Consultant SOI New Stickney Reconstruction.pdf
PDF 253 KB Posted
- Attached to
- A&E Services, New Stickney Reconstruction
- Solicitation number
- 22SOI7923
- Issued by
- Beadle County, South Dakota
About this file
This document is a Request for Statements of Interest issued by the South Dakota Department of Game, Fish and Parks (GFP) for Administration/Design/Construction services to be performed on the owner's behalf for the spillway replacement at New Stickney Lake in Aurora County, near Stickney, South Dakota. The project's scope of work includes geotechnical borings, site investigations, spillway replacement recommendations, design and plans preparation activities for grading and spillway structure replacement, land surveying, hydrologic/hydraulic design, and construction inspection. The selected consultant will be required to provide a 30% design concepts report by December 16, 2022, 60% design plans and cost estimate by February 2, 2023, and final design plans by March 15, 2023. Construction is to be completed by February 16, 2024, and the administration by June 1, 2024. Statements of Interest must be submitted by 5:00 PM CT on September 9, 2022 and should include the consultant's qualifications, capabilities, resources, past performance, availability, and project management approach.
The selection will be made by a technical review committee based on the stated criteria. The chosen consultant will be required to provide detailed invoices showing cost breakdowns billed to specific project codes in half-hour increments. There is no mention of pricing terms, set-asides, incumbents, funding requirements, or other salient financial information in the document.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
605.223.7660 | GFP.SD.GOV
WILDINFO@STATE.SD.US | PARKSINFO@STATE.SD.US
SOUTH DAKOTA DEPARTMENT OF
GAME, FISH AND PARKS
523 EAST CAPITOL AVENUE | PIERRE, SD 57501
REQUEST FOR STATEMENTS OF INTEREST
Date: August 18, 2022
To: Interested Consultant
Subject: Administration/Design/Construction for the following project located in Aurora County
(Near Stickney, South Dakota):
• Slope grading and spillway repair.
The Department of Game, Fish and Parks (GFP) is soliciting Statements of Interest for Administration/Design/Construction services to be performed on the owner’s behalf to provide site investigations, plans, specifications, cost estimates, and site inspection/testing for the spillway replacement at New Stickney Lake. The consultant will be working alongside SD GFP to provide plans, specs, and information to FEMA & SD DANR for the duration of the project.
The projects scope of work will include, but is not limited to:
• Geotechnical borings, site investigations, and spillway replacement recommendations for the project.
• Design and plans preparation activities for grading.
• Design and plans preparation activities for replacement of the spillway structure.
• Land surveying activities.
• Hydrologic/hydraulic design activities for replacement of the structure.
• Construction inspection activities for grading and structure replacement.
The Consultant shall provide site investigation & 30% design concepts report for the project by December 16th, 2022. The Consultant shall provide 60% design plans & cost estimate by February 2nd, 2023. The project completion date for design and submitting final design plans has been set as March 15th, 2023, Construction completion date has been set as February 16th, 2024, and Administration completion date has been set as June 1st, 2024.
The chosen Consultant will be asked to provide detailed invoices showing cost breakdowns billed to specific project codes in half hour increments.
Firms wishing to be considered for providing Administration/Design/Construction services for this project should send a Statement of Interest that outlines their qualifications and experience relative to this project.
Statements of Interest must include at a minimum:
• Specialized expertise, capabilities, and experience as demonstrated by the teams’ capabilities, and the proposed approach and methodology to meet the project requirements. (30%)
• Resources available to perform the work, including any specialized services, within the specified time limits for the project. Include resumes of all personnel, including all sub-consultants who will be assigned to this project. (30%)
• Record of past performance, including price and cost data from previous projects, quality of work, ability to meet schedules, cost control, and contract administration. (10%)
• Availability to project locale. (5%)
• Ability and proven history in handling special project constraints. (15%)
• Proposed project management techniques. (5%)
• Familiarity with project locale. (5%)
A technical review committee will select a firm based on the response to the criteria listed above.
605.223.7660 | GFP.SD.GOV
WILDINFO@STATE.SD.US | PARKSINFO@STATE.SD.US
SOUTH DAKOTA DEPARTMENT OF
GAME, FISH AND PARKS
523 EAST CAPITOL AVENUE | PIERRE, SD 57501
Copies of the Statement of Interest must be submitted by 5:00 PM CT on September 9th, 2022. Please send both a recyclable hard copy and electronic copy (media or e-mail attachment) to:
James Gilkerson, P.E.
Department of Game, Fish, and Parks 523 E Capitol Pierre, SD 57501-3182 Phone: 605-773-4521 Email: James.Gilkerson@state.sd.us
Those firms that desire additional information specific to the project may contact James Gilkerson at (605)- 773-4521 or email James.Gilkerson@state.sd.us
Thank you for your interest in this project. We look forward to working with you.
Sincerely, Ryan Tobin Engineering Supervisor Game, Fish and Parks
Ryan Tobin (Aug 18, 2022 15:44 CDT) Ryan Tobin
File details come from the government source that posted it. Updated .