This document is an Addendum 2 to a contract opportunity for the DNR Roof Replacement project at the Lake Ontario, Lake Superior, and Lake Michigan Lodges in Michigan. The project includes roof replacement work, and the addendum clarifies that unit pricing has been moved from the Bid Schedule to a separate Schedule of Unit Pricing. The bid due date is 2.14.24, and the project number is 522736. The DTMB file number is 751/22434.TYC.
The Bid Schedule includes a Base Bid and a Schedule of Alternates. The Schedule of Unit Prices or Contingent Change Order Prices includes items such as roof sheathing replacement. The Owner reserves the right to negotiate the unit prices prior to their incorporation into the final contract.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Advertisement.pdf | ||
| Constr bid addendum 1.pdf | ||
| RAM drawings.pdf | ||
| RAM specifications.pdf | ||
| Constr Bid addendum 3.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM 2
757 S. WISCONSIN AVENUE ▪ GAYLORD MI 49735
p h o n e 989.705.8400 ▪ f a x 989.705.8403
-1-
Addendum Number: 2
Date: 1.31.24
Project Name: DNR Roof Replacement – Lake Ontario, Lake Superior & Lake Michigan Lodges
SG Project Number: 522736 DTMB File No.: 751/22434.TYC
Bid Date: 2.14.24
This Addendum is being issued for the purpose of clarifying and/or modifying the original Bidding Documents and shall take precedence over them. Each Bidder’s proposal shall include the Work described herein. All requirements contained in the Contract Documents shall apply to this Addendum. All incidental work necessary to complete the Work shall be included in the Contractor’s quotation even though not particularly mentioned. Parts of the Specifications and Drawings referred to herein supersede previously issued data and form a part of this Addendum.
CLARIFICATIONS:
1. Unit pricing moved from the Bid Schedule and to be indicated in the Schedule of Unit Pricing.
ATTACHMENTS:
The following documents are a part of this Addendum:
1. Specification Manual pages 3 & 4.
END OF ADDENDUM
Bidding and Contract Document (R 03/22) Project Name: Lake Ontario Lodge Roof Replacement File No. 751/22434.TYC
Revision Date: 3/2022
Addenda: Bidder acknowledges receipt of: No. ___ dated: ________, No. ___ dated: ________ No. ___ dated: ________
BID SCHEDULE
Base Bid Schedule - The Bidder will complete the Work and accept as full payment, for the Work items listed, the following Unit Prices and/or Item Bid Prices, as applicable:
Base Bid Item No.
Bid Quantity
Description
Unit Price
Item Bid
TOTAL (This amount should equal the Base Bid amount on the Bid Summary Form) $
Base Bid (Sum of Item Bid Prices for all Base Bid Items):
__________________________________________________________________ Dollars $__________________________ (use words) (in figures)
Bidding and Contract Document (R 03/22) Project Name: Lake Ontario Lodge Roof Replacement File No. 751/22434.TYC
Revision Date: 3/2022
Schedule of Alternates - The Bidder will complete (or deduct from the Contract) the parts of the Work designated by the Alternates that follow and accept in full payment (or allow in full credit) for those parts of the Work the following Item Bid Prices:
Alternate Item No.
Bid
Item Bid
The Bidder further acknowledges and agrees that the separate prices bid on this “Schedule of Alternates,” where they are applicable and deemed acceptable by the Owner, will be used if incorporated into the Contract when the Owner issues the Notice of Award.
Schedule of Unit Prices or Contingent Change Order Prices - The Bidder shall use this “Schedule” to quote unit prices identified in the bid documents or propose other contingent Change Order prices. The proposed Unit Prices or contingent Change Order prices set forth in this schedule, at the sole discretion of the Owner, may, or may not be incorporated into the Contract Documents. The Owner reserves the right to negotiate Unit Prices or contingent Change Order prices set forth herein prior to their possible incorporation into the Contract Documents.
Item No. Bid
Item Bid Price
Roof Sheathing 1 Sheet Replacement plywood or osb sheathing per Section 06 6100