CON 436-20-122 Building 141 Flat Roof Renovation SPEC.pdf

PDF 3 MB Posted

Attached to
Z2AZ--(CON) 436 Ft Harrison Building 141 Flat Roof Renovations *(VA-21-00026615)
Solicitation number
36C25921Q0382
Issued by

About this file

This document provides details for a federal contract solicitation for building roof renovation services. The solicitation is for preparation of areas and abatement work to isolate patient treatment areas at the Salt Lake City VA Medical Center located at 500 Foothill Dr., Salt Lake City, UT. The work includes preparation for patient lift installation and is estimated between $100,000 and $250,000. Responses are due on or about November 6, 2020. The solicitation is a 100% set-aside for verified Service-Disabled Veteran-Owned Small Businesses and awardees must meet small business size standards under NAICS code 236220 with a threshold of $39.5 million. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 19 is the contracting agency.

View the file

Other files

File Type Posted
S02 Past Performance Questionnaire.docx DOCX document
36C25921Q0382_1.docx DOCX document
CON 436-20-122 DWG BUILDING 141 FLAT ROOF RENOVATIONS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Fort Harrison VAMC, Fort Harrison, MT 59636 12-08-20

VA: 436-20-122 Design

Submission Building 141 Flat Roof Renovations 11-01-19

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 10 Table of Contents 07-15

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 12-18

01 21 16.15 Project Schedules (Small Projects – Design/Bid/Build) 03-20

01 33 23 Shop Drawings, Product Data, And Samples 05-17

01 45 00 Quality Control 03-19

01 74 19 Construction Waste Management 09-13

01 91 00 General Commissioning Requirements 10-15

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 01 50.19 Preparation for Re-Roofing 02-16

07 08 00 Facility Exterior Closure Commissioning 11-16

07 22 00 Roof and Deck Insulation 02-16

07 53 23 Ethylene-Propylene-Diene-Monomer Roofing 02-16

07 60 00 Flashing and Sheet Metal 07-14

07 71 00 Roof Specialties 10-15

07 72 00 Roof Accessories

07 84 00 Firestopping 02-16

07 92 00 Joint Sealants 10-17

07 95 13 Expansion Joint Cover Assemblies 02-16

01 01 00-1

Building 141 Flat Roof Renovations 02-01-16

SECTION 01 01 00

GENERAL REQUIREMENTS

Table of Contents

1.1 GENERAL INTENTION

1.2 STATEMENT OF BID ITEM(S)

1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

1.4 FIRE SAFETY PRECAUTION ..................................................5-10

1.5 OPERATIONS AND STORAGE AREAS ...........................................11-20

1.6 ALTERATIONS ............................................................20-26

1.7 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS............................................................. 26-27

1.8 RESTORATION ............................................................27-28

1.9 PHYSICAL DATA

1.10 PROFESSIONAL SURVEYING SERVICES

1.11 LAYOUT OF WORK

1.12 USE OF ROADWAYS

1.13 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT ) ................31-32

1.14 TEMPORARY USE OF ELEVATORS

1.15 TEMPORARY TOILETS

1.16 AVAILABILITY AND USE OF UTILITY SERVICES ..............................34-35

1.17 TESTS AND MATERIAL TESTING

1.18 INSTRUCTIONS ..........................................................37-38

1.19 GOVERNMENT-FURNISHED PROPERTY ......................................... 39-40

1.20 RELOCATED EQUIPMENT ITEMS

1.21 INFECTION PREVENTION MEASURES .........................................41-45

1.22 WORKING HOURS

1.23 PAYMENT TO CONTRACTOR

1.24 SCHEDULE OF WORK PROGRESS (also see Section 01312)

1.25 BUY AMERICAN ACT (See GENERAL CONDITIONS section 0010)

1.26 SCHEDULE OF WORK PROGRESS (also see Section 01312)

1.27 SUPERINTENDENCE BY THE Contractor

1.28 PROJECT COORDINATION

1.29 PARKING

01 01 00-2

1.30 TIME EXTENSIONS

1.31 FIREARMS/BOW-ARROW

1.32 INSPECTION – ACCEPTANCE – WARRANTY (also see PHASING EQUIREMENTS)

1.33 WAGE DETERMINATION - MINIMUM HOURLY RATES OF WAGES

1.34 CONSTRUCTION SIGN

1.35 HISTORIC PRESERVATION

01 01 00-3

1.1 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for:

Building 141 Flat Roof Renovations, PROJECT NO. 436-20-122 as required by drawings and specifications.

B. Visits to the site by Bidders may be made only by appointment with the

Medical Center Resident Engineer/Project Engineer. Where used in this specification and/or on the contract drawings, Resident Engineer/Project

Engineer are one in the same.

C. Before placement and installation of work subject to tests by testing laboratory, the Contractor shall notify the Resident Engineer in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection.

Such prior notice shall be not less than three work days unless otherwise designated by the Resident Engineer.

D. ASBESTOS CONTAINING MATERIAL (ACM) - All ACM has been removed from affected project areas to the best of the VA's knowledge. However, if, while

01 01 00-4 construction is underway, any suspicious material is found/uncovered that is thought that could be ACM, the Contractor's superintendent will bring the information to the attention of the Resident Engineer immediately. The

Resident Engineer will investigate, determine what direction to take and advise the Contractor accordingly.

1.2 STATEMENT OF BID ITEM(S)

A. BASE BID: Furnish all labor, equipment and materials to perform all work shown on contract drawings and as specified in specifications for Project

436-20-122, Building 141 Flat Roof Renovations.

1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Additional sets of drawings may be made by the Contractor, at Contractor's expense, from reproducible sepia prints furnished by Issuing Office. Such sepia prints shall be returned to the Issuing Office immediately after printing is completed.

1.4 FIRE SAFETY PRECAUTIONS

A. The contractor will be required to employ an OSHA 30 hour certified person on site for the project duration during normal

01 01 00-5 work hours.

B. Exits for VA occupied areas of a building including rooms, suites, corridors and floors shall not be blocked by the construction or by construction materials. Exits may be blocked temporarily if it is unavoidable and adequate alternate measures are provided such as signage, instructions to occupants and a heat detection system.

C. Existing fire protection systems including fire alarm systems, smoke detection systems, and sprinkler systems shall not be impaired during construction except for devices in the immediate construction areas vacated by VA.

D. At the end of each workday, combustible packaging and crating materials for building products and equipment to be installed shall be removed from any

VA occupied building.

E. The necessary number and appropriate type of portable fire extinguishers per 29 CFR1926, National Fire Protection Association (NFPA) Standard Nos.

10 and NFPA 241 current standard shall be provided for all construction areas. These will be provided by the Contractor.

F. As required by the Joint Commission on Accreditation of Healthcare

Organizations, smoking shall be prohibited in or adjacent to all construction areas in existing buildings.

01 01 00-6

G. Weekly fire hazard inspections shall be conducted by the Contractor once construction starts and until the building is turned over to the government. A report shall be provided to the Resident Engineer listing all hazards and corrective actions taken. Fire/Safety inspections will be conducted by Resident Engineer as per General Conditions. Fire/Safety inspections will also be performed by station Fire/Safety Specialist which will be coordinated with Contractor by Resident Engineer.

H. A fire safety plan shall be established and maintained in accordance with

29 CFR 1926, prior to any construction, detailing all fire safety measures which will be addressed during the construction. The plan shall be provided to the Resident Engineer for review and comment.

I. Temporary structures, including trailers that are used for storage or offices, shall be a minimum of 9 meters (30 feet) from any VA occupied building.

J. All temporary heating equipment shall be installed in accordance with requirements of applicable 29 CFR 1926, NFPA 241 and NFPA 70.

K. All flammable liquids shall be handled, stored and used in accordance with

29 CFR 1926, NFPA 241 and NFPA 30.

01 01 00-7

L. All temporary electrical wiring and equipment used for construction shall be installed and used in accordance with pertinent provisions of 29 CFR

1926, NFPA 241 and NFPA 70.

M. Maintain construction site to permit access of fire department vehicles as necessary. Clear building construction areas of unnecessary obstructions so that all portions are accessible for fire department apparatus and permit emergency egress of construction and other personnel.

N. All necessary precautions shall be taken by the Contractor to prevent accidental operation of any existing smoke detectors by minimizing the amount of dust generated in the vicinity of any smoke detectors.

O. All construction activities not already covered above shall be in accordance with the latest edition of NFPA No. 241, Standard for

Safeguarding Construction, Alteration, and Demolition Operations, in effect at time of contract award.

P. The Contractor shall be responsible for assigning an authorized supervisory representative to issue hot work permits. Before any cutting or welding is conducted, the Contractor or sub-Contractors shall obtain permission from the Contractor's authorized representative by the issuance of this permit.

All hot work shall be conducted safely in accordance with National Fire

Protection Association Standard No. 51B, Fire Prevention in the Use of

Cutting and Welding Process, 1994 edition. Coordinate with Project

Engineer. Permits are required from Fire Department at least 24 hours in advance or as approved by Project Engineer.

01 01 00-8

The attached sample permit format or a similar one may be used.

PERMIT

FOR CUTTING AND WELDING

WITH PORTABLE GAS OR ARC EQUIPMENT

VA Project No:

Name of Contractor's Firm:

Date:

Building/Location:

Work To Be Done:

Any Special Precautions:

Fire Watch Required: Yes No

The location where the work is to be performed has been examined, necessary precautions have been taken, and permission is granted for this work.

Signed

(Contractor Individual Responsible for

Authorizing Hot Work)

Permit Expires: (Date)

Time Hot Work Started: Time Hot Work Completed:

FINAL CHECK-UP

Work area and all adjacent areas to which sparks and heat might have spread (including floors above and below and on opposite sides of walls) were inspected 30 minutes after the work was completed and were found fire safe.

Signed

(Contractor's Fire Watch)

(Form - Page 1 of 2)

01 01 00-9

ATTENTION

Before approving any cutting and welding permit, the Contractor's authorized representative or their appointee shall inspect the work area and confirm that precautions have been taken to prevent fire in accordance with

NFPA Standard No. 51B.

PRECAUTIONS

o Sprinklers are in service where installed o Cutting and welding equipment in good repair o Within 10.7 meters (35 feet); floors swept clean of combustible, no combustible material or flammable liquids, all wall and floor openings covered, and covers suspended beneath work to collect sparks o When working on enclosed equipment and in confined space, equipment and area is free of flammable vapors o Fire watch provided during and 30 minutes after operation (60 minutes for torch applied roofing operations) o Portable fire extinguisher with adequate rating available in the immediate vicinity o Standpipe system in service where installed o Protection of any sprinkler heads when hot work is in close proximity o Smoking prohibited in immediate vicinity o Non-combustible shields provided when hot work is done near combustible walls, partitions, floors, roofs o Prohibition of hot work on pipes contacting combustible walls o Personnel trained in use of equipment including portable fire extinguishers and sounding a fire alarm o Final check-up conducted after 30 minutes

(Form - Page 2 of 2)

01 01 00-10

1.5 OPERATIONS AND STORAGE AREAS (PHASING PLANS)

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Resident Engineer. The Contractor shall hold and save the

Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. The Contractor shall, under regulations prescribed by the Resident

Engineer, use only established roadways. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the

Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

C. Working space and space available for storing materials shall be as determined by the Resident Engineer and/or as shown on contract drawings.

01 01 00-11

D. Workmen are subject to rules of Medical Center applicable to their conduct.

E. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and

Contractor's personnel, except as permitted by Resident Engineer where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

F. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by

01 01 00-12

Resident Engineer. All such actions shall be coordinated with the

Utility Company involved.

G. Phasing: To insure such executions, Contractor shall furnish the

Resident Engineer with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the Resident Engineer two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.

H. When a portion of the building is turned over to Contractor, Contractor shall accept entire responsibility therefore.

1. Contractor shall maintain a minimum temperature of 4.5 degrees C

(40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment.

I. Utilities Services: Maintain existing utility services for Medical

Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc.

of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by Resident Engineer.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of Resident

01 01 00-13

Engineer.

2. Contractor shall submit a request to interrupt any such services to Resident Engineer, in writing, 72 hours in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center.

Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the Resident Engineer.

5. In case of a contract construction emergency, service will be interrupted on approval of Resident Engineer. Such approval will be confirmed in writing as soon as practical.

J. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are not to be abandoned are not required to be entirely removed, shall be sealed, capped or plugged. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

K. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to

01 01 00-14 occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

L. Coordinate the work for this contract with other construction operations as directed by Resident Engineer.

1. Contractor will allow only persons having business with this project on the project site. There will be no children allowed.

No one from VA except Resident Engineer is allowed on project site unless otherwise specified by Resident Engineer.

1.6 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the Resident Engineer of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both to the Resident

Engineer. This report shall list by rooms and spaces:

1. Existing condition and types of flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations

01 01 00-15 occur and which have been agreed upon by Contractor and Resident

Engineer.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of

Resident Engineer, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by

Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled

"DIFFERING SITE CONDITIONS" and "CHANGES" of Section 01001, GENERAL

CONDITIONS.

C. Re-Survey: On final inspection date, the Contractor and Resident

Engineer together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report.

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures;

and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workmen in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

01 01 00-16

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

4. Dampen debris to keep down dust and provide temporary construction partitions in existing structures where directed by

Resident Engineer.

E. Disposal and Retention: Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored.

Items which remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse.

Store such items where directed by Resident Engineer.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings

01 01 00-17 and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.7 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES,

AND IMPROVEMENTS

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Resident Engineer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Resident Engineer may have the necessary work performed and charge the cost to the Contractor.

C. For additional requirements on protecting vegetation, soils and the

01 01 00-18 environment. Refer to Articles, "Alterations", "Restoration", and

"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

D. The Contractor will comply with the control of pollutant discharges by employing the best management practices. The affected activities include but are not limited to the following:

Designating areas for equipment maintenance and repair;

Providing waste receptacles at convenient locations and provide regular collection of wastes;

Locating equipment wash down areas on site, and provide appropriate control of wash waste waters;

Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials;

and

Providing adequately maintained sanitary facilities.

1.8 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the Resident Engineer. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the Resident Engineer before it is disturbed.

Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

01 01 00-19

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems

(including telephone) which are indicated on drawings and which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" and "DIFFERING SITE CONDITIONS" of Section

01001, GENERAL CONDITIONS.

1.9 PHYSICAL DATA

A. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by exploration.

1.10 LAYOUT OF WORK

A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout.

The Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and

01 01 00-20 labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated.

1.11 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical

Center property and, when authorized by the Resident Engineer, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed by the Contractor at

Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

1.12 TEMPORARY USE OF ELEVATORS

Use of existing elevators for handling building materials and

Contractor's personnel will be permitted subject to the following provisions:

A. Contractor makes arrangements with the Resident Engineer for use of elevators. Contractor may not obtain elevators for exclusive use.

B. Personnel for operating elevators will not be provided by the

Department of Veterans Affairs.

C. Contractor covers and provides maximum protection of following elevator components:

1. Entrance jambs, head soffits and threshold plates.

2. Entrance columns, canopy, return panels and inside surface of car enclosure walls.

3. Finish flooring.

D. All parts of controllers, start relay panel, selector, hoisting and governor ropes, etc., worn or damaged during temporary use shall be

01 01 00-21 removed and replaced with new parts, if recommended by elevator inspector after temporary use and before acceptance by the

Government.

E. Place elevator in condition approved by Resident Engineer.

1.13 TEMPORARY TOILETS

A. Provide where directed, (for use of all Contractor's workmen) ample temporary suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.

1.14 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The Contractor shall carefully conserve any utilities furnished without charge.

B. The Contractor, at Contractor's expense and in a workmanlike manner satisfactory to the Resident Engineer, shall install and maintain all necessary temporary connections and distribution lines. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, and associated paraphernalia.

C. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials.

1. Obtain heat by connecting to Medical Center heating distribution

01 01 00-22 system.

a. Steam is available at no cost to Contractor.

D. Electricity (for Construction and Testing): Furnish all temporary electric services.

1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.

E. Water (for Construction and Testing): Furnish temporary water service.

1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection. Water is available at no cost to the

Contractor.

2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at Resident Engineer's discretion) of use of water from Medical Center's system.

F. Steam: Furnish steam system for testing required in various sections of specifications.

1. Obtain steam for testing by connecting to the Medical Center steam distribution system. Steam is available at no cost to the

Contractor.

2. Maintain connections, pipe, fittings and fixtures and conserve steam-use so none is wasted. Failure to stop leakage or other

01 01 00-23 waste will be cause for revocation (at Resident Engineer's discretion), of use of steam from the Medical Center's system.

1.15 TESTS

A. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Resident

Engineer. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.

B. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.

C. Material Testing:

1. Conduct field material tests as required in the specification sections in the presence of an authorized representative or the

Resident Engineer. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.

2. The contractor will as part of the contract, employ an independent certified third party testing firm approved by the government,that has no interest in the contractor’s company to perform all required project material testing and furnish the results directly to the government. The cost of all material testing will be the responsibility of the contractor and be included in the bid price.

1.16 INSTRUCTIONS

A. Contractor shall furnish Maintenance and Operating manuals and verbal instructions when required by the various sections of the specifications and as hereinafter specified.

B. Manuals: Maintenance and operating manuals (two copies each) for

01 01 00-24 each separate piece of equipment shall be delivered to the Resident

Engineer at the project completion. Manuals shall be complete, detailed guides for the maintenance and operation of equipment.

They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.

C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed instructions to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections.

Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, 01 01 00-25 progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed. This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the Resident Engineer and shall be considered concluded only when the Resident Engineer is satisfied in regard to complete and thorough coverage. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the Resident Engineer, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.

1.17 GOVERNMENT-FURNISHED PROPERTY

A. The Government shall deliver to the Contractor, the

Government-furnished property shown on the drawings.

B. Equipment furnished by Government to be installed by Contractor will be furnished to Contractor at the Medical Center.

C. Contractor shall be prepared to receive this equipment from

Government and store or place such equipment not less than 90 days before Completion Date of project.

D. Storage space for equipment will be provided by the Government and the Contractor shall be prepared to unload and store such equipment therein upon its receipt at the Medical Center.

E. Notify Resident Engineer in writing, 60 days in advance, of date on which the Contractor will be prepared to receive equipment furnished by Government. Arrangements will then be made by the

Government for delivery of equipment.

01 01 00-26

1. Immediately upon delivery of equipment, Contractor shall arrange for a joint inspection thereof with a representative of the

Government. At such time the Contractor shall acknowledge receipt of equipment described, make notations, and immediately furnish the Government representative with a written statement as to its condition or shortages.

2. Contractor thereafter is responsible for such equipment until such time as acceptance of contract work is made by the

Government.

F. Equipment furnished by the Government will be delivered in a partially assembled (knock down) condition in accordance with existing standard commercial practices, complete with all fittings, fastenings, and appliances necessary for connections to respective services installed under contract. All fittings and appliances

(i.e., couplings, ells, tees, nipples, piping, conduits, cables, and the like) necessary to make the connection between the

Government furnished equipment item and the utility stub-up shall be furnished and installed by the Contractor at no additional cost to the Government.

G. Completely assemble and install the Government furnished equipment in place ready for proper operation in accordance with specifications and drawings.

1.18 RELOCATED EQUIPMENT ITEMS

A. Contractor shall disconnect, dismantle as necessary, remove and reinstall in new location, all existing equipment indicated by symbol "R" or otherwise shown to be relocated by the Contractor.

B. Perform relocation of such equipment or items at such times and in

01 01 00-27 such a manner as directed by the Resident Engineer.

C. Suitably cap existing service lines, such as steam, condensate return, water, drain, gas, air, vacuum and/or electrical, whenever such lines are disconnected from equipment to be relocated. Remove abandoned lines in finished areas and cap as specified hereinbefore under paragraph "Abandoned Lines".

D. Provide all mechanical and electrical service connections, fittings, fastenings and any other materials necessary for assembly and installation of relocated equipment; and leave such equipment in proper operating condition.

E. All service lines such as noted above for relocated equipment shall be in place at point of relocation ready for use before any existing equipment is disconnected. Make relocated existing equipment ready for operation or use immediately after reinstallation.

1.19 INFECTION PREVENTION MEASURES

A. Implement the requirements of VAMC’s Infection Control Risk Assessment

(ICRA) team. ICRA Group may monitor dust in the vicinity of the construction work and require the Contractor to take corrective action immediately if the safe levels are exceeded.

B. Establish and maintain a dust control program as part of the contractor’s infection preventive measures in accordance with the guidelines provided by

ICRA Group. Prior to start of work, prepare a plan detailing project-specific dust protection measures, including periodic status reports, and submit to Project Engineer and Facility ICRA team for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP

DRAWINGS, PRODUCT DATA AND SAMPLES.

01 01 00-28

1. All personnel involved in the construction or renovation activity shall be educated and trained in infection prevention measures established by the medical center.

C. Medical center Infection Control personnel shall monitor for airborne disease (e.g. aspergillosis) as appropriate during construction. A baseline of conditions may be established by the medical center prior to the start of work and periodically during the construction stage to determine impact of construction activities on indoor air quality. In addition:

1. The RE and VAMC Infection Control personnel shall review pressure differential monitoring documentation to verify that pressure differentials in the construction zone and in the patient-care rooms are appropriate for their settings. The requirement for negative air pressure in the construction zone shall depend on the location and type of activity. Upon notification, the contractor shall implement corrective measures to restore proper pressure differentials as needed.

2. In case of any problem, the medical center, along with assistance from the contractor, shall conduct an environmental assessment to find and eliminate the source.

D. In general, following preventive measures shall be adopted during construction to keep down dust and prevent mold.

1. Dampen debris to keep down dust and provide temporary construction partitions in existing structures where directed by Resident Engineer.

Blank off ducts and diffusers to prevent circulation of dust into occupied areas during construction. The contractor will construct barrier wall to control area flow from construction areas to the occupied hospital and maintain negative airflow from clean area to work area through the use of negative pressure.

01 01 00-29

2. Do not perform dust producing tasks within occupied areas without the approval of the Resident Engineer. For construction in any areas that will remain jointly occupied by the medical Center and Contractor’s workers, the Contractor shall:

a. Provide dust proof one hour fire-rated temporary drywall construction barriers to completely separate construction from the operational areas of the hospital in order to contain dirt debris and dust.

Barriers shall be sealed and made presentable on hospital occupied side. Install a self-closing rated door in a metal frame, commensurate with the partition, to allow worker access. Maintain negative air at all times. A fire retardant polystyrene, 6-mil thick or greater plastic barrier meeting local fire codes may be used where dust control is the only hazard, and an agreement is reached with the

Resident Engineer and Medical Center.

b. HEPA filtration is required where the exhaust dust may reenter the breathing zone. Contractor shall verify that construction exhaust to exterior is not reintroduced to the medical center through intake vents, or building openings. Install HEPA (High Efficiency

Particulate Accumulator) filter vacuum system rated at 95% capture of

0.3 microns including pollen, mold spores and dust particles. Insure continuous negative air pressures occurring within the work area.

HEPA filters should have ASHRAE 85 or other prefilter to extend the useful life of the HEPA. Provide both primary and secondary filtrations units. Exhaust hoses shall be heavy duty, flexible steel reinforced and exhausted so that dust is not reintroduced to the medical center.

c. Adhesive Walk-off/Carpet Walk-off Mats, minimum 600mm x 900mm (24” x

01 01 00-30

36”), shall be used at all interior transitions from the construction area to occupied medical center area. These mats shall be changed as often as required to maintain clean work areas directly outside construction area at all times.

d. Vacuum and wet mop all transition areas from construction to the occupied medical center at the end of each workday. Vacuum shall utilize HEPA filtration. Maintain surrounding area frequently. Remove debris as they are created. Transport these outside the construction area in containers with tightly fitting lids.

e. The contractor shall not haul debris through patient-care areas without prior approval of the Resident Engineer and the Medical

Center. When, approved, debris shall be hauled in enclosed dust proof containers or wrapped in plastic and sealed with duct tape. No sharp objects should be allowed to cut through the plastic. Wipe down the exterior of the containers with a damp rag to remove dust. All equipment, tools, material, etc. transported through occupied areas shall be made free from dust and moisture by vacuuming and wipe down.

f. Using a HEPA vacuum, clean inside the barrier and vacuum ceiling tile prior to replacement. Any ceiling access panels opened for investigation beyond sealed areas shall be sealed immediately when unattended.

g. There shall be no standing water during construction. This includes water in equipment drip pans and open containers within the construction areas. All accidental spills must be cleaned up and dried within 12 hours. Remove and dispose of porous materials that remain damp for more than 72 hours.

h. At completion, remove construction barriers and ceiling protection

01 01 00-31 carefully, outside of normal work hours. Vacuum and clean all surfaces free of dust after the removal.

E. Final Cleanup:

1. Upon completion of project, or as work progresses, remove all construction debris from above ceiling, vertical shafts and utility chases that have been part of the construction.

2. Perform HEPA vacuum cleaning of all surfaces in the construction area.

This includes walls, ceilings, cabinets, furniture (built-in or free standing), partitions, flooring, etc.

3. All new air ducts shall be cleaned prior to final inspection.

1.20 WORKING HOURS

A. Normal working hours will be 8:00 a.m. - 4:30 p.m. weekdays, Monday

- Friday.

B. There will be no work performed on any Federal Holiday.

C. Exceptions to the above must be requested in writing to Resident

Engineer at least two weeks in advance of work date.

D. Approximately 30% of the contractors work may have to be done after normal business hours (8:00AM to 4:30PM), so the normal operation of the hospital remains unaffected.

E. Other exceptions as per phasing requirements.

1.21 PAYMENT TO CONTRACTOR

A. Within 30 calendar days of receipt of notice to proceed, the

Contractor shall submit to the Resident Engineer a Contractor's cost breakdown. Such schedule shall be signed, and four (4) copies shall be submitted. The approved schedule will be one of the bases of determining progress payments to the Contractor for work completed. All work items are to be sufficiently broken down.

01 01 00-32

1. Costs as shown on this schedule must be true costs. The Resident

Engineer may require the Contractor to submit original estimate sheets or other information to substantiate detail make-up of the cost schedule.

2. The sum of subbranches, as applied to each branch, shall equal to total cost of such branch. The total costs of all branches shall equal the contract price.

B. The Veterans Administration will consider for monthly progress payments material and/or equipment procured by the Contractor and stored on the construction site as space is available or at a local approved location off the site under such terms and conditions including, but not limited to the following:

1. The materials or equipment is in accordance with the contract requirements and approved samples and shop drawings.

2. The Contractor furnishes satisfactory evidence of possession of title to such material and/or equipment and that the material and/or equipment will be utilized on work covered by the contract. A letter requesting payment and specifying full title of materials must be made to Resident Engineer. Two (2) copies of invoices from original vendor must be attached specifying item and quantities.

3. Only those materials and/or equipment approved by the Resident

Engineer for storage will be included.

4. Such materials and/or equipment shall be protected against weather, theft and other hazards and shall not be subject to deterioration.

5. Off site storage must be approved in writing by surety.

01 01 00-33

1.22 SCHEDULE OF WORK PROGRESS (also see Section 01312)

A. The Contractor shall submit with the schedule of costs, as required by "Payment to Contractor" clause, a progress curve indicating anticipated work progression against lapsed contract time, for approval of the Resident Engineer. Submission shall be in quadruplicate on VA Form 08-6159 Construction Progress Chart furnished by the Veterans Administration and shall be signed by the Contractor. The curve shall start on the date the Contractor receives the "Notice to Proceed" and terminate on the original contract completion date. Both dates shall be indicated on the

Construction Progress Chart. This chart will be supplemented by detailed CPM schedule specified in Section 01312 and shall coincide accordingly.

B. The scheduled percent completion will be compared to the actual percent completion to determine if the contract work is on schedule. Monthly progress reports will be prepared by the VA on a

Contract Progress Report Form (VA Form 08-6001 or 08-6001a, as appropriate). This report will indicate both scheduled percent completion and actual percent completion. The scheduled percent completion will be taken from the approved progress curve. The actual percent completion will be based on the value of work in place divided by current contract amount.

1.23 BUY AMERICAN ACT (See GENERAL CONDITIONS section, 01010)

1.24 SUBCONTRACTOR

A. Contractor is completely responsible for the acts or omissions of all sub-Contractors.

B. Contractor is required to submit a list of all sub-Contractors that

01 01 00-34 will actually perform work on this station.

C. For other sub-Contractor requirements, see General Conditions, Section 1001.

1.25 SUPERINTENDENCE BY THE Contractor

A. At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the work a competent superintendent who is satisfactory to the Resident Engineer and has authority to act for the Contractor.

B. The Contractor shall submit the name, experience and authority to

Resident Engineer.

1.26 PROJECT COORDINATION

A. The Contractor's Superintendent is to coordinate all project phasing with Resident Engineer only.

B. Contractor is expected to have all parts, equipment, etc., in order to perform the required work. The VA will not loan, sell or exchange any parts or equipment to Contractor or SubContractor.

1.27 PARKING

A. Parking for Contractor is authorized in only regular parking areas.

Parking immediately adjacent to buildings is not allowed.

Contractor may park vehicles adjacent to building entrances only to load/unload equipment or tools as designated by Resident Engineer.

B. Contractor will control any excessive vehicle parking within project boundaries.

1.28 TIME EXTENSIONS

A. Sufficient time has been allowed for this project and it is not anticipated to have any time extensions.

01 01 00-35

B. It is the Contractor's responsibility to perform submittals, etc.

and to schedule all work items to meet the time requirements of this contract.

1.29 FIREARMS/BOW-ARROW

A. Because of this station being of Federal Domain, firearms and bow-arrow are not allowed.

B. Those found in possession of firearms on station are subject to possible fines and confiscation of firearms/bow-arrows.

1.30 INSPECTION – ACCEPTANCE – WARRANTY (also see PHASING REQUIREMENTS)

A. Inspection of materials and articles furnished under this contract will be made at the site by the Resident Engineer or their agents.

B. Final inspection will not be made until the…