About this file

This document summarizes an awarded federal contract notice for raising and reconstructing roads and utilities to accommodate redevelopment of the Town of Martin Phase II site in Martin, Kentucky. The US Army Corps of Engineers, Huntington District awarded contract number W91237-20-C-0007 to Aspen Construction Company on August 3, 2020 for $27,443,282.74. The work involves hollow site excavation to a specified elevation to remove the area from flood risk, raising existing KY-1428 and Ice Plant Hollow Road, construction and adjustment of certain utilities, and final grading and reclamation of a borrow site. The period of performance is in Martin, Kentucky, and the award was set aside for total small business.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IAW FAR 5.207

1. Action Code: C

2. Date: 3 August

3. Year: 2020

4. Contracting Office Zip Code: 25701-2070

5. Product of Service Code: Y1QA

6. Contracting Office Address:

US Army Corps of Engineers, Huntington District, 502 8th Street, Huntington, WV 25701-2070

7. Subject:

Town of Martin Phase II Redevelopment Site, Martin. KY

8. Proposed Solicitation Number: W9123720B0002

9. Closing Response Date: 10 June 2020

10. Contact Points:

Kristin D. Blake, Contract Specialist, (304) 399-5693

Bethany D. Clinton, Contracting Officer, (304) 399-5692

11. Contract Award Number: W9123720C0007

12. Contract Award Dollar Amount: $27,443,282.74 Base and all options

13. Contract Line Item Number: 1-307

14. Contract Award Date: 3 August 2020

15. Contractor: Aspen Construction Company, 3798 State 371 NW, Hackensack, MN 56452-

16. Description: Hollow site to a specified elevation (removed from flood risk) in the area situated between KY-1428 and base of the mountain forming the valley wall of Beaver Creek at the Town of Martin. Raising existing KY-1428 and existing Ice Plant Hollow Road to accommodate and serve the Phase II site and the residents of Ice Plant Hollow and to maintain traffic through the area. Construction and/or adjustment of certain utilities necessary to accommodate the project and provide for future services at the Phase 2 Redevelopment Site.

Final grading and reclamation of the Mayo Hollow borrow site.

17. Place of Contract Performance: Martin, KY

18. Set-A-Side Status: Total Small Business

Kristin D. Blake, Contract Specialist

Bethany D. Clinton, Contracting Officer

2020-08-03T14:22:24-0400
Bethany D. Clinton
2020-08-03T14:51:38-0400
Kristin D. Blake

File details come from the government source that posted it. Updated .