This document is a Combined Synopsis/Solicitation for a firm-fixed price contract for chemical treatment services related to the Cerro Montoso Cheatgrass project managed by the Bureau of Land Management Taos Field Office in New Mexico.

The solicitation is set-aside for small businesses under NAICS code 115310 (Support Activities for Forestry - Fuels Management Services) with a $34 million size standard. The contractor will be required to apply the herbicide Plateau (Imazapic) at a rate of 4 oz/acre across approximately 330 acres. Key deliverables include an on-site meeting with BLM prior to treatment, final approval, and an on-site meeting before any chemical application. The period of performance is estimated to be from October 1, 2024 to October 31, 2024. Quotes are due by 4:00 pm MT on September 18, 2024 and must be submitted by email to the contracting officer. Contractors must be registered in SAM and provide their UEI and CAGE code with their quote.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CERRO MONTOSO CHEATGRASS, BUREAU OF LAND MANAGEMENT, TAOS

FIELD OFFICE, TAOS COUNTY, NEW MEXICO

This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in Subpart 12.6, as supplemented with additional information included in this notice. This announcement and attachments constitute the only solicitation; quotes are being requested and a written solicitation will not be issued. Consider this solicitation (140L3724Q0157) as a Request for Quotes (RFQ). This solicitation documents incorporate provisions and clauses in effect through Federal acquisition Circular 2019-03. This solicitation is set-aside for small business. NAICS 115310 – Support Activities for Forestry

– Fuels Management Services. The small business size standard is $34.0 million. Product Service Code F014 – Natural Resources / Conservation – Tree Thinning. The resulting purchase order will be a firm-fixed price type contract with a single lump sum payment. (SEE ATTACHMENTS FOR COMPLETE

STATEMENT OF WORK, MAPS, WAGE DETERMINATIONS, AND CLAUSES / PROVISIONS.)

Approximately 330 Acres x $__________ = $________________

TASKS/TECHNICAL REQUIREMENTS

The following tasks for which the contractor shall use in the treatment of the Cerro Montoso Cheatgrass Project (see attached maps):

Chemical Application

• An on-site meeting with BLM personnel and on- site contractor personnel shall be held prior to the implementation of any chemical treatments.

• Apply the herbicide, Plateau (Imazapic) at a rate of 4oz/acre a pre-emergent.

Since, this herbicide is being used as a pre-emergent, the entire 330 acres must be covered at the 4 oz/acre.

• Application of the herbicide CANNOT cause any ground disturbance.

• If original application technique is not by hand, then, a follow up application by hand, must occur to get any areas that do not have herbicide applied to them.

• Contractor must follow all manufacture labels for this chemical.

• Contractor must meet all requirements to apply herbicide on federal and New Mexico state lands.

DELIVERABLES

• On Site Meeting with BLM and Contractor

• Final Approval

• On Site Meeting before any Chemical Application is to Begin

PLACE OF PEROFRMANCE

The project lies north of Taos. All project boundaries reside within BLM and New Mexico state lands. Grid Coordinates are as follows: Township 29N, Range 11E, Sections, 02, 03, 04, 09 and 10.

• The Contractor shall NOT block roadways.

• The Contracting Official shall at any time place certain work restrictions as necessary to the project, for the safety of general public.

• Before any equipment is brought into the public land project area it shall be washed to remove non-native seeds or any other foreign object debris.

• Cleaning shall consist of the removal all dirt, grease, debris, and materials that shall harbor noxious weeds and their seeds. Cleaning shall occur away from the project site. Equipment includes: Trucks, UTV’s, Trailers and Hand-tools

PERIOD OF PERFORMANCE

Estimated start date is October 1, 2024, with performance time of completion due by October 31, 2024.

SPECIAL CONSIDERATIONS MAPS

BLM Maps shall show project boundaries and treatment acreage. Geo-referenced PDF Avenza Maps of treatment polygons shall be made available by the BLM.

PROJECT SITE ACCESS

The contractor shall use existing roads and/or access routes that have been previously approved for vehicle use by the BLM. All access into the project shall be by existing roads or by foot. No vehicle access shall be allowed off established two track roads.

• Closest amenities (fuel, food and lodging) are approximately 30 miles.

• Road Conditions may become difficult in wet conditions.

BOUNDARIES OF PROJECT AREA

Project area boundaries shall be provided as geo-referenced PDF maps for use in Avenza Maps. Contractor may flag project area boundaries as needed (flagging not provided by BLM).

The Government will award a purchase order resulting from this solicitation to the responsible offeror whose offer is conforming to the solicitation and provides the best value to the Government on a Lowest Price Technically Acceptable.

Quotes are due Wednesday, September 18, 2024, by 4:00 p.m. Mountain Time. Contractors submit quotes by email to awhetham@blm.gov.

Note: Any contractor to submit an acceptable quote or be awarded a government contract must be registered and active in the System for Award Management (SAM). Contractors must register at www.sam.gov.

• Contractor's must submit their Unique Entity ID (UEI) and CAGE code with their quote.

UEI ______________________

CAGE ____________________

For further information about this requirement, offerors should contact Audrey Whetham at awhetham@blm.gov.

The provisions and clauses attached apply to this solicitation.

Contractors Signature _______________

Date: _______________

TASKS/TECHNICAL REQUIREMENTS

File details come from the government source that posted it. Updated .