This document is a Justification & Approval for Other Than Full and Open Competition form for a simplified acquisition by the National Park Service. The procurement is for contracted removal of a landslide slump formation blocking a visitor throughway on National Park Scenic Drive (NU RT 10), involving hauling concrete debris and landscape restoration. The urgent justification stems from heavy rainfall in FY25 causing a landscape slide that partially blocked one traffic lane, creating potential safety hazards.

The document indicates urgent and compelling circumstances warrant a sole source procurement, with market research conducted by requesting a vendor to inspect the site. The National Park Service (NPS) currently lacks the capacity and equipment to remove the debris in accordance with Standard Operating Procedure 3426. The document is dated 17 July 2025, with digital signatures from Philip T. McCall (Chief of Facility Management) and Joseph Kirk (Contracting Officer) approving the non-competitive acquisition process. The specific cost estimate is redacted in the document.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Last updated 6/2/2016

ATTACHMENT 2

JUSTIFICATION & APPROVAL FOR OTHER THAN FULL AND OPEN COMPETITION

for SIMPLIFIED ACQUISITIONS OVER THE MICROPURCHASE THRESHOLD (See FAR

Part 2) UP TO SAT (See FAR 13.106-1)

Date: _17 July 2025_______________________

PR Number: 44024934_________________________

1. Nature and/or description of the item/service being procured and its intended use (include the anticipated cost):

___Contracted removal of landslide slump formation partially blocking visitor throughfare on National Park Scenic Drive – NU RT 10, hauling of roadway concrete debris and restoration of landscape to permit normalized park operations and restoration of traffic lane. The government estimate the cost to be

2. Sole Source Justification rationale (Check one and explain below):

______ Only one responsible source.

___X___ Urgent and compelling circumstances exist. Include critical delivery or performance dates, and when you became aware of the requirement. Provide a specific statement of the impact on Government operations, financial or otherwise, if the required delivery or performance dates are not met.

______ Other _____________________________________________________

Explain: The park has experienced higher than regular normal rainfall in FY25, 2.17 inches on MAY 15, and 1.78 inches which caused lubrication of the landscape causing slides to occur partially closing 1 half lane of traffic. With half of the lane being blocked, traffic is having to merge into the oncoming lane to pass the area safely. Having the rubbish on have the road increases the chances of accidents to occur if not removed ASAP. Park personnel currently do not have capacity or machine flexibility to remove this debris in accordance with SO 3426.

3. Market Research. Please explain the results or why one was not performed. State whether any other offers were received, or anyone expressed interest:

Market research was performed by requesting a vendor to visit the site to inspect and provide feedback on how to clean up the pile. Currently NPS had secured area with traffic control devices temporarily.

Last updated 6/2/2016

ATTACHMENT 2

JUSTIFICATION AND APPROVAL FOR OTHER THAN FULL AND OPEN COMPETITION

for SIMPLIFIED ACQUISITIONS OVER $3,000 ($2,000/$2500 for Construction/Services AND UP

TO $150,000

(See FAR 13.106-1)

PR Number ________________________

4. If this is a determination for sole source, the contracting officer certifies:

a. Only one source is available, or urgent and compelling circumstances exist.

b. The anticipated price will be determined fair and reasonable using the price analysis techniques described in FAR Part 13.106-3(a).

(Signature) ___//s// Philip T. McCall (Date)_________14 July 2025____________

Type or Print Name: ______Chief of Facility Management Title:

(Signature) _______________________________________ (Date) ___________________________

Type or Print Name: __________________________________________ Contracting Officer Over $50,000:(if applicable)

(Signature) _______________________________________ (Date) ______________________

Warranted Individual 1 Level Above Contracting Officer

PHILIP MCCALL Digitally signed by PHILIP MCCALL Date: 2025.07.17 10:12:03 -06'00'

JOSEPH

KIRK

Digitally signed by

JOSEPH KIRK

Date: 2025.07.18 09:36:11 -06'00'

File details come from the government source that posted it. Updated .