STATEMENT OF WORK
FY21 MID SEASON REPAIR
AVAILABILITY NOAA SHIP
FERDNINAND R. HASSLER
S250
VESSEL PARTICULARS
LENGTH (LOA): 37.7 m (123.7 ft)
BREADTH AT MAIN DECK: 16.4 m (53.8 ft) BREADTH AT PONTOON, MAX: 18.5 m (60.7 ft)
DEPTH: 7.0 m (23.0 ft) DRAFT, MAX: 3.95 m (12.96 ft)
DISPLACEMENT, MAX: 744.4 tonnes (732.6 long tons)
GROSS TONNAGE (ITC): 809
HULL: Welded Steel
NOAA Ship FERDINAND R. HASSLER (S-250)
Work Item Index Item Number Description SWBS REV
General Technical Requirements 10002 Approach, Mooring, and Berthing 002 ‐
10005 General Services for Ship 005 ‐
600 Series
106312 Topside General Corrosion Control 631‐2 ‐
NOAA Ship FERDINAND R. HASSLER ( S250 )
GENERAL SERVICES AND REQUIREMENTS
ITEM NO. 002 01OCT2019
Approach, Berth and Mooring NOAA MEB
002 - 1
1.0 ABSTRACT
1.1 The Contractor shall provide a safe and adequate approach route, safe and secure berth, and moor the vessel.
2.0 REFERENCES
2.1 MIL. STD. MIL-C-28628D, dtd. July 1991; Camels.
2.2 MIL. STD. MIL-F-29248, dtd. 21 November 1986; Fenders, Marine, Foam Filled, Netless
2.3 NOAA Drawing No. FA01, Profiles
2.4 NOAA Drawing No. FA02, General Arrangement
3.0 ITEM LOCATION/DESCRIPTION
3.1 The following vessel characteristics and expected arrival conditions are provided:
3.1.1 Expected arrival draft:
a) Fwd: TBD
b) Aft: TBD
3.1.2 Highest Point Above Baseline: 22 m (Mast)
3.1.3 Principal Characteristics:
LENGTH OVERALL 37.7 m (123.7 ft)
BREADTH MAIN DECK 16.4 m (53.8 ft)
BREADTH PONTOON 18.5 m (60.7 ft)
DRAFT (Design Waterline) 3.85 m (12.6 ft)
FULL LOAD DISPLACEMENT 744.4 tonnes (732.6 long tons)
4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES: None
GENERAL SERVICES AND REQUIREMENTS
ITEM NO. 002 01OCT2019
Approach, Berth and Mooring NOAA MEB
002 - 2
5.1 The contractor and all subcontractors regardless of tier are advised to review other work items under this contract, inclusive of work items 007and 005, to determine the collaborative effects of these work requirements. Many of the definitions relating to performance of this work item are found in Work Item 001.
6.0 QUALITY ASSURANCE REQUIREMENTS: None additional.
7.0 STATEMENT OF WORK REQUIRED
7.1 The ship must be afforded a safe approach, secure berth, and safe mooring at all times.
7.2 APPROACH:
7.2.1 The ship shall be afforded an unobstructed approach to the Contractor’s facility (plant);
including rented, leased, subcontracted facilities, or the facilities of any subcontractor where the vessel will be berthed and moored, for any part of the performance period. There must be no danger of the ship grounding, or alliding with all overhead obstructions during transit.
This applies for delivery to the Contractor, redelivery to the Government, or any inter/intra facility transits.
7.2.2 Consistent with ship’s draft condition, the ship shall remain afloat with out any danger of grounding and avoid alliding with all overhead obstructions during all transits.
a) A minimum “Air Draft” clearance of not less than Ten (10) Feet shall be afforded between the highest vertical projection of the vessel at mean high water, all bridges and any cables passing above/across the marked channel along the entire route.
7.2.3 The minimum amount of water under the deepest / lowest projection from keel baseline at all times all tides during transit/approach shall be as follows:
a) From the sea buoy to a point in the navigable channel where the contractor takes delivery of the vessel, minimum clearance shall be 3 Feet of water under the lowest projection at mean low water.
b) From the point in the navigable channel where the Contractor takes delivery of the vessel, and vessel has Pilot aboard with adequate tug support to proceed dead stick to the intended pier, minimum clearance shall be 2 Feet of water under the lowest projection at mean low water.
5.0 NOTES
GENERAL SERVICES AND REQUIREMENTS
ITEM NO. 002 01OCT2019
Approach, Berth and Mooring NOAA MEB
002 - 3
7.2.4 Offerors must submit with their proposals copies of all the latest National Oceanographic and Atmospheric Administration (NOAA) (or US Army Corps of Engineers) waterway approach charts to their facility. Charts are to show the entire route of transit from the sea buoy to the Contractor’s facility, including any for proposed inter/intra facility transits. Charts must provide adequate demonstration that the Offeror has positively determined the route(s) providing safe vessel transit. The approach chart shall be equal to the berthing chart in dimensions and contain the following data:
7.2.5.1 Offerors shall furnish current depth soundings for the approach to the pier and/or dry-dock from the main channel.
7.2.5.2 Soundings must indicate the depths over the full length of the approach, from the point in the navigable channel where the contractor takes delivery of the vessel to the pier and/or drydock at a maximum of one hundred (100) foot intervals.
Adequate breadth of soundings shall be provided to demonstrate sufficient underwater clearance for vessel arrival, departure and any required turning evolutions. Approach soundings shall be considered current if taken within two hundred and seventy (270) days from the date of issue of the solicitation. NOAA charts or excerpts of such documents will not be accepted.
7.2.5.3 All information must be readily available to clearly chart the progress of the ship from arrival at the port to safe mooring or dry-docking. The ship must be afforded safe access and egress to and from the Contractor’s pier and/or dry-dock.
7.3 BERTH:
7.3.1 Consistent with ship’s anticipated arrival drafts, the ship shall remain afloat (except when dry-docked), with no danger of grounding during the entire performance period.
7.3.2 The Contractor's assigned berth for the vessel shall be at a suitable pier where the ship will remain afloat (not resting on the bottom) at all times. The minimum amount of water under the deepest / lowest projections from keel baseline at all times while at the pier and all tides shall be no less than three (3) feet of water except when weather conditions exist per work item 007.
7.3.3 The ship must be afloat during any anticipated severe weather, as covered under work item 007.
7.3.4 Offerors must submit with their proposal all information relative to berthing facilities.
Information must include the following characteristics of the pier:
GENERAL SERVICES AND REQUIREMENTS
ITEM NO. 002 01OCT2019
Approach, Berth and Mooring NOAA MEB
002 - 4
• Location
• Pier number and/or name
• Street address, city, state, and zip code
• Geographic reference to a current navigational chart using longitude and latitude coordinates.
• Length
• Width
7.4 MOORING:
7.4.1 The ship shall be provided a safe and secure mooring capable of withstanding the force of winds at a speed of 40 knots received perpendicularly on the beam at drafts consistent with minimum acceptable dry-docking displacement or the light load condition, (which ever is greater as stated in the solicitation). Not less than seventy five percent (75%) of the ship shall be along side the pier. Should any portion of the ship extend beyond the pier, a minimum of three (3) separate additional mooring points shall be provided for each extension. These shall be in addition to those on the pier. The additional mooring points shall be distributed on both the Port and Starboard sides of the ship.
7.4.2 Offerors must submit with their proposal all information relative to mooring facilities.
7.4.3 Information must include the following characteristics of the mooring arrangement:
a. Location, pier number and/or name, street address, city, and state with geographic reference to current navigational chart using longitude and latitude.
b. Length
c. Width
d. Locations, type, design and proof test loads for all mooring fittings, e.g., bollards, bits, cleats, deadmen, etc.
e. The arrangement of all mooring lines between the ship and mooring securements.
f. The angle of the mooring lines between the ship and each mooring securement point.
g. Quantity, size, locations and securement method of all camels and fenders.
h. General construction characteristics including: type, location, quantity of pilings; surface type and condition; location and sizes of drains; buildings and structures (sheds); width of apron and access limits for vehicles.
i. All permanently installed services, e.g.’, shore power, fire water mains, potable water lines, telephone lines, steam, compressed air. In addition, the locations where portable services equipment (when necessary), will be parked shall be indicated.
j. Location of and distances to nearest fire alarm call boxes.
k. Fences and gates
GENERAL SERVICES AND REQUIREMENTS
ITEM NO. 002 01OCT2019
Approach, Berth and Mooring NOAA MEB
002 - 5
7.4.4 Each Offeror shall draw the ship to scale, in the exact location it will occupy during the performance period, using the ship characteristics given in this solicitation on the mooring chart.
7.4.5 Documentation of design load calculations for mooring appurtenances shall be furnished.
Calculations shall demonstrate design and construction to be capable of withstanding wind speeds of 64 to 118 knots, when received perpendicularly on the beam (at drafts consistent with minimum acceptable dry-docking displacement or the light load condition, (which ever condition in the solicitation creates the greater sail area), and not be torn out.
7.4.5.1 In those instances where the documentation of the design loads for securement appurtenances cannot be provided, it shall be required to have furnished copies of the most recent test certificates.
7.4.5.2 Test certificates shall be considered recent if tests were conducted within five (5) years of the date of issue of the solicitation, and the pier has not been subject to potential collision or weather-related damage. NOAA charts or excerpts of such documents will not be accepted.
7.4.5.3 All mooring appurtenances regardless of design type, i.e., bollards, bitts, or cleats, must be in an upright position and have bases or pedestals in sound condition without any broken securement bolt holes in the base mounting flanges. All securements (bolts, washers, nuts, etc.) shall be installed tightly in place, and in good condition.
All arms and horns in place with none missing, broken, bent, misshaped or distorted.
Concrete foundations shall be in sound condition without excessive spalling and cracks or chipped and damaged concrete. Damage due to spalling, cracking, and chipping over ten percent of a foundation’s area is not acceptable. Wood and pier mooring appurtenance foundations, stringpiece mountings and support structures shall be in sound condition without cracks, rips, splits, or missing portions.
7.4.5.4 All information must be readily available to clearly ascertain the safety afforded by the mooring arrangement offered the ship.
7.4.6 Camels and/or fenders:
7.4.6.1 Camels and/or fenders shall be used at all times to breast out (separate) the ship from the pier. Camels shall be single or multiple, of hardwood in accordance with or equal to reference 2.1.
GENERAL SERVICES AND REQUIREMENTS
ITEM NO. 002 01OCT2019
Approach, Berth and Mooring NOAA MEB
002 - 6
7.4.6.2 Fenders shall be of the suspended foam filled design in accordance with or equal to reference 2.2, or solid rubber dock suspended type.
7.4.6.3 Floating camels and /or suspended fenders shall be a minimum of six (6) feet wide/ diameter and six (6) feet long.
7.4.6.4 Dock mounted fenders shall provide for a minimum clearance for SIX (6) feet.
7.4.6.5 The quantity and frequency of placement for camels/fenders shall be no less than one camel/fender for each 40 feet of the ship’s length over all, and adequate to protect the ship form contacting the side of the pier.
7.4.7 In instances where it is necessary to breast the ship out from the pier by use of a barge to facilitate achieving adequate depth of water for berthing, or when a floating crane is brought alongside in performing a work item(s), the barge or crane shall be fended off from the side of the ship by use of camels or fenders. Truck or heavy construction machinery tires are not acceptable.
7.4.8 During the course of this repair/overhaul period, no other ship will be docked alongside of or tied up to this vessel, nor shall this ship be docked alongside of or tied up to any floating dry-dock.
8.0 GENERAL REQUIREMENTS: None Additional
| NOAA | Ship | FERDINAND | R. | HASSLER | ||
| ( | S250 | ) | ||||
| GENERAL | SERVICES | AND | REQUIREMENTS | |||
| ITEM | NO. | 005 | 29MAY2021 | |||
| General | Services | for | Ship | NOAA | MEB |
005 -
1.0 ABSTRACT
1.1 Provide general services to the ship for duration of the overhaul period.
2.0 REFERENCE/ENCLOSURES
2.1 References:None
3.0 ITEM LOCATION/DESCRIPTION
3.1 Shipwide/Various
4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES
4.1 None.
5.0 NOTES
5.2 Review other work items under this contract to determine their effect on the work required by this work item.
6.0 QUALITY ASSURANCE REQUIREMENTS
6.1 All work performed and services provided shall be to the satisfaction of the COR.
7.0 STATEMENT OF WORK REQUIRED
7.1 Furnish the services specified in this work item, from the date of the ship’s arrival at the Contractor's facility until the date of final departure from the Contractor's facility:
7.1.1 Electrical Shore Power
7.1.1.1 The Contractor shall provide a reliable source of electrical power at a minimum capacity of 400 Amps. This power shall be for ship’s use only; Contractor is responsible for furnishing separate power for Contractor activities. Shorepower substations shall be enclosed in a vault or designed to be weather-proof. Substation shall have a primary isolation switch. Substation secondary shall be a three phase ungrounded system and shall have 400 amp circuit breakers for each shore power connection. Line to line voltage at the ship’s service switchboard shall be maintained at 480V +/- 5%, 60 Hz +/- 3%. Line voltage imbalance shall not exceed 2%.
7.1.1.2 One (1) 400 amp shore power cable with NATO (Joy type) plug is required to be furnished by the contractor, to connect the pierside substation secondary to the ship’s shore power connection. Electric cables utilized shall be in good material condition, free of tears, cracks or poorly repaired insulation. Cables shall be sized such that the voltage drop between the substation secondary and the ship’s shore power connection does not exceed 4% at full load. All three phases shall be carried in each cable. All conductors of each cable shall be of equal cross-sectional area. Cable lengths shall be of equal length +/- 10% of the average length. Cables shall be routed such that there is sufficient slack to allow for natural movement of the ship with tide and weather, but length shall not be excessive such that the cables be allowed to fall into the water or become trapped between the ship’s hull and the pier. Cables shall avoid sharp edges and tight bends, and proper strain relief shall be provided for vertical runs.
| NOAA | Ship | FERDINAND | R. | HASSLER | ||
| ( | S250 | ) | ||||
| GENERAL | SERVICES | AND | REQUIREMENTS | |||
| ITEM | NO. | 005 | 29MAY2021 | |||
| General | Services | for | Ship | NOAA | MEB |
Cables shall be protected from pedestrian and vehicular traffic. In line connectors and splices shall be properly insulated, sealed and elevated such that they will not be exposed to standing water. Subsequent to installation, but prior to energizing, resistance tests (500V, 1 megaohm minimum corrected to 70 degrees F) shall be performed between conductors, and between each conductor and ground for all cables. Each cable shall be checked for proper phase rotation.
7.1.1.3 Ship shall be bonded to the pier whenever shore power connection is energized to ensure proper operation of ship’s ground detection equipment. Contractor shall be responsible to connect and disconnect upon ship’s arrival, in-yard shifts, dock and sea trial events, and for ship’s departure. Ship’s shore power connection boxes are located on the 01 Level aft bulkhead on centerline. Contractor shall perform walkthrough with the COR and the vessel’s Chief Marine Engineer upon arrival to lay out an approved shore power cable routing.
7.1.2 Potable Water
7.1.2.1 Provide potable water, 60 psig at approximately 100 GPM. Provide and install all valves, fittings and hoses required to connect to the ship’s shore potable water connection. All equipment and installations used shall meet United States Public Health Service or equivalent international public health service standards for drinking water intended for human consumption. It is strictly prohibited to connect anything other than potable water to the potable water manifold. The potable water connection shall be fully dedicated and direct connection to a potable water source. No split lines or additional headers allowed. Connect and disconnect potable water upon ship’s arrival, at each in-yard shift, for tests and trials and for ship’s departure.
Potable water connections are located on the Main Deck, port side.
7.1.2.2 Potable Water Pricing: Provide a calibrated in-line water meter with which to measure the vessel’s shore potable water consumption. The meter shall be installed in the immediate vicinity of the ship’s shore potable water receiving station(s) and shall be readily accessible to the COR and the vessel’s Chief Engineer. An initial meter reading shall be witnessed by the COR and the Chief Engineer. Meter readings shall be recorded and presented to the COR on a weekly basis. At the end of the availability, the final meter reading shall be recorded and witnessed by the COR and the Chief Engineer. A report shall be prepared and submitted with total calculated potable water consumption. The Government will only pay for actual potable water consumed. The contractor shall provide a bid price based on an estimated potable water consumption of 1,500 gallons per day. In addition, contractor shall bid a unit price per gallon for adjustments to the award price for lesser or greater total consumption. Any required adjustments shall be made via a contract modification.
7.1.7 Sewage and Gray Water Disposal
| NOAA | Ship | FERDINAND | R. | HASSLER | ||
| ( | S250 | ) | ||||
| GENERAL | SERVICES | AND | REQUIREMENTS | |||
| ITEM | NO. | 005 | 29MAY2021 | |||
| General | Services | for | Ship | NOAA | MEB |
7.1.7.1 Provide all pumping arrangements, hoses, connections and shore-side disposal facilities necessary to remove and dispose of sewage and gray water from the ship for the duration of the performance period, in accordance with all federal, state and local requirements. Ensure all equipment is in good material condition and that all connections are 100% leak-free. Connect and disconnect sewage and gray water lines upon ship arrival, and for vessel departure.
7.1.8 Debris and Garbage Removal
7.1.8.1 Clean the entire ship on a daily basis, Monday – Saturday, except federal holidays.
All paint containers, chips, shavings, dirt, paper, boxes, and other work item debris shall be collected and placed in metal containers which shall be removed daily from the ship and disposed of in accordance with state and local regulations. Oil, refuse, hazardous wastes, and scrap materials, shall also be removed on a daily basis and disposed of in a proper manner and in accordance with federal, state and local laws and regulations. No debris or garbage shall be left onboard the vessel overnight.
7.1.8.2 All garbage that has been generated by the ship's crew and shipyard personnel shall be collected and removed on a daily basis. The contractor shall provide metal containers at appropriate locations for garbage deposit. Minimum ¾” thick plywood deck protection shall be placed under all garbage containers. Garbage containers shall be maintained in a sanitary condition, free of insects and rodents.
7.1.9 Working Deck Protection
7.1.9.1 Contractor shall NOT utilize working deck garage areas for lay-down, garbage containers, or staging areas without written consent from the COR. As authorized, contractor shall temporarily install adequate means to protect working deck non-skid surfaces. Blocking, plywood, and HERCULITE lay down materials shall be utilized wherever contractor lands materials and/or equipment on the working deck. Any damage to working deck surfaces shall be repaired and restored to like new condition, at contractor’s expense.
7.1.10 Gangways
7.1.10.1 Provide and install two (2) safe and proper gangways for access to the ship on thew main deck. One gangway shall be used for routine access to the vessel. The second gangway shall be designated for emergency use only. Gangway locations shall be to the satisfaction of the COR.
7.1.10.2 Gangways shall meet the requirements of OSHA Standard 1915.74, Access to Vessels. Gangways shall be a minimum of 20 inches wide. Gangways shall be adequately secured against shifting, shall be illuminated and properly trimmed.
7.1.10.3 Each side of the gangway, and turntable if used, shall have a railing with a minimum height of 33 inches, and shall be fit with a mid-rail. Rails shall be wood, pipe, chain, wire or rope and shall be kept taut at all times. The gangway shall be properly trimmed at all times.
7.1.10.4 Obstructions shall not be laid on or across the gangway. Means of access shall be adequately illuminated for its full length. Safety nets shall be provided and secured
| NOAA | Ship | FERDINAND | R. | HASSLER | ||
| ( | S250 | ) | ||||
| GENERAL | SERVICES | AND | REQUIREMENTS | |||
| ITEM | NO. | 005 | 29MAY2021 | |||
| General | Services | for | Ship | NOAA | MEB |
to the ship and to the pier edge to provide adequate coverage. The net shall extend 6 feet on all sides of the gangway.
7.1.10.5 The emergency use gangway shall have signs posted at each end indicating its use for emergencies only.
7.1.10.6 Any alterations to ships rails and life lines required to place gangways must be restored to original condition prior to the vessel’s departure.
7.2.1 Shipboard and Compartment Access and Security
7.2.1.1 Within ten (10) days of the contract award, submit the following plans to the
COR for review and approval.
7.2.1.2 Security Plan: The plan shall include a description of security measures that will be taken to safeguard the ship and its machinery, spare parts, and outfitting.
7.2.2 Shipboard Access:
7.2.2.1 No less than five (5) days before scheduled ship arrival, the Contractor shall deliver to the COR a list of all contractor and subcontractor companies (including contractor furnished Tech Reps) personnel who will be involved in the onboard performance of the contract. The list shall contain the names and citizenship of all contractor and subcontractor personnel.
7.2.2.2 Prior to the commencement of each weekend or unscheduled overtime shift, not identified in the contractor’s production plan schedule as originally submitted with the contractor’s proposal (or subsequently revised during contract performance), the contractor shall provide to the COR a list of all contractor and subcontractor (including contractor furnished Tech Reps) personnel scheduled to work each shift.
The list shall contain the names and citizenship of all contractor and subcontractor personnel.
7.2.2.3 The contractor shall have and demonstrate for approval at the time of submitting his proposal, an employee identification badge/pass and security system. The requirements are for all direct employees to be issued badges.
7.2.2.4 Temporary individual badges shall be issued to all subcontractor workers and visitors.
Subcontractor and visitor badges shall be clearly identifiable as such from those of full time employees by being distinctly different in color and marking from those issued direct employees and each from the other.
7.2.2.5 The contractor shall obtain from the COR a list of crew members (and changes thereto as they occur), Government Technical Representatives and other known visitors for each day. These lists shall be the basis for NOAA access to the ship.
7.2.2.6 The COR may deny access to the ship to contractor personnel if the personnel list required by paragraph 7.3.1 is not delivered prior to the start of the performance period or if the personnel list required by paragraph 7.3.2 is not delivered prior to the start of weekend or unscheduled overtime shifts.
7.2.3 Shipboard Security
| NOAA | Ship | FERDINAND | R. | HASSLER |
| ( | S250 | ) |
| GENERAL | SERVICES | AND | REQUIREMENTS | |||
| ITEM | NO. | 005 29MAY2021 | ||||
| General | Services | for | Ship | NOAA | MEB |
005 - 5
7.2.3.1 A roving uniformed security guard (firearms not required), shall be posted aboard continiously. The guards shall be other than full time production workers assigned for this task on a temporary basis.
7.2.3.2 The guards shall insure that only authorized personnel are allowed onboard, this to include: COR and associated Overhaul Management Team staff, all ship's force, contractor workers, subcontractor workers, Government Furnished Technical Representatives, and visitors (NOAA and others when prior authorization is issued by
COR).
7.2.3.3 Verification of each individual's identity shall be required by presentation of a valid contractor issued identification card or Government issued identification card. ONLY these documents will be acceptable identification.
7.2.3.4 Unannounced visitors without contractor issued or government issued identification are not permitted onboard The guard shall immediately notify the COR, the CO, and the contractor’s Project Manager to verify the visitors identity.
7.2.3.5 The contractor shall ensure that painted signs with one (1) inch lettering giving notice of the conditions for access described in paragraph 7.3.7 are prominently displayed at the foot of each gangway. Signs shall be in English language, and additionally in the language of the local area.
7.2.3.6 The roving patrol shall continuously tour all spaces. Spaces to be inspected shall include but not limited to:
The lowest level of all machinery spaces; engine room(s), auxiliary machinery room(s), pump room(s), shaft alley(s), generator room(s), boiler /fire room(s), steering gear room(s) and all other machinery spaces.
All engineering, dry, general material, refrigerated and frozen, paint and flammable, boatswain's, sponsor, and other store rooms.
All communication, scientific data, telemetry, sponsor data, sonar trunk(s), laboratories, work and machine shops.
All galley(s), pantry(s), mess rooms, lounges, berthing areas, toilets and showers, and other spaces.
7.2.3.7 The roving patrol shall be required to enter all unlocked spaces and traverse same in a manner that necessitates using an exit other than the one used for entry, except in those cases where only one entry/exit route/door exists.
7.2.3.8 All doors to spaces not requiring entry by contractor workers in the performance of the repair work set forth in the work items of the specifications shall be checked to ensure they are locked.
7.2.3.9 All such spaces will be locked by the ship's force upon arrival at the contractor's facility. The contractor’s project manager shall ensure that the head of the shipyard security force has assigned a responsible individual to perform an initial inspection of all spaces with a ship’s force officer to identify the locked spaces and prepare a list of these for use by the roving patrol. The list shall be updated daily or as frequently as necessary. Doors on the list found unlocked shall be reported immediately to the head of the shipyard security department and to the shipyard Project Manager.
Copies of the list and each revision shall be furnished to the COR.
| NOAA | Ship | FERDINAND | R. | HASSLER | ||
| ( | S250 | ) | ||||
| GENERAL | SERVICES | AND | REQUIREMENTS | |||
| ITEM | NO. | 005 | 29MAY2021 | |||
| General | Services | for | Ship | NOAA | MEB |
7.2.3.10 The roving patrol shall be aware of and on the alert to the signs and conditions which indicate any of the following:
Flooding and rising water levels in machinery spaces and holds Fire Water/oil damage (from leaking or broken steam, water or oil piping) Explosion dangers (from escaping welding/burning and sewage gases) Live disconnected electrical lines or welding leads Loose and unsecured equipment or machinery which can fall/drop from heights Unauthorized persons onboard the ship during work and non work hours
7.2.3.11 It shall be the contractor's responsibility to provide the required training to the roving patrol on how to identify these conditions in a shipyard work environment.
7.2.3.12 The roving patrol shall have portable radio communications at all times. In addition, communications with other shipyard security forces shall also be maintained.
7.2.4 Compartment Security
7.2.4.1 All compartments shall remain locked unless the contractor is required to accomplish daily work. Ship’s force shall be notified in advance of required entry into any particular compartment.
7.2.4.2 The contractor shall permit free movement of properly identified employees and materials of the government to all points of the ship at all times during the contract period. The contractor shall also permit free movement of properly identified government employees and subcontractors through the yard and to the ship. The contractor shall allow private contractors, hired by the government to perform certain installation work aboard the ship. The Contractor shall grant passage through his facility to the ship to all properly identified technicians or other workmen hired by the government. A driver’s license or similar ID and a copy of a government work order or purchase order shall constitute proper identification.
7.2.4.3 Contractor and subcontractor personnel shall not be permitted to eat in the ship’s mess. Ship’s mess decks are off limits to contractor and subcontractor personnel not performing work in those spaces as a part of this specification.
7.2.4.4 The contractor shall take appropriate measures to ensure that all contractor and subcontractor personnel comply with all posted notices onboard.
7.3 Care of the Ship
7.3.1 Provide a safe berth for the vessel at a pier where the ship will be afloat with a minimum of three (3) feet of water under the keel/lowest projection at all times and during all tides, as specified in work item 002 of this work package. The ship shall be securely moored to the pier with the contractor’s mooring lines, sufficient camels and/or fenders between the ship and pier to prevent any structural and coating system damage. Mooring facilities and locations of protective camels and/or fenders shall be presented for COR approval per work item 002 prior to vessel’s arrival at the contractor’s facility.
| NOAA | Ship | FERDINAND | R. | HASSLER | ||
| ( | S250 | ) | ||||
| GENERAL | SERVICES | AND | REQUIREMENTS | |||
| ITEM | NO. | 005 | 29MAY2021 | |||
| General | Services | for | Ship | NOAA | MEB |
7.3.2 Upon arrival of the vessel at the contractor's facility, conduct a joint survey with COR to ascertain the operational status of all equipment and systems on board the vessel, and the cleanliness of all spaces onboard the vessel. The ship's crew will be made available for up to seventy-two (72) hours after arrival to assist in this survey.
7.3.2.1 Submit an “As Found” condition report to the COR within five (5) days after arrival of the vessel at the contractor's facility.
7.3.3 The contractor shall be responsible for the entire ship from the time of delivery to the contractor until the COR accepts it for redelivery. All ship's parts, equipment, systems, etc., damaged or destroyed by the contractor shall be repaired or replaced, as original, at contractor's expense. Such consideration includes, but is not limited to, piping, electric cables, machinery, insulated/refrigerated storerooms, compartments, bulkheads, decks, and ducting damaged by neglect, weather, personnel, dirt, foreign substances, etc., or lost through theft.
7.3.4 All paint and flammable liquids that are temporarily stored on board the ship by the contractor shall be stored in a suitable container designed in accordance with international, federal, state, and local regulations for flammable liquid storage.
7.3.5 Rigid control of welding and grounding shall be maintained for the protection of the hull, stern tubes, and hull appendages. Care shall be taken to ensure that welding polarity and ground connections of welding machines used aboard the ship or other ships in the immediate vicinity, on the pier, or on the wharf to which the ship is moored, shall not damage any part of the ship.
7.3.6 The contractor shall adequately protect the underwater portion of the hull from the time of delivery until the COR accepts the ship for redelivery. If, at any time prior to redelivery, circumstances exist for believing that the underwater portion of the hull has been damaged or impaired, the contractor shall make arrangements at his expense for an underwater survey. If damage has in fact occurred, the contractor shall place the ship in drydock and completely repair, clean, and paint the damaged areas.
7.3.7 The contractor shall survey all deck drains in way of work areas upon vessel arrival and submit a condition report on whether subject drains are free and clear or clogged. Drains found clogged subsequent to this initial survey shall be kept clear and in proper working condition, unless previously identified as being clogged.
7.3.8 The contractor shall maintain all machinery space bilges in a clean and dry condition for the entire shipyard availability period.
7.4 External Vessel Contamination Protection
7.4.1 Prevent contamination of ship’s ladder ways, decks, deck coverings, equipment, materials, furnishings, and spaces at all times throughout the performance period of this contract. This shall include, but not be limited to operations during abrasive and/or hydro blasting, vacuum blasting, scaling, surface cleaning, sanding, painting, welding, grinding, pumping/transferring of water/oils/liquids, and any other source of contamination by work accomplished in this specification package. Contractor shall be responsible for protecting against contamination from neighboring and/or adjacent facilities and/or other work projects within contractor facility, that are capable of emitting contaminants onto the vessel.
Accomplish below specified requirements as found required in support of this work
| NOAA | Ship | FERDINAND | R. | HASSLER | ||
| ( | S250 | ) | ||||
| GENERAL | SERVICES | AND | REQUIREMENTS | |||
| ITEM | NO. | 005 | 29MAY2021 | |||
| General | Services | for | Ship | NOAA | MEB |
specification package and as found required to protect vessel from outside sources of contamination:
7.4.2 Temporarily install protective coverings on the deck, deck equipment, machinery, wire ropes, cranes, boats, and any other materials and/or equipment in way of possible contamination. Contractor shall use heavy duty canvas, then cover the canvas covering with heavy duty PVC sheets. Protection and covering material shall be fastened securely to prevent protective coverings from being removed.
7.4.3 Temporarily plug, blank, wrap, cover or mask openings and portlights to prevent entry of contaminants into machinery, equipment, systems, electronic equipment, valves, vents, and other openings, when not in use.
7.4.4 Temporarily install new industrial foam filter material on the intake and exhaust end of the ventilation systems. Renew filtering material when air flow becomes restricted on exhaust and intake of ventilation systems. Change out and renew filter material when required, for the entire contract performance period.
7.4.5 Removal of any preventive measures specified above shall not be accomplished without permission of the COR. Where removal of preventive measures specified above become necessary to accomplish other related work items, the contractor shall remain responsible for ensuring no contamination of the areas are involved, and preventive measures are restored.
7.4.6 Once approved by the COR the contractor shall remove protective measures and sweep, clean, and washdown area, and equipment impacted.
7.5 Final Vessel Cleaning
7.5.1 Three (3) days prior to the crew move-aboard milestone if applicable, or approximately 1 days prior to contract performance period end date, the contractor shall accomplish the following cleaning requirements onboard the vessel:
7.5.1.1 All temporary protective covering shall be removed.
8.0 GENERAL REQUIREMENTS: None Additional
PAINT AND PRESERVATION
ITEM NO. 631-2 27MAY2021
Top Side General Corrosion Control NOAA MEB
631-2-
1.0 ABSTRACT: This item described the requirements provide personnel, tools, equipment, and materials to paint the 01 and 02 weather decks and 01 level super structure aboard the NOAA Ship FERDINAND R.
HASSLER.
2.0 REFERENCES/ENCLOSURES
2.1 REFERENCES
2.1.1 Drawing M286-631-FC61-2, Paint Schedule
2.1.2 Drawing M286-085-FA01-013, Profiles
2.1.3 Drawing M286-085-FA02-015, General Arrangements
2.1.4 Steel Structures Paint Council (SSPC) Standards
2.1.5 SFLC Standard Specification 6310
3.0 ITEM LOCATION/ QUANTITY/DESCRIPTION
3.1 Location: Various, Weather Decks (01 and 02 Level)
4.0 GOVERNMENT FURNISHED MATERIAL/SERVICES
4.1 NONE
5.0 NOTES
5.1 The contractor and all subcontractors, regardless of tier must consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTRs.
5.2 The contractor and all subcontractors, regardless of tier, are advised to review other work items under this contract to determine their effect on the work required under this work item. Many of the definitions relating to performance of this work item are found in Work Item 001.
6.0 QUALITY ASSURANCE REQUIREMENTS
6.1 All surface preparation and painting shall be in accordance with the paint manufacturer’s printed recommendations and instructions. Where this specification or referenced material contradicts manufacturer’s instructions, the manufacturer’s instructions take precedence.
6.2 Provide the services of a National Association of Corrosion Engineers (NACE) Level 2 or 3 qualified technical representative for the coating products for supervision of surface preparation and coating system application. The technical representative shall be primarily used to observe the surface preparation, paint film thickness of coats, and to resolve technical difficulties such as allowable overcoat times, low ambient temperature or high relative humidity.
PAINT AND PRESERVATION
Top Side General Corrosion Control NOAA MEB
6.3 Provide the on-site services of a manufacturer's representative for the coating system being applied.
All surface preparation and other aspects of the coating system application shall be acceptable to the paint manufacturer's representative.
6.4 The COR or designated representative shall be present for all inspections and grant final approval before proceeding to the next phase of surface preparation or coating application.
7.0 STATEMENT OF WORK
7.1 The surfaces to include in this work item include:
7.1.1 01 Level Exterior Deck, Rails, Stanchions and Bulwarks
7.1.2 01 Level Super Structure
7.1.3 02 Level Deck, Rails, and Stanchions
7.2 Accomplish all required set-up, masking, and containment requirements applicable with any/all local, state, and federal regulations pertaining to work in this work item.
7.2.1 Secure, or otherwise mask off ventilation intakes or exhausts in the immediate vicinity to prevent the ingestion of dust/debris and fumes into the ship.
7.2.2 Coordinate with COR and Ship’s Force to secure power to lights, receptacles, equipment, etc. as needed.
7.2.3 Tarp off and/or shrink-wrap area to prevent paint chips, debris, or other shipboard contaminates from entering the water.
7.2.4 During inclement weather tarp off, or otherwise protect, the area from contamination.
Space heaters and dehumidifiers shall be used as needed to ensure the environmental conditions are within the paint manufacturer’s recommended ranges during the entire curing timeframe.
7.3 Accomplish surface preparation of the areas identified in paragraph 7. 1. Prepare the areas as follows:
7.3.1 Remediate the chalked appearance of the superstructure on the 01 level, and all rails, stanchions, and bulwarks. The total bulkhead area is approximately 1600 sq. ft.
7.3.1.1 Pressure wash to remove the chalked appearance and etch the coating with sandpaper, and re-clean to remove dust.
7.3.1.1.1 Any areas with exposed substrate of less than one square foot shall be spot primed and feathered IAW SSPC-11 “Power Tool Cleaning to Bare Metal”. Edges shall be feathered into sound coating system at least 2 inches all around. Apply prime coat within 12 hours but before flash rusting occurs, repeating power tool cleaning if necessary.
7.3.1.1.2 Significantly damaged or deteriorated (rusting, peeling or delaminating) areas greater than one square foot shall be abrasive blasted to “Near White Metal” in accordance with SSPC-10, or UHP hydro blasted to WJ-3. Edges shall be feathered into sound coating system at least 2
PAINT AND PRESERVATION
Top Side General Corrosion Control NOAA MEB inches all around. Apply prime coat within 12 hours but before flash rusting occurs, re-blasting if necessary.
7.3.1.2 Pay particular attention to areas not normally accessible to the crew without the use of a ladder.
7.3.1.3 Top coat with Sher-Loxane 800 or similar polysiloxane paint suitable for marine applications.
7.3.1.4 Wrap/Unwrap as needed, taking care not to mar glass windows and ports.
7.3.1.5 Cut in all lines.
7.3.1.6 Re-establish black dado line at bottom, hand rails, and weather doors.
7.3.1.7 Provide the COR with recommended products if deviating from listed paint system.
7.3.1.8 Apply coating systems per reference 2.1.5.
7.3.1.8.1 Minimum between coat drying times must be carefully observed. The general application instructions such as drying and overcoat times indicated in this specification and in the manufacturer's product literature may be modified as indicated by the paint manufacturer's representative to accommodate cold or hot weather.
7.3.1.8.2 Any over spray shall be removed and the hull coating system repaired.
7.3.2 Prepare the 01 and 02 Level Decks to SSPC-SP 10/ NACE NO. 2 using grit confirming to MIL-A-22262 or SSPC-SP WJ-2(L)/NACE WJ-2(L) in accordance with Appendix A of reference 2.1.5 for “Weather Decks Non-Skid, Broadcast Grit for Steel”.
7.3.2.1 Apply deck coating system in accordance with Appendix A of reference 2.1.5
(SFLC STD Spec 6310) for “Weather Decks Non-Skid, Broadcast Grit for Steel”.
7.3.2.2 The top coat for decks shall be Deck/Blue Gray #16099 from color card AMS-
STD-595A.
7.3.2.3 Heavily coat deck surfaces in #16 broadcast grit conforming to the requirements of ref. 2.1.5
7.3.2.4 No more than approximately 3 inches shall separate areas of grit coverage from the deck edge, deck machinery, or other obstructions.
7.3.2.5 COR shall be advised of the paint system selected for use and provided with all applicable documentation demonstration its applicability to this installation.
Previously discussed Sherwin Williams polysiloxane deck coatings are acceptable without further approval.
7.3.3 All coating application shall be in accordance with paint manufactures instructions except that cure times maybe modified as advised by paint manufacturer’s representative to account for cold weather.
7.3.4 Do not apply inorganic zinc to water-jetted surfaces.
PAINT AND PRESERVATION
Top Side General Corrosion Control NOAA MEB
8.0 GENERAL REQUIREMENTS
8.1 Upon award of the contract, the successful contractor may submit a proposal for a complete paint system considered to be equal to, or exceed that specified. All aspects of the proposed system shall be addressed including the following:
8.1.1 Coating compatibility
8.1.2 Manufacturer's representative availability
8.1.3 Detailed price comparison to that specified
8.2 Upon review of the proposal by the Contracting Officer and COR, a decision will be made to accept or reject the proposal. If the proposal is accepted a formal modification to the contract will be issued. If the proposal is rejected, the specified paint system will be applied.
(End Work Item)