Contract A _ Mooty Bridge Force Main _ Sewer .pdf
PDF 700 KB Posted
- Solicitation number
- PE-74150-NONST-2024-000000009
- Issued by
- Walker County, Georgia
About this file
This document is a base bid form for Contract A of the 2024 Mooty Bridge Force Main & Sewer Improvements project in LaGrange, Georgia. The project, which is being managed by Troup County, involves the construction, testing, and placing into service of various components of a 14" HDPE force main and 8" PVC sewer line, including open-cut construction, horizontal directional drilling, bore installation, and associated appurtenances such as manholes and air valves. The bid form lists 12 line items with quantities, unit prices, and total prices for the work. The project also includes erosion control measures, mobilization, demobilization, and an allowance for field testing of materials.
Pricing terms are not explicitly stated, but the bid form indicates that the Owner will be furnishing certain equipment and materials for Contract A. No set-asides or incumbent information is provided. The project appears to be funded through local sources, as no federal or state funding requirements are mentioned. The total base bid amount is to be provided by the bidder, and the amount shown in words will govern in case of conflict.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Notice to Contractors _ Contract A_2024 Mooty.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BASE BID FORM -REVISED 4-5-2024
Contract A - 2024 Mooty Bridge Force Main & Sewer Improvements
LaGrange, Georgia
Each of the following Base Bid Items includes the Construction, Testing & Placing into Service of each Base Bid Item, Complete per the Plans, Specifications & Contract Documents. Refer to Specification Section 01152, I.10 Explanation of Bid Items and Payment. Also, refer to Section 00800, 1.C. for a list of Equipment and Materials furnished by the Owner for Contract A. All required clearing is included in the Erosion Control Bid Item.
Item No. Description Quantity Unit Unit Price Total Price
Contract A - 2024 Mooty Bridge Force Main & Sewer Improvements
1 14" HDPE, DR 11 (DIPS) Force Main, Min.4' Depth, Open Cut Construction, Complete per Plans. 1360 LF $_______________ $_______________
2 14" HDPE, DR 11 (DIPS) Force Main, Min.4' Depth, HDD Construction Sta 0+90 to Sta 2+00; Sta 10+15 to Sta 13+70 & Sta 18+40 to Sta 26+15 as noted, Complete per Plans. HDD No Rock Cost per LF. 1240 LF $_______________ $_______________
3 Rock Clause - Provide the HDD Rock Cost per LF above the HDD No Rock Cost per LF, as Bid in Item 2 above. 1 LF 400.00$ 400.00$
4 12" Force Main Discharge Piping inside 5' Dog-House Manhole with poured invert, Complete per Plans & Detail C590 1 LS $_______________ $_______________
5 3" Combination Air Valve Assembly with Backwash Accessories inside 5' Dia. Dog-House Manhole, Complete per Plans & Detail C600 1 LS $_______________ $_______________
6 Install Bore for Mooty Bridge Road, 14" HDPE DR 11 Force Main, 20" Steel Casing with End Seals, see Plan Sheet B-7. 50 LF $_______________ $_______________
7 Remove existing 8" Clay Sewer and Install 8" PVC SDR 26 Sewer, see Plan Sheet B-8 for actual depths.
This task requires sewer bypassing during construction. 280 LF $_______________ $_______________
8 Install 4" HDPE Power, 2" HDPE Fiber & 2" HDPE Water on east side of 14" Force Main from Sta 0+00 to Sta 3+80, to be located during construction. HDD Construction required from Sta 0+90 to Sta 2+00. 380 LF $_______________ $_______________
00300-4
BASE BID FORM -REVISED 4-5-2024
Contract A - 2024 Mooty Bridge Force Main & Sewer Improvements
LaGrange, Georgia
Each of the following Base Bid Items includes the Construction, Testing & Placing into Service of each Base Bid Item, Complete per the Plans, Specifications & Contract Documents. Refer to Specification Section 01152, I.10 Explanation of Bid Items and Payment. Also, refer to Section 00800, 1.C. for a list of Equipment and Materials furnished by the Owner for Contract A. All required clearing is included in the Erosion Control Bid Item.
Item No. Description Quantity Unit Unit Price Total Price
9 Erosion Control Plans & Details, Complete per Plans 1 LS $_______________ $_______________
10 Mobilization 1 LS 10,000.00$ 10,000.00$
11 Demobilization 1 LS 5,000.00$ 5,000.00$
12 Allowance for Field Testing of Materials, Only if Approved by the Engineer for Payment 1 LS 5,000.00$ 5,000.00$
TOTAL BASE BID AMOUNT (Total of Items 1-12) $_______________
Total Base Bid In Words: ____________________________________________________________________ _______________________________________________________________ Dollars and Cents (In Case of Conflict, The Amount Shown in Words Shall Govern)
00300-5
| Addendum No. 1 Signed.pdf |
| 00300-BBF-2024 Mooty Bridge FM&S-Contract A-Addendum 1.pdf |
| Sheet1 |
File details come from the government source that posted it. Updated .