About this file

Summary

This is a Request for Proposals (RFP) issued by the County of San Mateo's County Executive's Office soliciting qualified independent certified construction auditing firms to provide construction auditing services for four San Mateo County Event Center Improvement Projects: the San Mateo County Resiliency Center (SMCRC), the Cypress Restroom Project, the RV Park Project, and the CalOES Generator Project. The selected firm will conduct a comprehensive review of project management procurement, payment procedures and records, bidding and selection processes, construction expenditures, contractor payment applications, invoices, change orders, contract modifications, labor and material costs, and supporting documentation to verify that amounts billed were properly supportable under applicable contracts and consistent with approved project records. The deadline for questions and contract exceptions is October 28, 2026, at 12:00 p.m., and proposals are due November 2, 2026, at 12:00 p.m., via the County's eProcurement portal. No pre-proposal conference or site visit is planned. The engagement requires completion of auditing services within 60 days, with required deliverables including an audit work plan, document request list, preliminary findings report, final construction audit report, management response and resolution log, supporting workpapers, and a closing meeting presentation. The contract term is one year with three optional one-year extensions at the County's sole discretion, exercisable with written notice at least 30 days before term end.

The RFP includes evaluation criteria weighted as follows: relevant construction auditing experience in potential legal action (35 percent), qualifications and experience of proposed personnel (20 percent), audit methodology and technical approach (25 percent), project schedule and staffing capacity (10 percent), and cost and overall value based on rewarding the lowest cost (10 percent). Minimum qualifications require firms to have provided similar services for a minimum of four years within the last seven years, be registered with the System for Award Management (SAM), and possess a valid Unique Entity ID (UEI) number. Proposers must submit detailed fee proposals identifying hourly rates by staff classification, estimated hours by task, reimbursable expenses, and a not-to-exceed amount for each anticipated audit assignment. The County's standard contract template has been included with the solicitation for agreements valued below $200,000, and proposers must complete legal review and submit any contract exceptions by the deadline. No incumbent, specific contract value, or set-asides are identified in the solicitation documents. The work is investigative in nature, designed to investigate allegations of financial accountability and identify potential overpayments, mispayments, and unsupported costs to improve the County's construction procurement, contract administration, and financial controls.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

County of San Mateo

Request for Proposals (RFP - Informal) for Construction

Auditing Services – San Mateo Event Center Improvement

Projects

County Executive's Office

RFP - Informal No. 2027-RFP - Informal-00183

RFP - Informal Contact: Michael Bolander mbolander@smcgov.org

1. Introduction and Schedule

The County of San Mateo (the “County” or “SMC”) covers most of the San Francisco Peninsula. The region covers 744 mi and is home to nearly 800,000 residents and 20 incorporated cities. The County provides for the health and welfare of all people within its borders and serves as the local government for the unincorporated areas. Innovation thrives here in industries including bioscience, computer software, green technology, hospitality, financial management, health care, education and transportation. The

County prides itself on how that prosperity fosters its commitment to protecting and enhancing the health, safety, welfare and natural resources of the community.

1.1. Summary

The County of San Mateo is soliciting proposals from qualified independent certified construction auditing firms with experience in potential misuse of government funds to provide construction auditing services of four San Mateo County Event Center Improvement Projects that were partially funded by the County General

Fund. The Projects include San Mateo County Resiliency Center (SMCRC); Cypress Restroom Project; RV

Park Project; and CalOES Generator Project

The selected firm will review the project management procurement, payment procedures and records, bidding and selection process, construction expenditures, contractor payment applications, invoices, change orders, contract modifications, labor and material costs, and supporting documentation to determine whether amounts billed were properly supportable under the applicable contract, and consistent with approved project records.

The purpose of these services is to investigate allegations of financial accountability, identify potential overpayments, mis payments and/or unsupported costs, verify compliance with contractual requirements, and provide findings and opportunities for improvement to the County's financial contributions construction procurement contract administration and financial controls.

1.2. Contact Information

Michael Bolander Principal Management Analyst Email: mbolander@smcgov.org Phone: (650) 363-4791

Department:

County Executive's Office

Department Head:

Michael Callagy County Executive

1.3. Timeline

RFP Released October 23, 2026

Deadline for Questions, Comments and

Contract Exceptions

October 28, 2026, 12:00pm mailto:mbolander@smcgov.org tel:(650)363-4791

Page 3 of 11 Release date of October 23, 2026

Proposal Due Date and Time November 2, 2026, 12:00pm

2. Scope of Work

2.1. SCOPE OF SERVICES

The selected consultant shall be prepared to provide fast-track construction auditing services as requested by the County and to be completed no later than 60 days.

Services may include, but are not limited to, the following:

2.1 Pre-Award and Contract Review

• Review Procurement and Bidding Records including, but not limited to, Requests for Proposals

(RFPs), bid submissions, bid tabulations, evaluation and scoring sheets, procurement documentation, and award resolutions

• Evaluate bidding procedures and compliance with existing policies related to selection process

• Review executed construction contracts, amendments, approved change orders, task orders, and other applicable contract documents.

2.2 Payment Application and Invoice Auditing

• Examine contractor payment applications, invoices, and supporting documentation.

• Verify that amounts billed are consistent with contract terms, approved pricing, and authorized work.

• Review the approved project budget, schedule of values, and contract expenditure history.

• Reconcile contractor billings with Event Center’s payment records and project accounting records.

• Verify quantities, unit prices, labor charges, equipment costs, materials, subcontractor billings, and other applicable charges.

• Review documentation supporting stored materials, mobilization, and other advance or progress payments, where permitted by the contract.

• Identify duplicate billings, mathematical errors, unsupported costs, and potential overpayments.

• Verify retainage calculations and release requirements.

2.3 Change Orders and Contract Modifications

• Analyze the validity, scope, pricing methodologies, and authorization chains for field directives and change orders.

• Review proposed and approved change orders for appropriate authorization and supporting documentation.

• Evaluate cost breakdowns, labor and equipment rates, material costs, markups, and subcontractor pricing.

• Compare modifications against the original contract, approved budget, and applicable contract provisions.

Page 4 of 11 Release date of October 23, 2026

• Identify potential cost duplication, unsupported pricing, or work billed outside the approved scope.

2.4 Compliance and Documentation Review

• Review compliance with applicable contract requirements and project payment procedures.

• Examine certified payroll records, prevailing wage documentation, subcontractor payment records, and other labor compliance documentation when included in the audit scope.

• Review applicable insurance, bonding, and other required documentation as directed by the County.

• Identify missing, inconsistent, or incomplete records that may affect the validity of project payments.

2.5 Findings and Recommendations

• Document all findings with supporting evidence and references to applicable contract provisions.

• Quantify questioned costs, potential overpayments, and other financial discrepancies when reasonably determined.

• Distinguish confirmed errors from costs requiring further investigation or clarification.

• Recommend corrective actions and improvements to the County's internal controls and construction payment procedures.

2.6 Required Deliverables

The selected consultant shall provide the following deliverables for each assigned audit:

1. Audit Work Plan: Audit objectives, procedures, records required, anticipated schedule, and proposed methodology.

2. Document Request List: Detailed list of contracts, payment records, change orders, payroll records, and other required documentation.

3. Preliminary Findings Report: Summary of potential discrepancies, unsupported costs, compliance concerns, and requests for clarification.

4. Final Construction Audit Report: Audit scope, methodology, records reviewed, findings, supporting evidence, financial impact, and recommended corrective actions.

5. Management Response and Resolution Log: Tracking of County responses, contractor explanations where applicable, corrective actions, and outstanding issues.

6. Supporting Workpapers: Organized documentation sufficient to substantiate findings and support authorized County or independent auditor review.

7. Closing Meeting: Presentation of results to designated County representatives.

All reports and work papers shall be delivered electronically in formats approved by the County. The consultant shall comply with applicable County requirements for records retention, confidentiality, and access to audit documentation.

3. Submission Requirements

Page 5 of 11 Release date of October 23, 2026

3.1. Submission Deadline

Proposals must be electronically received by 12:00 pm, on Monday, November 2, 2026, via eProcurement system.

Allow sufficient time for the upload to complete by the Due Date and Time. Partial uploads will automatically terminate, and proposals will be rejected. The eProcurement system submission time will be the official submission time. The County will not be responsible for and may not accept proposals that are late due to slow internet connections or for any other failure of the eProcurement system.

NOTE: The County does not maintain the eProcurement system and is not liable for site failures or technical problems. To resolve technical issues, contact OpenGov Technical Support by using the real time chat located in the lower right hand corner of the screen, or via email at procurement-support@opengov.com https://procurement.opengov.com/portal/smcgov

3.2. Pre-submission Registration

Organizations or individuals interested in responding to this solicitation must register online with the

County of San Mateo at:

• https://procurement.opengov.com/portal/smcgov

It is recommended that organizations complete this registration as soon as possible. The County will not be responsible for and may not accept proposals that are late due to a failure to register in the eProcurement system.

3.3. Submission via eProcurement Portal

Required Documents

Please refer to the Technical Proposal section for submittal documents and requirements.

Electronic Submissions

Include the proposer name and the RFP title and number in each filename. Submit proposals via the eProcurement website, allowing sufficient time for the upload to complete by the Due Date and Time. As noted above, the eProcurement portal submission time will be the official submission time, and partial uploads will automatically terminate, and proposals will be rejected. Contact eProcurement Portal with technical questions regarding this site.

Conflicts between Certain Requirements

Prior to the submission deadlines and solely relating to a determination of the timeliness of questions, comments, and proposal submissions, information displayed on the eProcurement portal site will take precedence in the event of a discrepancy between that information and the information within the solicitation documents. For all other discrepancies, the information in the solicitation documents will take precedence.

Format mailto:procurement-support@opengov.com mailto:procurement-support@opengov.com https://procurement.opengov.com/portal/smcgov https://procurement.opengov.com/portal/smcgov https://procurement.opengov.com/portal/smcgov/projects/320075/document?section=undefined

Page 6 of 11 Release date of October 23, 2026

Documents should be created in the following format:

• Text should be Times New Roman (12-point minimum font size) and unjustified (i.e., with a ragged-right margin)

• Pages should have margins of at least one inch on all sides (excluding headers and footers)

• If the proposal is lengthy, a Table of Contents should be included.

• PDF format is preferred.

Errors in Proposals

The County will not be liable for any errors in proposals. Proposals may be rejected as unresponsive if they are late, incomplete, missing pages or information, or cannot be opened for any reason. The County may waive minor irregularities, but such waiver will not modify any remaining RFP requirements.

3.4. County Rights an General Requirements

The County reserves the rights stated in the final solicitation, including the right to reject proposals, request clarifications, amend the solicitation, cancel the procurement, or negotiate with selected firms, as permitted by applicable law and County policy.

The selected firm shall comply with applicable County contracting requirements, insurance provisions, confidentiality obligations, records access requirements, and other terms included in the executed agreement.

4. Minimum Qualifications and Technical Proposal

4.1. Minimum Qualifications

4.1.1. Has Proposer has been providing similar services for a minimum of four (4) years within the last seven (7) years?*

☐ Yes

☐ No

*Response required

4.1.2. Please confirm your firm is registered with System for Award Management (SAM)*

☐ Please confirm

*Response required

4.1.3. What is the registered Business Name and Unique Entity ID (UEI) No.?*

Unique Entity ID (UEI) numbers can be found on sam.gov

*Response required

4.2. Technical Proposal

Proposing firms shall demonstrate:

• Experience performing construction cost audits, payment application reviews, or construction contract compliance audits.

Page 7 of 11 Release date of October 23, 2026

• Experience with public-sector construction projects, preferably for counties, cities, or other governmental agencies.

• Knowledge of construction accounting, contract administration, change orders, retainage, and project cost controls.

• Qualified personnel with appropriate auditing, accounting, construction cost, or compliance credentials.

• Independence from the contractors and other parties whose costs or activities will be audited.

• Sufficient staffing and resources to meet the County's required schedules.

Proposals shall identify any actual or potential conflicts of interest and describe how they will be addressed.

4.2.1. Introduction and Executive Summary *

Submit a letter of introduction and executive summary of the proposal. The letter must contain:

• Name, title and contact information (email, phone, and address) for representative of proposer that is responsible for communication related to this RFP.

• Name, title, contact information, and signature of person authorized to obligate firm to perform the commitment contained in the proposal.

Submission of the letter will constitute a representation by proposer that it is willing and able to perform the commitments contained in the proposal and has not violated the terms of this RFP.

*Response required

4.2.2. Statement of Minimum Qualifications *

Describe how the proposer meets the minimum qualifications as set forth in Minimum Qualifications of this RFP.

Submission of the Minimum Qualifications checklist is not a substitute for providing a detailed written response.

*Response required

4.2.3. Project Approach*

This section should correlate to the Scope of Work . Proposer should give a short summary describing how it will perform the relevant work

*Response required

4.2.4. Scope of Work tasks/milestones*

Describe your proposed approach to tasks/milestones

*Response required

4.2.5. Proposed schedule *

Page 8 of 11 Release date of October 23, 2026

Attach proposed schedule reference ability to complete the project within the County's required time frame

*Response required

4.2.6. Performance Measures*

Describe a plan for achieving performance measures

*Response required

4.2.7. Firm Qualifications *

Attach information regarding background and qualifications, including the following:

• A brief description of the proposer.

• Examples, of not more than three (3), comparable construction audit assignments conducted by the proposer, including the client, reference and telephone numbers, primary staff members involved, budget, schedule, and project summary. Descriptions should be limited to one (1) page for each project.

• If subcontractors are anticipated, identify them (if known) and provide information on how they will be used.

*Response required

4.2.8. Team Qualifications*

Provide a chart identifying:

▪ Project team and reporting structure

▪ Lead project manager

▪ Role each person will play in the project

Provide a brief description of the experience and qualifications of the project team members, including short resumes if desired.

Written assurance that the key individuals listed and identified will be performing the work and will not be substituted or reassigned without the County’s prior approval

*Response required

4.2.9. Sample construction audit report, with confidential information removed.*

*Response required

4.2.10. Proof of required insurance and other documentation specified by the County.*

*Response required

4.2.11. Disclosure of actual or potential conflicts of interest.*

*Response required

4.2.12. References*

Page 9 of 11 Release date of October 23, 2026

Provide 3 references for each of the following, including the name, address, and telephone number of recent clients (preferably other public agencies):

*Response required

4.2.13. Fee Proposal*

Firms shall submit a detailed fee proposal identifying hourly rates by staff classification, estimated hours by task, reimbursable expenses, and any proposed fixed fees.

The proposal shall include a not-to-exceed amount for each anticipated audit assignment or other pricing structure requested by the County.

All fees shall be inclusive of the services proposed, except for expenses expressly authorized by the County.

*Response required

5. Evaluation and Selection Criteria

The proposals will be evaluated by a selection committee with relevant expertise. The County intends to evaluate the proposals generally in accordance with the criteria itemized below. Proposers with the highest scoring proposals may be interviewed by the committee to make the final selection.

No. Evaluation Criteria Scoring Method Weight (Points)

1. Relevant construction auditing experience in potential legal action

Points Based 35 (35% of Total)

2. Qualifications and experience of proposed personnel

Points Based 20 (20% of Total)

3. Audit methodology and technical approach

Points Based 25 (25% of Total)

4. Project schedule and staffing capacity

Points Based 10 (10% of Total)

5. Cost and overall value Reward Low Cost 10 (10% of Total)

6. Instructions to Proposers

6.1. Instructions

There will be no pre-proposal conference or site visit for this project.

Page 10 of 11 Release date of October 23, 2026

6.2. Communications

A. As of the issuance date of this RFP and continuing until it is canceled or an award is made, no proposer or person acting on behalf of a prospective proposer may discuss any matter relating to the RFP with any officer, agent, or employee of the County, other than through eProcurement portal, to the Authorized Contact Person, or as outlined in the evaluation or protest procedures.

B. Proposers (including any agent, owner, employee, board members, or other such affiliates) shall not offer any gift, favor, or other personal benefit to any County officer or employee during the procurement process for this agreement, including during the solicitation period and contract negotiations.

Violation of the foregoing prohibitions may result in a proposer being found non-responsible and barred from participating in this or future procurements.

6.3. Contract Award

A. Award Procedure

Contract negotiations are neither an offer nor guarantee that a contract will be executed. A contract award, if any is made, will be to the responsive, responsible proposer offering the overall best value to the County for the services and goods described in this solicitation, or as applicable, for a specific portion of the services and goods described. Any agreement reached will be memorialized in a formal agreement using the attached template, executed by the appropriate authority.

B. Notice of Intent to Award

If a decision is made to take steps to enter into an agreement with one or more proposers, the

County will post a Notice of Intent to Award or otherwise notify proposers the remaining proposers of their non-selection. Notice may instead be provided by including approval of the agreement as an item on an agenda for a meeting of the Board of Supervisors.

C. Commencement of Performance

After all parties have signed the agreement, the County will notify the contractor and performance may proceed. Prior to execution of the agreement by the County, no County employee may authorize work under the agreement. Any work performed prior to the full execution of the Agreement may not be compensated.

D. Levine Act DisclosureThe Levine Act (California Government Code Section 84308) imposes certain requirements on parties contracting with the County of San Mateo related to campaign contributions to County “officers,” including elected County officers and candidates seeking elective office, who may participate in making a decision on certain County contracts. Elected

County officers in San Mateo County include: the San Mateo County Board of Supervisors, Assessor-County Clerk-Recorder, County Controller, Coroner, District Attorney, Sheriff, and Tax

Collector-Treasurer.Generally, under current County policy, approval by the Board of

Supervisors is required for any agreement for services above $200,000, and agreements for

Page 11 of 11 Release date of October 23, 2026 services below that threshold may be approved by Department heads.If your proposal is selected, you will be required to certify compliance with the Levine Act.As part of this process, you will need to certify and warrant that you have fully complied, and will remain in full compliance, with all applicable requirements of the Levine Act in connection with the

Agreement, including making any required disclosures of campaign contributions to County

Officers, which includes but may not be limited to elected County Officers. Elected County

Officers include members of the San Mateo County Board of Supervisors, as well as the

Assessor-County Clerk-Recorder, Controller, Coroner, District Attorney, Sheriff, and Tax

Collector-Treasurer. Any campaign contribution required to be disclosed under the Levine Act in connection with this Agreement shall be disclosed on the County of San Mateo Levine Act

Disclosure Form, a copy of which is available from the County upon request.Parties are solely responsible for accurate certification and disclosure. The Levine Act is complex, and this brief description is not legal advice. For example, certain contributions must be aggregated when determining whether contributions have exceeded the $500 threshold. If your proposal is selected, you are urged to review the Levine Act and consider consulting an attorney.

6.4. Term

County Executive's Officeis issuing Request for Proposal (RFP) No. 2027-RFP - Informal-00183 for

Construction Auditing Services – San Mateo Event Center Improvement Projects.

The agreement shall have a term of one (1) year. In addition, the County shall have three (3) optional extensions, subject to County approval and the final agreement., which the County may exercise in its sole, absolute discretion. To exercise this option, the County shall provide written notice to the Contractor at least thirty days before the end of the agreement’s term.

The County’s standard contract template has been included with this solicitation. The awarded contractor will be expected to sign an agreement prepared by the County using this template. Please ensure that your firm has completed legal review of these contract terms. If your firm wishes to request exceptions to these standard terms, submit a Contract Exceptions Request by the Deadline for Contract Exceptions listed in the Solicitation Schedule. The County will consider Contract Exceptions Requests but reserves the right to reject requested modifications to its standard terms.

1. Introduction and Schedule
1.1. Summary
1.2. Contact Information
1.3. Timeline
2. Scope of Work
2.1. SCOPE OF SERVICES
3. Submission Requirements
3.1. Submission Deadline
3.2. Pre-submission Registration
3.3. Submission via eProcurement Portal
3.4. County Rights an General Requirements
4. Minimum Qualifications and Technical Proposal
4.1. Minimum Qualifications
4.1.1. Has Proposer has been providing similar services for a minimum of four (4) years within the last seven (7) years?*
4.1.2. Please confirm your firm is registered with System for Award Management (SAM)*
4.1.3. What is the registered Business Name and Unique Entity ID (UEI) No.?*
4.2. Technical Proposal
4.2.1. Introduction and Executive Summary *
4.2.2. Statement of Minimum Qualifications *
4.2.3. Project Approach*
4.2.4. Scope of Work tasks/milestones*
4.2.5. Proposed schedule *
4.2.6. Performance Measures*
4.2.7. Firm Qualifications *
4.2.8. Team Qualifications*
4.2.9. Sample construction audit report, with confidential information removed.*
4.2.10. Proof of required insurance and other documentation specified by the County.*
4.2.11. Disclosure of actual or potential conflicts of interest.*
4.2.12. References*
4.2.13. Fee Proposal*
5. Evaluation and Selection Criteria
6. Instructions to Proposers
6.1. Instructions
6.2. Communications
6.3. Contract Award
6.4. Term

File details come from the government source that posted it. Updated .