About this file

This Addendum 1 document pertains to a delegated design, fabrication, and installation project issued by the New York State Office of Parks, Recreation and Historic Preservation for alternative pedestrian access improvements at Niagara Falls State Park. The project encompasses the design and installation of two metal staircases to provide alternative access to Goat Island, construction of asphalt trails, and associated landscape improvements including tree protection, site preparation, concrete foundations, handrails, erosion control measures, earthwork, asphalt pavement, and landscape planting with an 18-month guarantee. A mandatory pre-bid meeting was held on September 21, 2026, at 11:30 AM at the Niagara Falls State Park Riverway Parking Area. Requests for Information (RFIs) must be submitted by September 30, 2026, at 4:00 PM, and sealed bids are due by 10:30 AM local time on October 14, 2026, with public opening via WebEx at 11:00 AM. The contract term is 365 days from approval by the New York State Comptroller's Office, with an estimated construction start of November 26 and substantial completion targeted for October 27.

The base bid cost estimate ranges from $645,225 to $872,951, with Alternate 1 (painting and coating of galvanized metal staircases) estimated between $153,000 and $207,000. Bid security is $47,000, and the project includes a $36,100 allowance with liquidated damages of $1,500 per day for project delays. This is a lump sum prime contract with Minority Business Enterprise (MBE) participation goals of 28% and Women Business Enterprise (WBE) goals of 2%; under Public Building Law 8(6), a responsible and reliable NYS-certified MWBE firm submitting a bid within ten percent of the lowest bid will be deemed the apparent low bidder if the bid does not exceed $1,737,918. Contractors and subcontractors must register with the New York State Bureau of Public Work and Prevailing Wage Enforcement and provide registration certificates at bid opening; failure to do so results in automatic disqualification. Significant work restrictions apply, including no work during high-volume park visitation weekends and holidays, no spring planting between April 15 and June 15, no fall planting between August 15 and November 15, no seeding between March 16 and September 30, and no tree clearing and removal between April 1 and October 31. Bidders must also complete a Gender-Based Violence and Workplace Certification form and provide an Executive Order No. 16 certification prior to contract award.

View the file

Other files

File Type Posted
D006640 NTB.pdf PDF
D006640 Addendum 2.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Kathy Hochul Kathy Moser John Honan Governor Commissioner Western Capital District Manager

New York State Office of Parks, Recreation and Historic Preservation - Niagara Region PO Box 1132, Niagara Falls, NY 14303 (716) 278-1770 www.nysparks.com

ADDENDUM 1

JOB NAME AND PROJECT NUMBER

Niagara Falls State Park Alternative Pedestrian Access to Goat Island General D006640

DATE: September 28, 2026

ALL BIDDERS SUBMITTING A BID FOR THE ABOVE-NAMED PROJECT SHALL TAKE NOTE OF THE

FOLLOWING CHANGES, ADDITIONS, INTERPRETATIONS, CLARIFICATIONS, ETC. IN CONNECTION WITH THE DRAWINGS AND SPECIFICATIONS AND OTHER BID DOCUMENTS. THE FOLLOWING INSTRUCTIONS HAVE PRECEDENCE OVER ANYTHING CONTRARILY SHOWN ON THE DRAWINGS OR DESCRIBED IN THE SPECIFICATION DOCUMENTS, AND ALL SUCH INFORMATION SHALL BE TAKEN INTO CONSIDERATION AND BE INCLUDED IN THE BIDDERS BID AMOUNT. ACKNOWLEDGE RECEIPT OF THIS ADDENDUM BY INSERTING ITS NUMBER AND DATE IN THE SPACE PROVIDED IN THE BID FORM. FAILURE TO DO SO

MAY SUBJECT BIDDER TO DISQUALIFICATION.

Summary of Addendum Items:

ITEM #1 - Included with Addendum 1 are the pre-bid meeting agenda and sign-in sheet held on September 21, 2026, at the Niagara Falls State Park- Riverway Parking Area.

END OF ADDENDUM 1

Niagara Falls State Park Alternative Pedestrian Access to Goat Island 332 Prospect St., Niagara Falls NY 14303

Project No. D006640 - General Construction Meeting Date: Sept. 21, 2026, at 11:30am Location: Niagara Falls SP- Riverway

All information provided during this meeting is for information only and is intended to be helpful. Any information discussed or presented at this meeting does not, and cannot, alter the contract documents. The contract drawings and project manual can only be modified via addendum. Technical questions from potential bidders must be submitted in the form of an RFI prior to the RFI due date. Bidders must register with NYS Parks to ensure receipt of any project addenda. Bids which do not acknowledge receipt of addenda will be disqualified.

Pre-Bid Meeting Agenda:

1. Introductions

2. Project Narrative:

The project includes the delegated design, fabrication and installation of two metal staircases to provide an alternative pedestrian access route to Goat Island, as well as the construction of asphalt trails and associated landscape improvements.

3. Project Scope of Work:

· Site protection of staging areas and work areas which includes temporary and movable chain-link construction fence, with privacy screens, additional temporary barriers, and access gates.

· Temporary pedestrian and vehicular access signs.

· Tree protection and pruning. Protection shall include avoidance of disturbance to tree root zones.

· Site preparation, selective demolition and removals

· Delegated design, fabrication and installation of metal staircases

· Reinforced cast-in-place concrete foundations

· Fabrication and installation of handrails

· Installation of temporary facilities and controls

· Installation of temporary soil erosion and control measures

· Earthwork and grading

· Cast-in-place concrete pavement

· Full-depth asphalt pavement

· Amendment of existing lawn or planted areas with approved topsoil and compost for plantings or lawn restoration.

· Landscape planting, including trees and shrubs

· Care for and maintenance of trees, shrubs and lawn until completion of contract.

· Provision of an 18-month guarantee for plantings with an additional 12-month guarantee for replacements

· Other Work indicated in the Contract Documents

4. Proposed Construction Schedule: (Project Completion is 365 days from Contract Approval by the NYS Comptroller’s Office)

· Estimated Contract Approval & Construction Start: 11/26

· Estimated Substantial Completion: 10/27

· Estimated Contract End Date: 11/27

5. Type of Contract: Lump Sum Prime Contract

6. Estimated Contract Value:

· Base Bid: $645,225 to $872,951

· Alternate 1 (Painting and Coating of Galvanized Metal Staircases): $153,000 to $207,000

Includes surface preparation, finishing, and coating of the two metal staircases following galvanization.

7. Overview of the Project Manual and Drawings:

D006640 General Construction

· Notice to Bidders

· Bid Form (Contractors to submit their Bids on the respective Bid Form as provided including the

NEW Gender-Based Violence and Workplace Certification) Effective November 5, 2025, State Finance Law § 139-m requires all vendors bidding on New York State contracts to implement and attest to a Gender-Based Violence and the Workplace policy. This policy must be in place for a bid to be considered.

· Alternates: 1 Alternate

· Bid Security: $47,000

· Project Allowance: $36,100

· Liquidated Damages: $1,500 for each day of project delay

· MWBE Goals (28% MBE / 2% WBE)

· Wage Rates (this is a prevailing wage rate job)

· Contractor Registry Requirement- Newly established subsection 220-i to

NYS Labor Law Article 8 requires contractors and subcontractors to register with the Bureau of Public Work and Prevailing Wage Enforcement for public work. Contractors must complete registration prior to bidding on public work projects covered under Article 8 of Labor Law. Bidders must prove they are registered at the time of bid opening by submitting a digital copy of their company’s registration certificate with their bid. Failure to provide the registration certificate at bid opening will result in automatic disqualification. The apparent low bidder will additionally be held responsible to provide copies of registration certificates for all subcontractors on their approved Utilization Plan before subcontractors commence work.

· Pursuant to Public Buildings Law § 8(6), effective January 11, 2020, for any projects where the project design commenced on or after January 1, 2020 and for any contracts over $5,000 for the work of construction, reconstruction, alteration, repair, or improvement of any State building, a responsible and reliable NYS-certified Minority or Women-Owned Business Enterprise that submits a bid within ten percent of the lowest bid will be deemed the apparent low bidder provided that the bid is $1,737,918 or less, adjusted annually for inflation as of March 1, 2026. If more than one responsible and reliable MWBE firm meets these requirements, the MWBE firm with the lowest bid will be deemed the apparent low bidder.

8. General Information:

a) Bidders are reminded to thoroughly review the drawings and specifications to obtain a complete understanding of the entire project scope. Existing restrictions and regulations will not be considered as grounds for additional cost over bid price.

· Instructions to Bidders

· Spec. Section 011000 – Summary of Work o Project information o Work covered by Contract Documents o Contractor's use of site and premises o Work restrictions

- No work will be allowed on the following high-volume park visitation weekends and holidays (Contractor to bid the project with this in mind and account for these non-workdays within the base bid price)

- Comply with the following construction date restrictions:

Spring Planting Period April 15th – June 15th

Fall Planting Period August 15th – November 15th

Seeding March 16th – September 30th

No tree clearing and removal April 1st – October 31st o Specification and Drawing Conventions o Miscellaneous provisions

· Spec Section 020105- Maintenance and Protection of Traffic and Site Visitors

· Spec Section 028100- Off-Site Transportation and Disposal

· Spec Section 013573- Delegated Design

b) RFI Schedule:

· RFI’s are due on 9/30/26 at 4pm. RFI’s received after this time and date will not be processed and bidders will have to bid the project as documented.

· Questions as they relate to the Contract documents are to be forwarded via e-mail to Eleanor Gaddi (eleanor.gaddi@parks.ny.gov) on the RFI Form provided in the project manual.

· The RFI response will be communicated by Addendum to all bidders who have obtained drawings and specifications.

c) Bid Opening:

· Bids shall be sent via email to western.capital.procurement@parks.ny.gov.

· Deadline for bid submission is 10:30 AM local time, 10/14/26 and will be publicly opened and read via Webex at 11:00 AM local time, 10/14/26.

· The Bid opening will be conducted ONLY via WebEx at the link listed below:

https://meetny-gov.webex.com/meetny-gov/j.php?MTID=mf2a5a5046a3e6550ed79c80844e844c2

· Late bids will not be eligible for consideration.

D006640 Addendum 1
ADDENDUM 1
JOB NAME AND PROJECT NUMBER
DATE: September 28, 2026
D006640 Pre-Bid Mtg Agenda
Niagara Falls State Park
Alternative Pedestrian Access to Goat Island
Pre-Bid Meeting Agenda:
April 15th – June 15th
Spring Planting Period
August 15th – November 15th
Fall Planting Period
March 16th – September 30th
Seeding
April 1st – October 31st
No tree clearing and removal