Commissioning Statement of Work Final.docx

DOCX document 79 KB Posted

Attached to
C222--AE Replace Electrical Panels & Expand Distribution Commissioning - 583-22-106 Federal contract opportunity
Solicitation number
36C25024R0025
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10

About this file

This document outlines the scope of work for commissioning services related to Federal Contract Opportunity 36C25024R0025 to replace electrical distribution panels and expand distribution at a Department of Veterans Affairs medical center. The commissioning agent will be responsible for assessing existing electrical capacity and loads, verifying generator capacity, reviewing plans for equipment removal and new installations, attending design meetings, developing checklists and test procedures, reviewing submittals, conducting site visits and inspections, overseeing functional performance testing, preparing manuals and reports, and ensuring compliance with all applicable safety codes throughout the design and construction phases. The contract will be awarded by the Veterans Health Administration Veterans Integrated Service Network 10 to qualified firms that can provide licensed professionals to inspect and approve electrical systems and perform commissioning activities in accordance with VA requirements.

View the file

Other files for this federal contract opportunity

Other files attached to C222--AE Replace Electrical Panels & Expand Distribution Commissioning - 583-22-106, newest first.
File Type Posted
36C25024R0025.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Commissioning Agent Scope of Work 583-22-106 Replace Electrical Distribution Panels & Expand Distribution to A-wing Project Page 62

Statement of Work Commissioning Agent for Project 583-22-106 Replace Electrical Distribution Panels & Expand Distribution to A- Wing A. General Scope The Commissioning firm shall furnish professional services as a commissioning agent and consultant for project 583-22-106 Replace Electrical Distribution Panels & Expand Distribution to A-wing. The Project is to improve the electrical system and expand the electrical distribution to A-Wing within Bldg. 1, WTS at the Richard L. Roudebush Veterans Affairs Medical Center, 1481 West 10th Street, Indianapolis, IN 46202.

The Commissioning firm will be used as a consultant and a subject matter expert to support the Contracting Officer (CO) and Contracting Office Representative (COR) during the Design phase and the Construction phase of the Project.

The Commissioning agent shall certify the design and construction to meet Federal Mandates and applicable code standards.

The commissioning authority shall verify the performance of the components and systems, ensure design requirements are met, develop a commissioning plan, include commissioning and requirements in construction documents, verify installation and performance of commissioned systems (testing and system monitoring), review and verify operation/maintenance manuals and training, and a commissioning report.

B. Specific Requirements during Design

1. The Commissioning Agent shall assess the power and capacity that is currently being provided by all the electrical supply equipment within Building 23 and Substations room(A-B0139) to validate the A/E’s assessment.

2. The Commissioning Agent shall assess the load from all the electrical equipment that receives service in the A-Wing from the Bldg.23 and A-wing Substations Room to validate the A/E’s assessment.

3. The Commissioning Agent shall review and verify if the existing A-wing emergency generators (3) can provide 100% backup emergency power for all new and existing equipment that is specified to be installed within the A-wing HV Switchgear Room. If the A-wing generator capacity be insufficient, or changes are needed, the Commissioning Agent shall make sure the A/E includes the necessary changes on their design.

4. The north and east existing HV lines within the A-wing HV Switchgear Room require new switchgear. The Commissioning agent shall VERIFY that the A/E include the installation of new breakers in the design.

5. The Commissioning Agent shall review the A/E’s plan for removal/demolition of the substations to ensure there are no service interruptions and areas are continuously served with redundant power sources during the evolution. The Commissioning Agent shall review the Lockout/tagout plans from the A/E. The Commissioning Agent shall make sure the plan(s) include estimated durations of time expected to complete the various task assignments.

6. The Commissioning Agent shall review the A/E’s strategy for any outages needed to complete work in Building 23, to include any feeder switching that may need to be completed in other areas of the facility.

7. The Commissioning Agent shall review all Facility Condition Assessment (FCA) deficiencies related to A Wing power to make sure the A/E will include all deficiencies will be addressed during the project.

8. The Commissioning Agent shall ensure the A/E provides a summary/narrative at each phase of the project and review said summary/narrative.

9. The Commissioning Agent shall assist the COR in finding replacement electrical equipment and components if the lead time is out of the range of the project.

10. The Commissioning Agent shall review the design to ensure it prevent any interruptions to veteran care. If temporary equipment is the only way to prevent interruptions, the Commissioning Agent shall be involved to make sure proper equipment will be used and this is included in the bid documents. If an outage is required, then the Commissioning Agent shall assist the VA in determining what will be affected during the outage, if the VA determines this is required.

11. The Commissioning Agent shall review design to verify that the A/E includes all supporting calculations related to the design at each design phase.

12. Contractor shall attend all weekly progress meetings during the design phase, via Teams will be acceptable.

13. Commissioning Firm shall review and discuss the AE’s cost estimate with the COR to ensure that the project cost will be within the VA’s budget and compare the estimate to current market values.

In Building 23

14. The Commissioning Agent shall review the A/E’s design to ensure that the plan is to use two switchgear spares (High Voltage Breakers) that are not currently used to feed the A Wing from Bldg. 23 to the A-wing Substations Room (A-wing basement), one of these Switchgears shall be a spare that is not normally used. The Commissioning Agent shall ensure that the Main-Tie-Main, located within Bldg. 23, has an auto-paralleling feature.

15. The Commissioning Agent shall review the AE’s design to ensure that the plan is to run three conduits between building 23 and the A-wing Substations Room (A-wing basement). Two to be used for the new two service lines and the third one to be used as a spare for the future. The Commissioning Agent shall make sure the A/E is not using the same path that was used for existing feeds.

Substations room (A-B0139)

16. The Commissioning Agent shall verify that the A/E’s design is to Install double ended subs for AMS1, AMS2, & AMS3 with a closed paralleling tie so that we can switch feeders without having to turn power off to the A-Wing. This would eliminate any outages that may occur due to any maintenance. The VA’s expectation is to have the spare feed that supplies all three subs, along with an independent primary feed.

17. The Commissioning Agent shall verify that the A/E’s design ensures that existing concrete curbs/pads are compatible with new substations or specify the modifications that need to be completed to existing curbs/pads.

18. The Commissioning Agent shall verify that the A/E’s design includes demo plan for all the existing equipment that will be replaced and its attachments as well as one existing substation that is not been used in the room. Demo plan shall include but not be limited to disassembly of large equipment, recycling, removal, etc. All drawing notes shall be verified by the A/E to be complete.

19. The Commissioning Agent shall verify that the A/E’s design follows VA guidelines for the minimum required distance from other utilities and not use the existing electrical path from Building 23 to underground steam vault to A-wing HV Switchgear Room. The drawings shall call out hydro-excavation if the utilities cannot be 100% identified.

20. The Commissioning Agent shall make sure that the A/E’s design assesses all services that will be affected during electrical shutdowns. The Commissioning Agent shall make sure that the Shutdowns shall take place after hours/weekends to not affect normal hospital operations.

21. The Commissioning Agent shall verify that the A/E’s design includes a reasonable phasing plan to include utilizing a generator to provide power for all equipment removal and replacement; and configured in such a way that all critical circuits maintain two power sources.

22. The Commissioning Agent shall verify that the Phasing plans includes the temporary equipment location, drawings with all equipment connections, risk assessment and refueling plan that shall be provided to the construction contractor. Refueling shall be the responsibility of the construction Contractor.

23. The Commissioning Agent shall make sure that the A/E’s design includes replacing the existing lighting within the A-wing HV Switchgear Room with new LED lighting.

24. The Commissioning Agent shall make sure that the A/E’s design includes a plan to refinish the floor, paint all concrete curbs yellow, and provide new rubber floor mats.

25. The Commissioning Agent shall make sure that the A/E’s design Specifies all electrical shutdown work to be accomplished after hours.

26. The Commissioning Agent shall verify that the A/E’s design Provides appropriate signage plan for proper identification and safety purposes within the A-wing HV Switchgear Room.

27. The Commissioning Agent shall verify that the A/E’s design provides proper climate control (heating and cooling) within the A-wing HV Switchgear Room for worst case conditions.

28. The Commissioning Agent shall verify that the A/E’s design ensures that the exhaust system is designed to address the expected heat load of both the existing and new electrical equipment within the A-wing HV Switchgear Room. The Commissioning Agent shall make sure that the A/E’s design ensures the generator exhaust is directed so that the exhaust will not be sucked in the nearby AHU intakes or exhaust into pedestrian walkways.

29. The Commissioning Agent shall verify that the A/E’s design develops a plan to mitigate flooding issues in the switchgear room. The A wing Switchgear room has flooded in the past. The Commissioning Agent shall make sure that the A/E evaluates the storm drainage situation and provide solutions to prevent future flooding.

A Wing Generator (3) room

30. The Commissioning Agent shall verify that the A/E’s design extend MCC panels and add spare buckets to allow expansion and accommodate future emergency power requirements. Contractor may need to do some modifications to the room to make this happen.

C. Specific Requirements during Construction

1. Commissioning firm shall review all construction contractor’s bids for the project and assist the CO and COR during the bidding process.

2. During Construction and by VA direction, Commissioning Firm shall review any RFIs and shall assist the VA on answering them within three business days.

3. During Construction and by VA direction, Commissioning Firm shall review any submittals, decline/approve, and send them to the COR within three business days.

4. Commissioning firm shall perform at least one site visit weekly, unless the COR approves a different visit schedule, during project construction until project completion to ensure that the workmanship and quality meet or exceed the expectations of the VA.

5. Commissioning firm shall monitor the project progress compared to the project schedule to help keep the project on or ahead of schedule.

6. Commissioning firm shall perform the final punch list which will cover the review of the project system to ensure that the systems are programed and adjusted for the project.

7. Commissioning firm shall assist with the review and turnover of all paperwork associated with the project (wiring diagrams, installation manuals, parts books, owner's manual, test reports, operating permit and so on) to the VA.

8. Commissioning firm shall perform Safety Audits during construction.

9. Commissioning firm shall be monitoring the project progress compared to the project schedule to help keep the project on or ahead of schedule.

10. Commissioning firm shall perform an inspection of all newly installed equipment/system(s) to ensure that all work is completed and provide inspection reports to the COR.

11. Contractor shall attend all weekly progress meetings during the construction phase. Via Teams will be acceptable unless the VA requires them to attend in person with prior notice.

12. Commissioning firm shall attend all meetings that the COR or the CO ask them to attend if they are related to the project, and if VA personnel provide at least 24 hours’ notice.

13. Commissioning firm shall review and discuss all invoices with the COR.

14. Commissioning firm shall verify that the contractor will install all the required equipment and utilities as per the contract bid documents, NFPA, NEC, the VA Specs, VA Design Manual, and all Indiana state and local codes.

15. Commissioning firm will commission Architectural, Structural, Electrical, Mechanical, Plumbing, Life Safety and Fire Protection systems. Contractor shall provide a detailed report with associated photos and recommendations for correction of all work after each site visit. Commissioning firm shall provide specific specifications/drawing notes/code references for any work that does not meet a specific specifications/drawing notes/code requirement when they ask for corrections.

16. Commissioning firm shall inspect/test all electrical work and equipment and review all electrical connections (HV/MV/LV) to ensure that all installation work meets compliance with the latest NFPA, NEC, the VA Design Manual and submittal requirements.

17. Commissioning firm shall provide his visit report within 24 business hours or less after conducting the visit.

18. Commissioning Firm shall perform preinstallation inspection of the equipment and request simulated functional testing performed by the manufacturer.

19. The Commission Agent shall provide additional electrical testing to the equipment. The primary recommended standard for independent testing of the installation of electrical systems is ANSI/NETA ATS.

D. The Commissioning firm shall respond immediately to VA personnel in case needed for emergency.

E. Contractor shall review and comply the VA Whole Building Commissioning Process Manual.

F. Commissioning Agent Shall follow all Applicable Commissioning Specifications on the VA Technical Information Library (TIL) available at http://www.cfm.va.gov/til/index.asp.

G. Commissioning Firm shall secure all materials before, during and after service. The Government assumes no liability for loss of or damage of Contractor owned property held on Government premises.

H. RLR VAMC is a federal facility. RLR VAMC, its Contractors and subcontractors shall comply with all Federal, State, and local laws. The most stringent law shall apply regardless of agency hierarchy. Commissioning Firm shall comply with all UP TO DATE codes as well as specific codes applied in VA construction jobs such as NEC, NFPA, OSHA, VA Design Guides and Manuals.

I. Commissioning Firm shall obtain all necessary licenses and/or permits required to perform this work. Commissioning Firm shall take all reasonable precautions necessary to protect persons and property from injury or damage during the performance of this contract. Commissioning Firm shall be responsible for any injury to their and employees, as well as for any damage to personal or public property that occurs during the performance of this contract due to fault or negligence and shall maintain personal liability and property damage insurance having coverage for a limit as required by laws of the State of Indiana.

J. Commissioning Firm shall review, discuss with the COR all biddable documents, and make sure all work is meeting all the requirements. The VA Technical Information Library (TIL) available at http://www.cfm.va.gov/til/index.asp is managed by the VA Office of Construction and Facility Management. It is the master repository for all VA Numbered Standards for Construction to include design and construction specifications, procedures, standard details, BIM/CAD standards, equipment guides, space planning and design guides. The documents of the TIL shall be the minimum design criteria for all VA projects performed in the construction of new facilities and the modernization, alteration, addition, or improvement of its real property.

VA additionally through the documents on the TIL has adopted the latest edition of the following codes and standards (but not limited to):

1. Occupational, Safety and Health Administration (OSHA) Standards

2. International Building Code (IBC)

3. National Electrical Code (NEC)

4. NFPA 101 Life Safety Code

5. National Fire Protection Association (NFPA) Codes, except for NFPA 5000 and NFPA 900

6. National Standard Plumbing Code (NSPC)

7. Safety Code for Elevators and Escalators, American Society of Mechanical Engineers (ASME) A 17.1

8. ASME Boiler and Pressure Vessel Code

9. ASME Code for Pressure Piping

10. International Plumbing Code (IPC)

11. Architectural Barriers Act Accessibility Standard (ABAAS) for Federal Facilities

12. Building Code Requirements for Reinforced Concrete, American Concrete Institute (ACI 318 – 2) and Commentary (ACI 318 – R2)

13. Manual of Steel Construction, Load and Resistance Factor Design Specifications for Structural Steel Buildings, American Institute of Steel Construction (AISC)

14. Energy policy Act of 2005 (EPAct)Ventilation for Acceptable Indoor Air Quality – ASHRAE Standard 62.1

15. DOE Interim Final Rule: Energy Conservation Standards for New Federal, Commercial and Multi-Family High-Rise Residential Buildings and New Low-Rise Residential Buildings, 10 CFR Parts 433, 434 and 435

16. Federal Leadership in High Performance and Sustainable Buildings: Memorandum of Understanding (MOU)

17. Executive Order 13423: Strengthening Federal Environmental, Energy, and Transportation Management

18. The Provisions for Construction and Safety Signs. Stated in the General Requirements Section 01010 of the VA Master Construction Specification

19. Ventilation for Acceptable Indoor Air Quality – ASHRAE Standard 62.1

20. Safety Standard for Refrigeration Systems – ASHRAE Standard 15

21. U.S. National CAD Standard

22. 5. Additional Requirements

23. ANSI C37.50—Low-Voltage AC Power Circuit Breakers Used in Enclosures—Test Procedures.

24. IEEE 450—Recommended Practice for Maintenance, Testing and Replacement of Vented Lead Acid Batteries for Stationary Applications.

25. IEEE 1188—Recommended Practice for Maintenance, Testing and Replacement of Valve Regulated Lead Acid Batteries for Stationary Applications.

26. NEMA AB4—Guidelines for Inspection and Preventive Maintenance of Molded Case Circuit Breakers Used in Commercial and Industrial Applications.

27. NETA ATS—Acceptance Testing Specifications for Electrical Power Distribution Equipment and Systems.

28. NFPA 70B—Recommended Practice for Electrical Equipment Maintenance.

29. NFPA 70C—National Electrical Code.

30. NFPA 70E—Standard for Electrical Safety in the Workplace.

31. NFPA 110—Standard for Emergency and Standby Power Systems.

32. NFPA 111—Standard for Stored Energy Emergency and Standby Power Systems.

K. General Requirements:

The Commissioning Agent shall include all tasks and provide all deliverables to complete the scope of work outlined below:

Commissioning Agent Task/Deliverables Description Pre-Design Phase

Project Phase/ Cx Task
Commissioning Task Description
Commissioning Deliverables

PRE-DESIGN PHASE

Pre-Design Commissioning Kickoff Meeting
Conduct Pre-Design Commissioning Kickoff Meeting with the VA and the Design Team.

Establish or review Owner’s Project Requirements (OPR), goals, objectives, and preliminary schedule.

Establish commissioning goals and objectives.

Establish the purpose and proposed process for commissioning the project.

Establish the individual roles of each participating commissioning team member.

Establish systems to be commissioned and preliminary acceptance criteria.

Draft Commissioning Plan

Meeting Minutes

Preliminary Owner’s Project Requirements

Commissioning Agent Task/Deliverables Description Design Phase

Project Phase/ Cx Task
Commissioning Task Description
Commissioning Deliverables

SD1 PHASE 35%

Design Submission Review
Complete a thorough commissioning review of the SD1 submittal documents and submitted criteria to establish the systems to be designed and installed in compliance with the Owner’s Project Requirements (OPR).

Documents provided to the Commissioning Agent should include, SD1 Design Narrative and other submittal documents required by PG 18-15, as well as other pertinent documents.

Design Phase Commissioning Issues Log (Incorporate Commissioning Agent review comments into Dr Checks for Project Tracking – Retain for Design Phase Cx Report)

Design Narrative
Review and Reconcile the Project Design Narrative. Narrative should incorporate OPR requirements from VA Standards and other Project Documents. Design Narrative should describe designer’s approach to the project requirements.

Design Narrative can include both the Owner’s Project Requirements (OPR) and the Basis of Design (BOD) information. Likewise separate documents can be developed and retained in the project record.

Design Phase Commissioning Issues Log (Incorporate commissioning review comments into Dr Checks for Project Tracking – Retain for Design Phase Cx Report)

Commissioning Plan
Develop the Project Design Phase Commissioning Plan that outlines process requirements, deliverables, roles, responsibilities, schedule, and milestones.

Provide a copy of the Commissioning Plan to the A/E. The A/E will incorporate the Commissioning Plan into the Design Narrative as described in PG 18-15 Project Design Phase Commissioning Plan

Duration Schedule for Commissioning Activities
Based on the Project Design Phase Commissioning Plan, prepare a duration schedule for the design phase commissioning activities required by the commissioning plan. This duration schedule should include Design Phase Activities. The Duration Schedule should provide sufficient detail to comply with the AE Team CPM scheduling requirements as outlined in PG 18-15.
Design Phase Commissioning Duration Schedule – Incorporate into Commissioning Plan
Design Review Meeting
Attend and participate in SD1 Design Review Meeting. Provide clarifications for identified Commissioning Issues as appropriate. Incorporate other comments or issues identified at Review Meeting that impact project commissioning into Commissioning Issues Log.
Revised Design Phase Commissioning Issue Log.

SD2 PHASE 65%

Design Submission Review
Complete a thorough commissioning review of the SD2 submittal documents and submitted criteria to establish the systems to be designed and installed in compliance with the OPR.

Documents provided to the Commissioning Agent should include, SD2 Design Narrative, calculations, room locations and preliminary layouts and other submittal documents required by PGA 18-15, as well as other pertinent documents.

Design Phase Commissioning Issues Log (Incorporate commissioning review comments into Dr. Checks for Project Tracking – Retain for Design Phase Cx Report)

Design Narrative
Review the updated Project Design Narrative. The Design Narrative should incorporate OPR requirements from VA Standards and other Project Documents. Design Narrative should describe designer’s approach to the project requirements.
Design Phase Commissioning Issues Log

(Incorporate review comments into Dr Checks for Project Tracking – Retain for Design Phase Cx Report)

Commissioning Plan
Update the Project Design Phase Commissioning Plan.

Provide a copy of the Commissioning Plan to the A/E. The A/E will incorporate the Commissioning Plan into the Design Narrative as described in PG 18-15 Updated Project Design Phase Commissioning Plan

Duration Schedule for Commissioning Activities
Based on the Project Design Phase Commissioning Plan, prepare a duration schedule for the Design Phase commissioning activities required by the commissioning plan. This duration schedule should include Design Phase Activities. The Duration Schedule should provide sufficient detail to comply with the AE Team CPM scheduling requirements as outlined in PG 18-15.
Design Phase Commissioning Duration Schedule – Incorporate into Commissioning Plan
Commissioning Specifications
Provide Outline Commissioning Specifications Sections utilizing the VA Master Construction Specification. Specifications shall be submitted in accordance with the requirements of PG 18-15.
Outline Commissioning Specifications

Specification Coordination Matrix for Commissioning Agent/A/E coordination.

Design Review Meeting
Attend and participate in SD2 Design Review Meeting. Provide clarifications for identified Commissioning Issues as appropriate. Incorporate other comments or issues identified at Review Meeting that impact project commissioning into Commissioning Issues Log.
Revised Design Phase Commissioning Issue Log

Note that resolution of some issues may be deferred to later design stages.

Design Phase Issue Log Resolution
Update the Commissioning Issues Log by recording resolutions to identified Commissioning Issues.
Revised Design Phase Commissioning Issue Log

DD1 PHASE 95%

Design Submission Review
Complete a thorough commissioning review of the DD1 submittal documents and submitted criteria to establish the systems to be designed and installed in compliance with the OPR.

Documents provided to the Commissioning Agent should include: DD1 Updated Design Narrative, calculations, equipment schedules, system and control schematic diagrams and appropriate schematics and other submittal documents required by PG 18-15, as well as other pertinent documents.

Design Phase Commissioning Issues Log (Incorporate review comments into Dr. Checks for Project Tracking – Retain for Design Phase Cx Report)

Design Narrative
Review the updated Project Design Narrative. The Design Narrative should be updated to reflect the evolution of the project design and note all significant deviations from prior version for ease of review and reconciliation. Design Narrative should describe designer’s approach to the project requirements.
Design Phase Commissioning Issues Log

(Incorporate review comments into Dr Checks for Project Tracking – Retain for Design Phase Cx Report)

Design Phase Controls Meeting
Meet with the Design Team and VAMC to develop HVAC and other system control strategies, sequences of operation, trending, and alarms.

The Commissioning Agent acts as a advocate for the VAMC and the facilities operations staff to assist the Design Team in developing realistic operating strategies and sequences of operations that will enable the facilities operations staff to operate the building systems to sustain the operational, energy and other systems parameters throughout the project life cycle.

Meeting Notes

Commissioning Plan
Update the Project Design Phase Commissioning Plan, including any revisions to Commissioning Team Members, Schedules and other modifications required by the progress of the project.

Prepare a Draft Construction Phase Commissioning Plan, including systems to be commissioned, an outline of construction phase roles and responsibilities, and an outline of required system documentation requirements.

Provide a copy of the updated Design Phase Commissioning Plan to the A/E. The A/E will incorporate the Commissioning Plan into the Design Narrative as described in PG 18-15 Updated Project Design Phase Commissioning Plan Draft Construction Phase Commissioning Plan

Duration Schedule for Commissioning Activities
Based on the Project Design Phase Commissioning Plan, prepare a duration schedule for the commissioning activities required by the commissioning plan. This duration schedule should include Design Phase Activities. The Duration Schedule should provide sufficient detail to comply with the AE Team CPM scheduling requirements as outlined in PG 18-15.

Based on the Draft Construction Phase Commissioning Plan, prepare a preliminary duration schedule for Construction Phase Commissioning Activities. Incorporate the draft duration schedule into the Draft Construction Phase Commissioning Plan.

Commissioning Duration Schedule – Incorporate into Commissioning Plan Draft Construction Phase Commissioning Duration Schedule – Incorporate into the Draft Construction Phase Commissioning Plan.

Commissioning Specifications
Provide Draft Commissioning Specifications Sections utilizing the VA Master Construction Specification. Specifications shall be submitted in accordance with the requirements of PG 18-15.

Provide a Specification Coordination Matrix that outlines the commissioning-related language that needs to be included in the individual equipment and technical specifications.

Draft Commissioning Specifications

Specification Coordination Matrix for Commissioning Agent/A/E coordination.

Design Review Meeting
Attend and participate in DD1 Design Review Meeting. Provide clarifications for identified Commissioning Issues as appropriate. Incorporate other comments or issues identified at Review Meeting that impact project commissioning into Commissioning Issues Log.
Revised Design Phase Commissioning Issue Log.

(Incorporate review comments into Dr. Checks for Project Tracking – Retain for Design Phase Cx Report) (Note that resolution of some issues may be deferred to later design stages.)

Design Phase Issue Log Resolution
Update the Commissioning Issues Log by recording resolutions to identified Commissioning Issues.

Revised Design Phase Commissioning Issue Log (Incorporate review comments into Dr Checks for Project Tracking – Retain for Design Phase Cx Report)

DD2 PHASE 100%

Design Submission Review
Complete a thorough review of the DD2 submittal documents and submitted criteria to establish the systems to be designed and installed in compliance with the OPR.

Documents provided to the Commissioning Agent should include: DD2 Updated Design Narrative, calculations, equipment schedules, system and control schematic diagrams, floor plans and appropriate schematics and other submittal documents required by PG 18-15, as well as other pertinent documents.

Design Phase Commissioning Issues Log (Incorporate review comments into Dr. Checks for Project Tracking – Retain for Design Phase Cx Report)

Design Narrative
Commissioning Agent to update, review and reconcile the Project Design Narrative. The Design Narrative should reflect the evolution of the project design and note all significant deviations from prior version for ease of review and reconciliation. Design Narrative should describe designer’s response to the project requirements.

Submit the updated Design Narrative to the AE team for review and comment. Incorporate review comments into the updated Design Narrative as necessary.

Design Phase Commissioning Issues Log

Commissioning Plan
Update the Project Design Phase Commissioning Plan, including any revisions to Commissioning Team Members, Schedules and other modifications required by the progress of the project.

Update the Construction Phase Commissioning Plan, including systems to be commissioned, an outline of construction phase roles and responsibilities, and an outline of required system documentation requirements.

Include the updated Commissioning Plan in the revised Design Narrative Updated Project Commissioning Plan

Commissioning Specifications
Provide Preliminary Commissioning Specifications Sections utilizing the VA Master Construction Specification. Specifications shall be submitted in accordance with the requirements of PG 18-15.

Review individual equipment and technical sections to ensure commissioning-related language has been included as provided in the Commissioning Specification Coordination Matrix.

Preliminary Commissioning Specifications

Marked up equipment and technical specification sections showing any revisions to commissioning-related language.

Specification Coordination Matrix for Commissioning Agent/A/E coordination.

Duration Schedule for Commissioning Activities
Based on the Project Design Phase Commissioning Plan, prepare an updated duration schedule for the design phase commissioning activities required by the commissioning plan. This duration schedule should include Design Phase Activities. The Duration Schedule should provide sufficient detail to comply with the AE Team CPM scheduling requirements as outlined in PG 18-15.

Based on the Project Construction Phase Commissioning Plan and the DD2 Phase design submission, update the draft Construction Phase Commissioning Duration Schedule. Incorporate the revised Construction Phase Duration Schedule into the Draft Commissioning Phase Commissioning Plan.

Design Phase Commissioning Duration Schedule – Incorporate into Design Phase Commissioning Plan Construction Phase Commissioning Duration Schedule – Incorporate into Construction Phase Commissioning Plan

Develop Preliminary Pre-Functional Checklists (PFC’s)

The Commissioning Agent will prepare Preliminary Pre-Functional Checklists (PFC) for type of system to be commissioned and distribute to all Cx Team members for review and comment. A completed PFC indicates the system, and its related equipment is ready for Systems Functional Performance Testing.

Preliminary Pre-Functional Checklists shall be included in the Construction Phase Commissioning Plan and the Commissioning Specifications.

Preliminary Pre Functional Checklists (PFC’s)

Develop Preliminary Systems Functional Performance Test (FPT’s) Procedures
Based on the systems to be commissioned and the systems shown in the DD2 submittal, the Commissioning Agent will prepare Preliminary Systems Functional Performance Test Procedures (FPT’s).

Preliminary FPTs shall be included in the Construction Phase Commissioning Plan and the Commissioning Specifications.

Preliminary Systems Functional Performance Test Procedures (FPT’s)

Design Phase Controls Meeting
Meet with the Design Team and VAMC to update HVAC and other system control strategies, sequences of operation, trending, and alarms.

The Commissioning Agent acts as an advocate for the VAMC and the facilities operations staff to assist the Design Team in developing realistic operating strategies and sequences of operations that will enable the facilities operations staff to operate the building systems to sustain the operational, energy and other systems parameters throughout the project life cycle.

Meeting Notes

Design Review Meeting
Attend and participate in DD2 Design Review Meeting. Provide clarifications for identified Commissioning Issues as appropriate. Incorporate other comments or issues identified at Review Meeting that impact project commissioning into Commissioning Issues Log.
Revised Design Phase Commissioning Issue Log.

(Incorporate review comments into Dr. Checks for Project Tracking – Retain for Design Phase Cx Report)

(Note that resolution of some issues may be deferred to later design stages.)

Design Phase Issue Log Resolution
Update the Commissioning Issues Log by recording resolutions to identified Commissioning Issues.
Revised Design Phase Commissioning Issue Log

(Incorporate review comments into Dr. Checks for Project Tracking – Retain for Design Phase Cx Report)

CD1 PHASE

Design Submission Review
Complete a thorough commissioning review of the CD1 submittal documents and submitted criteria to establish the systems to be designed and installed in compliance with the OPR.

Documents provided to the Commissioning Agent should include calculations, equipment schedules, system and control schematic diagrams, floor plans and appropriate schematics and other submittal documents required by PG 18-15, as well as other pertinent documents.

Design Phase Commissioning Issues Log (Incorporate review comments into Dr. Checks for Project Tracking – Retain for Design Phase Cx Report)

Design Narrative
Commissioning Agent to update, review and reconcile the Project Design Narrative. The Design Narrative should be updated to reflect the evolution of the project design and note all significant deviations from prior version for ease of review and reconciliation. Design Narrative should describe designer’s response to the project requirements.

Submit the updated Design Narrative to the AE team for review and comment. Incorporate review comments into the updated Design Narrative as necessary.

Revised Design Narrative

Commissioning Plan
Update the Project Design Phase Commissioning Plan, including any revisions to Commissioning Team Members, Schedules and other modifications required by the progress of the project.

Update the Construction Phase Commissioning Plan, including systems to be commissioned, an outline of construction phase roles and responsibilities, and an outline of required system documentation requirements.

Include the updated Commissioning Plan in the revised Design Narrative Updated Design Phase Project Commissioning Plan Updated Construction Phase Project Commissioning Plan

Duration Schedule for Commissioning Activities
Based on the Project Design Phase Commissioning Plan, prepare a duration schedule for the commissioning activities required by the commissioning plan. This duration schedule should include Design Phase Activities. The Duration Schedule should provide sufficient detail to comply with the AE Team CPM scheduling requirements as outlined in PG 18-15.

Based on the Project Construction Phase Commissioning Plan and the DD2 Phase design submission, update the draft Construction Phase Commissioning Duration Schedule. Incorporate the revised Construction Phase Duration Schedule into the Draft Commissioning Phase Commissioning Plan.

Design Phase Commissioning Duration Schedule – Incorporate into Design Phase Commissioning Plan Update Construction Phase Duration Schedule – Incorporate into Construction Phase Commissioning Plan

Commissioning Specifications
Provide Final Commissioning Specifications Sections utilizing the VA Master Construction Specification. Specifications shall be submitted in accordance with the requirements of PG 18-15.

Review individual equipment and technical sections to ensure commissioning-related language has been included as provided in the Commissioning Specification Coordination Matrix.

Final Project Commissioning Specifications

Marked up equipment and technical specification sections to identify any changes to commissioning-related language.

Develop Draft Pre-Functional Checklists (PFC’s)

The Commissioning Agent will update the Preliminary Pre-Functional Checklists (PFC) to Draft Pre-Functional Checklists for each type of system to be commissioned and distribute to all Cx Team members for review and comment.

Draft Pre-Functional Checklists shall be included in the Construction Phase Commissioning Plan and the Commissioning Specifications.

Draft Pre-Functional Checklists (PFC’s)

Develop Preliminary Systems Functional Performance Test (FPT’s) Procedures
Based on the systems to be commissioned and the systems shown in the CD1 submittal, the Commissioning Agent will update the Preliminary Systems Functional Performance Test Procedures (FPT’s) to become Draft Systems Functional Performance Test Procedures. .

Draft FPTs shall be included in the Construction Phase Commissioning Plan and the Commissioning Specifications.

Draft Systems Functional Performance Test Procedures (FPT’s)

Design Phase Controls Meeting
Meet with the Design Team and VAMC to update HVAC and other system control strategies, sequences of operation, trending, and alarms.

The Commissioning Agent acts as an advocate for the VAMC and the facilities operations staff to assist the Design Team in developing realistic operating strategies and sequences of operations that will enable the facilities operations staff to operate the building systems to sustain the operational, energy and other systems parameters throughout the project life cycle.

Meeting Notes

Design Review Meeting
Attend and participate in CD1 Design Review Meeting. Provide clarifications for identified Commissioning Issues as appropriate. Incorporate other comments or issues identified at Review Meeting that impact project commissioning into Commissioning Issues Log.
Revised Design Phase Commissioning Issue Log.

(Incorporate review comments into Dr. Checks for Project Tracking – Retain for Design Phase Cx Report) (Note that resolution of some issues may be deferred to later design stages.)

Design Phase Issue Log Resolution
Update the Commissioning Issues Log by recording resolutions to identified Commissioning Issues.
Revised Design Phase Commissioning Issue Log

FINAL DESIGN DOCUMENTS

Design Final Design Submission Review
Review Final Design Submission for resolution of Outstanding Commissioning Issues
Design Phase Commissioning Issues Log

(Incorporate review comments into Dr. Checks for Project Tracking – Retain for Design Phase Cx Report)

Design Narrative
Commissioning Agent to provide a Final Design Narrative to Include all modifications and/or deviations from CD1 Design Narrative. The Design Narrative should be updated to reflect the evolution of the project design and note all significant deviations from prior version for ease of review and reconciliation. Design Narrative should describe designer’s response to the project requirements. Where appropriate, provide documentation of approved deviations from design standards and reasoning for same.
Revised Design Narrative
Commissioning Plan
Update & Submit Project Construction Phase Commissioning Plan

Include the updated Commissioning Plan in the revised Design Narrative Project Construction Phase Commissioning Plan

Duration Schedule for Commissioning Activities
Based on the Project Construction Phase Commissioning Plan, prepare a duration schedule for the commissioning activities required by the commissioning plan. This duration schedule should include Construction Phase Activities. The Duration Schedule should provide sufficient detail to allow the Prime Contractor to incorporate commissioning activities into the Master Project Schedule.
Construction Phase Commissioning Duration Schedule – Incorporate into Commissioning Plan
Commissioning Specification
Provide updated Final Cx Specifications. Specifications shall be submitted in accordance with the requirements of PG 18-15.
Updated Project Commissioning Specifications
Design Phase Issue Log Resolution
Record resolutions to Cx Issues on the Design Phase Commissioning Issues Log.
Revised Design Phase Commissioning Issue Log

(Incorporate review comments into Dr Checks for Project Tracking – Retain for Design Phase Cx Report)

Design Phase Commissioning Report
Prepare Design Phase Commissioning Report to document the Design Phase commissioning process and results
Design Phase Commissioning Report

Commissioning Team Task/Deliverables Description Bid and Pre-Construction Phase

Project Phase/ Cx Task
Commissioning Task Description
Commissioning Deliverables

Pre-Bid Meeting

Attend Pre Bid Meeting; provide overall description of Commissioning Process, provide clarifications for Commissioning Issues.
Meeting Notes for PM/RE

Clarifications for Addendum if required

Pre-Construction Meeting
Attend Pre Construction Meeting and be prepared to clarify the Commissioning Process for this project (e.g., discuss commissioning representative selection).
None

Commissioning Team Task/Deliverables Description Construction Phase

Project Phase/ Cx Task
Commissioning Task Description
Commissioning Deliverables

Commissioning Kick Off Meeting (Construction Phase) [The kickoff meeting should occur within 60 days of Notice to Proceed.] Conduct a “Commissioning Kickoff Meeting” with the Construction Team Establish the purpose and process for commissioning the project.

Establish the individual roles of each participating commissioning team member.

Review the Construction Phase Commissioning Plan and Commissioning Specifications.

Review the Commissioning Documents Review the Project Schedule and discuss how commissioning activities will be incorporated into the master schedule.

Review Draft PFC and FPT; identify pre-requisites for functional testing.

ATTENDEES:

Commissioning Agent, A/E Design Team Representatives, Contractor’s Commissioning Representative, Subcontractor’s Commissioning Representatives, VA RE.

Meeting Minutes

Revised Project Commissioning Plan (Include Names/Contact Information for selected Commissioning Team Members)

Duration Schedule for Commissioning Activities
Based on the Construction Phase Commissioning Plan, prepare a duration schedule for the commissioning activities required by the commissioning plan. This duration schedule should be incorporated into the contractor’s project schedule to track all commissioning activities of the commissioning team.
Commissioning Duration Schedule

(Schedule shall be periodically updated to reflect changes in the project schedule and/or scope.)

Submittal & Shop Drawing Review

Review all pertinent project shop drawings necessary to support the Commissioning Process. Review of the shop drawings is for the purpose of developing appropriate Pre-Functional Checklists and Systems Functional Performance Test Procedures. Submittals & Shop drawings shall be reviewed for commissionability, maintainability and for compliance to the Construction Documents.

Note any issues identified in the Shop Drawing Review that might compromise the final commissioned system on the ‘Commissioning Review Log’ and submit comment to the Design Team and the RE contemporaneously with the A/E review for resolution.

Comments shall be submitted in accordance with the contractual submittal review time. Comments shall be provided to the Design Team no less than 7 days prior to the Submittal Review Due Date provided that the Cx Agent has no less than 7 days to review the submittals.

ANY ISSUES IDENTIFIED IN THE SUBMITTAL REVIEW THAT MIGHT REQUIRE A CONTRACT CHANGE BUT IS NECESSARY TO MEET DESIGN INTENT SHOULD BE SPECIFICALLY REFERRED TO THE RE.

Shop Drawing Cx Review List

Shop Drawing Review Comments

Construction Phase Commissioning Plan
Based on the work completed in the items above, the Construction Phase Commissioning Plan for the project shall be periodically reviewed with the Commissioning Team and updated to reflect changes in project equipment, sequences of operations, scope or schedule and with project personnel.
Revised Project Commissioning Plan

Commissioning Construction Observations

During the course of construction, the Commissioning Agent will visit the site to observe the progress of construction with respect to the systems being commissioned. The focus of the observations will verify that systems being installed comply with the Construction Documents and can be successfully configured, operated and maintained.

In addition, site observations visits will be scheduled to include.

Witnessing factory testing and/or contractor equipment/system start up activities.

Verification of Completed Pre-Functional Checklists Verification that the Contractor and his subcontractors are completing and documenting Pre-Test procedures required by the specifications.

Clarification and technical support for understanding and resolving Commissioning Issues.

Site Observation Reports

Updated Commissioning Issues Log

Commissioning Team Meetings

The Commissioning Agent will hold regular commissioning team meetings to review progress of the commissioning effort and reinforce individual responsibilities. The team will review schedule, construction sequence, and completed work (PFC, PFT and FPT’s) and outstanding issues on the Commissioning Issues Log.

Commissioning Team Meetings may be held at the jobsite or by teleconference depending upon the status of construction. While it is imperative that many of the Commissioning Team Meetings be held in person, during early construction phases, some meetings may be more cost effectively conducted remotely. Scheduling and location of meetings shall occur by consultation between the Commissioning Agent and the VA-RE.

The Prime Contractor’s scheduler should attend approximately every other Commissioning Team Meeting to review the master schedule and any changes that will affect commissioning activities.

Commissioning Meeting Agenda and Minutes Updated Commissioning Issues Log

Develop Final Pre-Functional Checklists (PFC’s)

The Commissioning Agent will prepare Pre-Final Pre-Functional Checklists (PFC) for the project and distribute to all Cx Team members for review and comment. The Commissioning Agent will incorporate review comments and prepare Final PFCs.

An executed PFC submitted by the Prime Contractor indicates the system and its related equipment is ready for Systems Functional Performance Testing.

The requirements for Pre-Functional Checklists shall be coordinated with the startup requirements specified for each commissioned system. The PFC’s shall be constructed to leverage the specified contractor and vendor start activities to avoid unnecessary duplication.

Pre-Functional Checklists (PFC’s)

Final Systems Functional Performance Test (FPT’s) Procedures
Based on construction documents and approved submittals, the Commissioning Agent will prepare Pre-Final Systems Functional Performance Test Procedures (FPT’s) for systems to be commissioned.

Completed Final FPT’s will be distributed to all appropriate members of the Commissioning Team for review and comment.

Final FPT’s will be issued once comments are reviewed and incorporated into final documents as appropriate.

Pre-Final and Final Systems Functional Performance Test Procedures (FPT’s)

Review Operations & Maintenance Manuals

The Commissioning Agent shall review Operations and Maintenance Manuals submitted by contractors for general conformance with specifications and VA’s requirements, including:

If provided with the manuals, Review Preventive Maintenance Schedules provided as part of the O&M Manuals for completeness. Verify that data is provided in a manner consistent with VA process for managing Preventive Maintenance tasks.

Review of O&M Manuals will include a review of system and component warranties to confirm conformance with contract requirements and adequate documentation of warranty contact information and VA obligations.

Review of O&M Manuals shall be completed in accordance with the Submittal Review schedule requirements.

Updated Commissioning Issues Log

Review Contractor Equipment Startup Checklists, TAB Reports and PFC’s

The Commissioning Agent will review all contractor prepared Equipment Startup Checklists, TAB Reports (including “pencil” daily test results) and PFC’s to confirm that the systems have been subject to appropriate Quality Control and Start Up procedures prior to initiation of Functional Performance Testing. Incomplete work, inadequate preparation and deficiencies will note noted and tracked on the Commissioning Issues Log.
Commissioning Issues Log
TAB Verification
The Commissioning Agent shall work with the TAB Contractor to verify that all Testing and Balancing work is conducted in strict accordance with the specified Procedural Standards for Testing, Adjusting and Balancing by either NEBB or AABC. The Commissioning Agent shall execute the following tasks:

Review the TAB Agenda provided by the TAB Contractor to verify that it is…