CUI//SP-PROCURE//LDC

PERFORMANCE WORK STATEMENT

TANK SYSTEM AND ASSOCIATED PIPING THICKNESS AND TIGHTNESS TESTING

AT THE CHEMICAL TRANSFER FACILITY (CTF), BLDG E3832

AND

MUNITIONS ASSESSMENT AND PROCESSING SYSTEM (MAPS) FACILITY, BLDG E1457

ABERDEEN PROVING GROUND (APG) MD 21010

1. INTRODUCTION

The U.S. Army Combat Capabilities Development Command Chemical Biological Center (DEVCOM CBC) Chemical Transfer Facility (CTF) is a repository for research and development stock of toxic chemical agents. The facility includes a critical system of storage tanks and piping. State regulations require that the storage tank system be tested for thickness and tightness every two years.

DEVCOM CBC’s Munitions Assessment and Processing System (MAPS) facility is a multi-component technology designed to drill, drain, decontaminate and detonate waste chemical munitions and other similar items. The facility includes tanks and piping to move and store hazardous waste. State regulations require periodic tank system integrity assessments.

1.1 BACKGROUND

The CTF has a system of storage tanks and piping. The Code of Maryland Regulation (COMAR) and Maryland’s Controlled Hazardous Substances permit #A-190 requires this system be tested for thickness and tightness every two years. The system was last tested in June 2020.

The MAPS has a system of storage tanks and piping. The COMAR and Maryland’s Controlled Hazardous Substances permit #A-190 requires periodic integrity assessments every three years. The system was last inspected in June 2020.

1.2 OBJECTIVE.

The objective of this contract is to conduct thickness and tightness testing on the CTF storage tanks and piping, conduct formal external inspections of the tanks, a formal visual inspection and hydrostatic testing of the piping system at the MAPS, and received the resulting reports.

2.0 APPLICABLE DOCUMENTS

2.1 COMAR 26.13.05.10D(4).

2.2 American Petroleum Institute (API) Standard 653 (Tank Inspection, Repair, Alteration, and Reconstruction)

2.3 API Standard 570 (Piping Inspection Code)

2.4 Steel Tank Institute (STI) Standard SP001 (Inspection of Aboveground Storage Tanks)

2.5 Army Directive 2014-05/Army Regulation (AR) 190-13

3.0. DELIVERABLES. All data shall be delivered in accordance with the attached DD Form 1423. The contractor may obtain a copy of Data Item Descriptions listed in block 4 from: https://quicksearch.dla.mil/qsSearch.aspx

3.1 Inspection Reports. The deliverables shall include a Final Written Inspection Report in accordance with Exhibit Line Item Number A001 and a briefing to the CTF and MAPS personnel. For the CTF, the report shall cover the piping and each of the five tanks; four (4) elevated tanks and one (1) sump tank below grade. The report shall include vessel and piping layouts and vessel drawings. Each drawing will show associated thickness results. For MAPS, the report shall cover the five tanks and the piping system. Contractor shall provide all instrumentation, transducers and personnel required to perform services.

3.2 Annual Progress Reports. The contractor shall provide an annual progress report in in accordance with Exhibit Line Item Number A002. The report shall outline the effort performed to date under the contract, assessment of technical progress, and any issues that may impact scope, schedule, and project status. The report shall also propose any performance measures, subject to Government review and approval, which will effectively demonstrate whether the objectives are being achieved.

4.0. SCOPE OF SERVICES. The U.S. Army Combat Capabilities Development Command, Chemical Biological Center (DEVCOM CBC) requires Thickness and Tightness Testing of the CTF tank system and associated piping equipment to ensure sufficient structural strength, as required by the Resource Conservation and Recovery Act (RCRA) Permit and the Code of Maryland Regulation (COMAR) 26.13.05.10D(4). The Chemical Transfer Facility is Building E3832 on the Edgewood Area of Aberdeen Proving Ground. The street address is 8897 Guard Street, Aberdeen Proving Ground, Maryland 21010.

The CTF tanks include a reactor tank (500 gallon), a sump tank (600 gallon), a receiving tank (1800 gallon), and two final hold tanks (1800 gallon each). The reactor tank, receiving tank, and the two final hold tanks are above ground. The sump tank is below floor level, but the contractor will not be required to access that area. These 5 non-insolated tanks will not be empty during testing. These 5 tanks require external inspections including American Petroleum Institute (API) Standard 653 (Tank Inspection, Repair, Alteration, and Reconstruction), API Standard 570 (Piping Inspection Code), and Steel Tank Institute (STI) Standard SP001 (Inspection of Aboveground Storage Tanks).

Additional description regarding the piping connected to the tanks that must be tested are as follow: The hazardous waste piping consists of 3" carbon steel piping, 2" carbon steel piping, 2" stainless steel piping, 1-1/2" stainless steel piping, 1" stainless steel piping, and 3/4" stainless steel piping. All piping is above grade.

The MAPS facility is Building E1457 on the Edgewood Area of Aberdeen Proving Ground. The street address is 9026 Ricketts Point Road, Aberdeen Proving Ground, Maryland 21010.

The MAPS tank system includes two fiberglass reinforced plastic tanks (300 gal each), three stainless steel tanks (332 gal each) and associated piping. These tanks will be empty during testing. These five tanks require formal external inspections in accordance with STI Standard SP001 (Inspection of Aboveground Storage Tanks). The hazardous waste piping system requires a formal visual inspection in accordance with API-570 and pressure testing in accordance with API 570 Section 5.8.2 and applicable requirements in COMAR 26.13.05.

The MAPS facility is located on a secure area of APG. The contractor shall ensure that all employees conducting service visits provide information required for background checks to meet access requirements to secure areas on APG. Background checks will be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. After a successful background check, the contractor employee will receive an ESCORT REQUIRED badge. After contract award, the contractor will be given contact information for individuals that can act as an escort for pump-outs.

5.0 AVAILABLE INFORMATION

The Government will provide the following information and documentation regarding the CTF and MAPS tank systems to the awardee upon award via email:

a. Previous Professional Engineering Certification in conformance with Resource Conservation and Recovery Act (RCRA) and any available contract documents consisting of design documents (plans and specification and design report) with modifications, if any, made during the installation and operational history of the tank system. All documentation is stored on site for review.

b. Results of original tank and piping thickness and tightness testing. All documentation is stored on site for review.

c. List of personnel familiar with the installation and operation of the system for conducting interviews to establish the installation procedures and/or past operational performance of the system.

d. Standing Operating Procedures (SOP) and Operations and Maintenance (O&M) Manuals related for the tank system.

6.0. REQUIREMENTS. Personnel Requirements: Technicians performing field measurements shall have Level I certification in Ultrasonic Testing by the American Society of Nondestructive Testing. All work shall be reviewed by personnel certified Level III in Ultrasonic Testing by the American Society of Nondestructive Testing. Personnel shall provide a copies of the technician’s certifications to the Contracting Officer’s Representative (COR) prior to the start of work. MAPS inspections shall be conducted by STI-SP001 and API-570 certified inspectors.

6.1 Testing must be completed by the dates outlined in Section 6.3. If not completed by these dates, the CTF and MAPS will be in violation of the Maryland Department of the Environment (MDE) Permit and fines will occur.

6.2 Tank thickness, tightness testing, hydrostatic testing and formal visual inspections shall occur in accordance with the dates outlined in Section 6.3 and will be scheduled by mutual agreement between the Government and the Contractor. The testing report shall be provided to the Government within two weeks of test performance.

6.3 Period of Performance (PoP): Shall be 1 year, with 3 option years.

6.3.1 Base Year - The CTF shall be tested in June 2022. PoP will be from June 2022 to May 2023. The inspection report shall be delivered 30 days after completion of test.

6.3.2 Option Year 1 – The MAPS shall be tested in June 2023. PoP will be from June 2023 to May 2024. The inspection report shall be delivered 30 days after completion of test.

6.3.3 Option Year 2 – The CTF shall be tested in June 2024. PoP will be from June 2024 to May 2025. The inspection report shall be delivered 30 days after completion of test.

6.3.4 Option Year 3 – The MAPS and CTF shall be tested in April 2026. PoP will be from June 2025 to May 2026. The inspection reports shall be delivered 30 days after completion of tests.

7.0 ENVIRONMENTAL

7.1 Contractor shall comply with all applicable federal, state, and local environmental laws, statutes, regulations, executive orders, permits, Army regulations (with supplements), as well as Major Subordinate Command (MSC) and installation regulations and policies. Contractor shall immediately report any conflicts between applicable federal, state, local environmental laws, statutes, executive orders, and provisions of Army Regulation 200-1, and any specifications within this contract to the COR as well as the Director of Engineering & Public Works.

7.2 Contractor shall immediately report any nonconformance and/or noncompliance with applicable Federal, State or Local environmental laws, Army and installation environmental regulations or policies to the COR and Director of Engineering & Public Works.

8.0 SAFETY AND HEALTH

Contractor personnel or any representative of the contractor shall abide by all federal and Department of the Army safety regulations while working on the Aberdeen Proving Grounds.

9.0. SECURITY STATEMENTS

9.1 Access and general protection/security policy and procedures. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility, or area. Contractor and all associated subcontractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by Department of Defense (DoD), Headquarters, Department of the Army (HQDA) and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

9.2 For contractors that do not require a Common Access Card (CAC), but require access to a DoD facility or installation. Contractor and all associated subcontractor employees shall comply with adjudication standards and processes using the National Crime Information Center Interstate Identification Index (NCIC- Ill) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/ facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

CUI//SP-PROCURE//LDC