Construction Scope of Work.pdf

PDF 3 MB Posted

Attached to
Window Caulking at Federal Courthouse in Fargo, North Dakota
Solicitation number
47PJ0022R0043
Issued by

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(Construction Scope of Work)

CONSTRUCTION SCOPE OF WORK

U.S. GENERAL SERVICES ADMINISTRATION, ROCKY MOUNTAIN REGION 8

Date: 02/28/2022 Revision:

Section 1: Project Title Fargo Quentin Burdick Federal Building Courthouse, Seal West Courthouse 2nd Floor Windows and East Historic Courthouse south façade windows.

Section 2: Project Location, Building Name, & Building Number Fargo Quentin Burdick Federal Building Courthouse Annex, 655 1st St Ave N, Fargo ND 58102 Building Number: ND0047ZZ, ND0006ZZ

Section 3: Contact List

Contracting Officer (CO) Name: Cody Lee Email: cody.lee@gsa.gov Address: 657 2nd Ave N. #244 Fargo, ND 58102 Phone (O): (701) 566-6124

Contract Specialist (CS) Name: Laura Funk Email laura.funk@gsa.gov Address: 657 2nd Ave N. #244 Fargo, ND 58102 Phone (O): (701) 566-6114

Project Manager Name: Jim Boisjolie Email: james.boisjolie @gsa.gov Address: 657 2nd Ave N. #244 Fargo, ND 58102 Phone (O): (701) 541-2368

Property Manager Name: Travis Mart Email: travis.mart@gsa.gov Address: 657 2nd Ave N. #244 Fargo, ND 58102 Phone (O): (701) 566-6126

Section 4: Project Background & Project Description The purpose of this project is to prevent moisture from entering the windows. The exterior seals around the edges of the windows are to be removed and re-caulked as a preventative maintenance measure.

Section 5: Project Objectives The contractor shall provide all labor, materials, equipment, and supervision to provide a complete project as listed below.

1) Remove failed, loose, or damaged caulk/sealant.

2) Prepare surfaces for new caulk/sealant for maximum adhesion.

3) Protect existing surfaces not receiving caulk. Remove and clean any areas of over-application or accidental application not intended to be applied.

4) Install new caulk/sealant. New caulk/sealant colors will match existing materials. New caulk/sealant will be approved for the materials on which it is used. Existing materials consist of metal (aluminum) and glass.

5) Contractor is responsible for temporary barricading of sidewalks and driveways as well as procuring of necessary ROW permitting. Overnight storing of equipment on site will be the responsibility of the Contractor and any storage locations must have prior approval of the Building Manager.

6) Upon completion, clean work areas including glass, sills, aluminum frame, and stone. Remove all tools, equipment, and materials. Remove work related debris and trash. Clean exterior windows.

7) Provide 1 year warranty.

8) Window Types “G”, “H”, and “I” in Building 47 were sealed under a previous project.

9) A staging area will be determined by mutual agreement after contract award.

10) The following information is provided for bidding purposes only. The contractor is advised to conduct a site visit and field-verify the exact information required for use in completing the work and submitting an offer.

11) No asbestos or lead containing materials shall be used.

12) The contractor is responsible for the protection of all existing building property surfaces from damage due to work performed under this contract. Damages to existing surfaces caused by the performance of this contract shall be repaired as to match the existing surface finish at no additional cost to the Government.

13) The Contractor shall remove all debris generated in the performance of this contract daily.

14) At the completion of the project, the project area shall be cleaned to building standards as determined by the GSA Property

Manager. Should the contractor fail to clean the project limits in a timely manner, GSA will contract for said cleaning and the cost will be deducted from the contract. Ensure that all penetrations are sealed with fire rated approved material as required by the International Building Code.

15) The CO has the right to reject any unsatisfactory or unsuitable material or workmanship.

Section 6: Proposal Pricing & Site Walk

1) Pre-proposal Site Visit Meeting:

a) The site visit shall consist of a meeting to review construction requirements followed by a walk-thru of the project site. The meeting shall be attended by the contractor and GSA project personnel, and appropriate sub-contractors. Contact the Project Manager to schedule a site visit.

b) Review existing conditions of the project area including any field verification.

c) Review the solicitation/evaluation requirements.

d) Contact Project Manager to schedule a site visit.

2) Cost Proposal Requirements:

a) When submitting a proposal, provide a cost breakdown for each task into the following categories: Materials, equipment, labor hours, subcontractor's quotes, overhead, profit, and bond broken down into shell, tenant improvement (TI) (by tenant), Building- Specific Amortized Capital (BSAC), and environmental (as applicable). Follow P120 guidelines for tier level 3 based on project triage tool. Pricing shall be broken down by Construction Specification Institute (CSI) divisions.

b) Provide two separate bids, one for work to be performed on the West Courthouse (Bldg ND0047ZZ) and a separate bid for work to be performed on the East Historic Courthouse (Bldg ND0006ZZ).

Section 7: Period of Performance

Once award has been issued, the contractor has 90 calendar days to complete the project. The contractor must also promptly begin the badging process at the time of award. Please allow a minimum of 30 days to complete the badging process. Extensions will be granted for unforeseen conditions and other factors outside of the contractor’s control at the Contracting Officer’s discretion.

Section 8: Universal Scope Requirements ALL of the requirements in this section are MANDATORY for ALL GSA projects

See the attached Universal Scope Requirements document for the full details outlining each item

Failure to comply with any and all of the requirements will result in the project not being accepted as complete

REQUIREMENTS for ALL Projects (Construction, Design & Design/Build)

a. Safety and Health Program

b. Asbestos Containing Materials. To comply with federal and state regulations as well as GSA policy, an asbestos pre-alteration assessment is required for all construction projects as outlined in Section B of the Universal Scope Requirements.

c. Lead Containing Paint / Lead Based Paint

d. Accessibility

e. Green Purchasing

f. Construction Indoor Air Quality (IAQ) Management Plan

g. Construction Waste Diversion

REQUIREMENTS for ALL projects IF APPLICABLE

h. Excavation Permit

i. Utility Locates

j. gBuild

k. Historic Compliance

l. Commissioning (for all new AHUs or all new building system equipment)

m. GSA IT Network

n. Building Monitoring and Control Systems (BMC)

o. Advanced Metering System

p. Sustainable Environmental Management System (SEMS)

Section 9: Submittals

1) Contractor shall submit a Method of Procedures (MOP) to the GSA Delivery Project Manager (PM) for approval prior to commencement of work. At a minimum, the MOP shall include:

a) Brief narrative describing method of accomplishment, construction techniques, etc

b) Project schedule (to include critical path, major milestones, long lead time items, mob & de-mob, inspection dates, substantial completion, and occupancy dates)

c) Service/Utility Outages (if necessary)

d) Phasing schedule (if necessary)

e) Any building infrastructure/BAS equipment that may be impacted

2) Manufacturer's specifications, instructions and material specification sheets in original form

3) Submittal register/ log for all products specified to establish a standard of quality to include. Submittal register response by the government shall be 14 calendar days or less.

a) For pricing purposed please assume 2 hard copies of submittals and 2 electronic copies to be sent to the project manager. Distribution list including final quantities will be finalized after receipt of the submittal log/ register by GSA project manager.

4) If product samples are not submitted in a timely fashion, any delays caused by the contractor will not warrant a time extension.

After completion of all work, the Contractor shall submit to the project manager the manufacturer's specifications, instructions and material specification sheets in original form. Additionally, the Contractor shall submit all inventory changes (removals, additions, upgrades, etc., and new condition codes) to the COR.

5) Submittal response by the government shall be 14 calendar days or less.

Section 10: General Requirements

1) Contractor Use of the Premises

a) During the period of the project, the contractor will have access to the site only during business hours of 8:00 am 5:00

pm. No on-site work shall be performed outside these hours or on holidays unless otherwise directed by the Contracting Officer. The contractor will need to coordinate with the Contracting Officer to arrange access to the parking lot. The contractor shall make every effort to cause a minimum of damage to parking lots, any other paved areas, any items that need to be moved during the course of the project, and any areas not included in this scope of work. Any damage caused will be repaired at the contractor’s expense.

b) Operations will continue during this project so particular attention shall be given to phasing of project to minimize disruptions to their activities. Contractor shall coordinate with GSA representatives and then provide a schedule with phasing and duration for each activity. Schedule approval is to be obtained at least seven days prior to any work commencing. Communication during this project will be critical to meet this need.

2) Progress Meetings

a) Progress meetings are not required for this project. The project manager and building team representative shall make daily inspections of the work progress.

3) Equipment The contractor shall provide all equipment associated with the entire project, operate in a safe manner and adhere to all OSHA and GSA standards.

4) Equipment and Material Storage The contractor shall provide and store all equipment, the materials specified above, and any other materials required completing the project. The materials are required to be kept clean and dry throughout the duration of the project.

Contractor to coordinate with building manager for location of storage sheds.

5) Sanitary Facilities Provide and maintain temporary toilet facilities in accordance with State Health Department and GSA requirements.

6) Electricity, Water, and Gas GSA will pay for electricity, water, and gas during the course of this project. The contractor is responsible for making connections to the existing systems. Temporary electrical work shall meet the requirements of NFPA 70-1996 (NEC), Article

305. When temporary connections are removed, restore existing utility services to their original condition.

7) Contractor’s Field Office The contractor may provide an office for their own use. Size, location, and construction shall be subject to approval.

8) Fire Watch Contractor shall be responsible for providing fire watch if required per attached GSA fire watch guidelines.

9) Fire Alarm Impairment and Hot Work When a fire suppression or alarm system impairment is required, contractor shall provide written outage request to GSA for approval in advance of impairing any systems. Contractor shall be responsible for having a GSA approved NICET certified fire alarm contractor perform all system impairments. During fire alarm/suppression impairments or hot work procedures, contractor shall provide a fire watch per the GSA Regional Fire Watch Guidelines.

10) Protection of Public The building site will continue to be used by tenants. The contractor shall fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. The contractor shall illuminate barricades and obstructions at night and maintain safe building access and egress for tenants.

11) Housekeeping The project site shall be kept in a neat, orderly, and safe condition at all times. The contractor shall provide enough containers for collecting construction debris and construction materials to be recycled. The contractor shall wet down dry materials and rubbish to prevent blowing dust and keep volatile wastes in covered containers.

12) Transportation and Deliveries The contractor shall arrange deliveries of materials in accordance with construction schedules; coordinate with COR to avoid conflict with other tenants and other work conditions at the site. Contractor must make GSA PM & CO aware of any lead times that may affect the project schedule.

13) Cleaning Before scheduling the final inspection, the Contractor shall accomplish six items: (1) Remove all tools, equipment, surplus material, and rubbish; (2) Restore or refinish, to original condition, surfaces that are damaged due to the work of this contract; (3) Remove grease, dirt, stains, foreign materials, and labels from finished surfaces; (4) Thoroughly clean building interiors; (5) Pickup all construction debris from the site; and (6) At time of final inspection, project shall be thoroughly cleaned and ready for use.

14) Protection of the Building The construction contractor is responsible for the protection of all existing building property for damage due to work performed under this contract. Any damage caused by the performance of this contract shall be repaired to match like or better condition at no additional cost to the government

15) Disruptive Work All painting, staining, or other activity which may cause noxious or undesirable fumes and/ or any noisy work that may be disruptive to the tenants/ public must be performed after normal working hours. The use of paint or stain that does not generate odors is preferred and may be required if the space will be occupied the following day with prior written approval from GSA.

Section 11: Badging & Security

1) Contractor is responsible to follow GSA’s security and badging requirements as detailed in the Badging & Security Requirements (Vendor Fitness Determination Training Manual) to be provided with contract Award.

2) US Access shared enrollment centers can be found at fedidcard.gov. Travel distances to the nearest center should be accounted for during the badging process.

Section 12: Payments

1) Information regarding payment requests and payment is in the solicitation/ contract. Please contact the CO if you have any questions regarding payments.

Section 13: Substantial Completion & Final Inspection

1) When project, or designated portion of project is complete, request a final inspection. Upon receipt of request that project is substantially complete, the Contracting Officer will proceed with the inspection within ten days of receipt of request or will advise the contractor of items that prevent the project from being designated substantially complete.

2) The contractor shall provide O&M manuals. The O&M manuals shall contain the following:

o Executed Warranties (at project completion) o Maintenance and operation manuals

Section 14: Historical Building: N/A

Section 15: Attachments

1) Universal Scope requirements

2) Drawings

West Courthouse – 47 Building

Work to be performed on the highlighted windows.

Approx. quantities and dimensions.

Historic Courthouse - 06 Building

All south facing windows along with the 6 windows located on the west side will be included in the bid.

File details come from the government source that posted it. Updated .