The Government's Core Requirement for the Danvers Firehouse include:
· Pre-Engineered Steel Building Kit inclusive of all components required for erection, including concrete anchor bolts, and (2) sets of engineered erection drawings/specifications.
· 96'-0 x 42'-0 interior dimension (Clear Span with no interior columns).
· 19'-0 minimum eave height.
· 4:12 Pitched Insulated Gable Roof (R-20 minimum) able to resist minimum 50 psf snow load suitable for construction in Massachusetts.
· Painted and Insulated Wall Panels (R-13 minimum) w/ min 26 gauge exterior sheeting able to resist up to 130mph wind load.
· (4) each 18'-0w x 16'-0h insulated overhead doors w/ electric openers and hardware.
· (2) each 3'-0 x 7'-0 Personnel Doors with hardware.
· (2) 24" x 24" Fixed Louver for ventilation with hardware.
Delivery of entire kit to Danvers, MA Period of Performance: 90 Calendar Days after effective date of the Award.