffic-arm movement, gate movement, simulated position and communications faults, power loss, backup operation, and restoration. Confirm visibility from the driver approach, no conflicting indications, correct warning and clearance timing, and that green cannot illuminate without all required passage confirmations.

Coordinate barrier, traffic arm, and gate movement to prevent conflicting commands and vehicle release toward an unsafe barrier condition. A release indication shall require confirmed passage conditions. Automatic cycles shall not deploy a barrier under an occupied detection zone. Define responses to sensor failure, gate disagreement, communications failure, and conflicting commands; annunciate faults and prevent unintended movement.

Do not assume emergency fast operation overrides ordinary safety inputs. If required by the finalized project schedule, provide the approved emergency sequence, protected activation controls, warning functions, command priority, and documented safety implications. Emergency stop and emergency deployment are separate functions and shall have distinct controls and instructions.

Power restoration shall not cause unexpected movement or automatic vehicle release. Require deliberate reset or operator action as established by the approved sequence. Provide safe maintenance isolation, protection from stored energy, and manufacturer-approved mechanical blocking or restraint where required. Coordinate emergency responder access with the Government fire and security authorities.

10 Inspection testing and acceptance Provide a manufacturer-authorized startup representative and an approved written test procedure. Give the Government at least five business days notice of acceptance testing. Complete required permits and inspections before acceptance. Field acceptance shall verify installation and operation; no destructive vehicle crash test is required at the facility.

Verify approved equipment and installation dimensions; foundation records and concrete strength; anchorage;

drainage; markings; enclosure ratings; accessibility for maintenance; and continuity of the approved protected boundary. Inspect electrical workmanship, conductor identification, torque records, grounding and bonding, protective device ratings, source voltage, phase rotation where applicable, and running voltage and current.

Perform electrical continuity, insulation resistance, and grounding tests appropriate to the installed system using manufacturer-approved methods. Isolate sensitive electronics and surge devices where required before testing.

Record results and acceptance limits. Demonstrate backup operation under representative loads and verify the specified duration or cycles using an approved test method.

Demonstrate each lane independently and the coordinated system. Test normal cycling, operator controls, position feedback, warnings, traffic arms, gate and access control interfaces, every safety input, occupied detection zones, simulated sensor faults, emergency stop, manual recovery, communications loss, power loss, and restoration. Test emergency fast operation only if included, under controlled conditions with an exclusion zone.

As a project acceptance criterion, complete at least 50 consecutive normal operating cycles per lane without unresolved faults, within the manufacturer duty cycle. Record operating times and confirm contract limits. Verify drainage by controlled water testing without flooding electrical equipment. Document all results, deficiencies, corrective action, and retests.

Correct deficiencies and repeat affected tests at no additional cost. Government acceptance requires satisfactory operation, completed inspections, approved test reports, restored site conditions, training, and closeout deliverables. Beneficial use alone does not establish final acceptance.

11 Training closeout and warranty Provide at least four hours of onsite training for designated operators and maintenance personnel covering normal operation, warnings, safety devices, emergency actions, power loss, manual recovery, isolation, routine

Barrier System Replacement | Page 6 inspections, and fault reporting. Provide manufacturer instructions and demonstrate procedures using the installed system.

Deliver searchable electronic operation and maintenance manuals; approved as-built site and foundation drawings; electrical one-line and point-to-point diagrams; conduit and cable schedules; circuit directories;

equipment serial numbers; crash-test documentation; inspection and test reports; maintenance intervals;

recommended spare parts; warranties; service contacts; keys; and authorized software licenses, configuration backups, and securely transferred administrative credentials.

Provide a minimum one-year warranty covering furnished equipment, workmanship, programming, and integration beginning at final Government acceptance, subject to contract warranty provisions. Correct covered defects at no additional cost, including labor, travel, replacement parts, and retesting. State required critical-outage response and restoration times in the finalized project schedule. Identify local service capability and include manufacturer-required preventive maintenance during the warranty period.

12 Maintenance and Optional Extended Service

The Contractor shall provide maintenance for one year beginning on the date of Government final acceptance.

Maintenance shall include manufacturer-recommended preventive maintenance, inspections, adjustments, lubrication, troubleshooting, and corrective repairs for the barrier system, controls, safety devices, electrical components, and stop/go signal lights. Labor, travel, service calls, and replacement parts required for normal operation shall be included. The Contractor shall document all maintenance and repairs and provide service reports to the Government.

The Contractor shall separately price optional additional one-year maintenance periods and identify any exclusions and service response times. Extensions shall be exercised at the Government’s discretion through written authorization by the Contracting Officer, subject to availability of funds.

13 Schedule and contract administration Submit the baseline schedule within ten business days after notice to proceed, including surveys, design, Government reviews, long-lead procurement, demolition, installation, outages, commissioning, and training. The contract shall establish the completion period and Government review durations before award. Coordinate all field work with the designated Government representative; only the Contracting Officer may authorize changes affecting price, scope, or contract time.

Maintain daily work and test records. Protect facility information and comply with access, escort, photography, personnel vetting, and material delivery requirements stated in the contract. Keep the site orderly and leave the installation secure at the end of every shift.

Barrier System Replacement | Page 7

Appendix A Existing site reference photographs Government-provided photographs show opposite views of the same two-lane barrier location. They are reference images only; quantities and dimensions shall be field verified. Visible conditions do not establish the existing system manufacturer, rating, or service condition.

View 1 Existing two-lane barrier arrangement

Barrier System Replacement | Page 8

View 2 Opposite side of existing barrier arrangement

Drafting references ASTM F2656/F2656M, Standard Test Method for Crash Testing of Vehicle Security Barriers; CISA, Dams Sector Active and Passive Vehicle Barriers Guide; and UFGS 34 75 13.13, Crash Rated Active Vehicle Barriers and Controls. These informed the draft; only editions and provisions expressly incorporated into the final contract are binding. Final design and code review remain project requirements.

https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2034%2075%2013.13.pdf

RFI Barrier System.pdf
Request for Information (RFI)
RFI.pdf
M30_Barrier_Replacement_SOW DFD 20261117.pdf
1 Scope and project basis
2 Requirements to finalize before solicitation
3 Codes qualifications and design
4 Survey and submittals
5 Temporary protection and removal
6 Crash performance and barrier equipment
7 Foundations drainage and restoration
8 Complete electrical installation
9 Controls integration and safety
10 Stop and go traffic lights
10 Inspection testing and acceptance
11 Training closeout and warranty
13 Schedule and contract administration
Appendix A Existing site reference photographs
Drafting references