SECTION 03 30 53
MISCELLANEOUS CAST-IN-PLACE CONCRETE
05/14
PART 1 GENERAL
1.1 SUMMARY
Perform all work in accordance withACI 318MACI 318.
1.2 UNIT PRICES
1.2.1 Concrete Payment
Payment will cover all costs associated with manufacturing, furnishing, delivering, placing, finishing, and curing of concrete for the various items of the schedule, including the cost of all formwork. Payment for concrete, for which payment is made as a lump sum, is to be included in this unit price payment item. Payment for grout, preformed expansion joints, field-molded sealants, waterstops, reinforcing steel bars or wire reinforcement is to be included in this unit price payment item.
1.2.2 Measurement
Concrete will be measured for payment on the basis of the actual volume of concrete within the pay lines of the structures as indicated. Measurement of concrete placed against the sides of any excavation without the use of intervening forms will be made only within the pay lines of the structure.
No deductions will be made for rounded or beveled edge, for space occupied by metal work, for electrical conduits or timber, or for voids or embedded items that are either less than5 cubic feet in volume or 1 square foot in cross section.
1.2.3 Unit of Measure
Unit of measure: cubicyard.
1.3 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONCRETE INSTITUTE (ACI)
ACI 117 (2010; Errata 2011) Specifications for
Tolerances for Concrete Construction and Materials and Commentary
ACI 301 (2016) Specifications for Structural
Concrete
ACI 301M (2016) Metric Specifications for Structural Concrete
ACI 302.1R (2015) Guide for Concrete Floor and Slab Construction
ACI 304R (2000; R 2009) Guide for Measuring, Mixing, Transporting, and Placing Concrete
ACI 305R (2010) Guide to Hot Weather Concreting
ACI 306R (2016) Guide to Cold Weather Concreting
ACI 318 (2014; Errata 1-2 2014; Errata 3-5 2015;
Errata 6 2016; Errata 7-9 2017) Building Code Requirements for Structural Concrete (ACI 318-14) and Commentary (ACI 318R-14)
ACI 318M (2014; ERTA 2015) Building Code
Requirements for Structural Concrete & Commentary
ACI 347R (2014; Errata 1 2017) Guide to Formwork for Concrete
ACI SP-66 (2004) ACI Detailing Manual
ASTM INTERNATIONAL (ASTM)
ASTM A615/A615M (2020) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
ASTM A1064/A1064M (2017) Standard Specification for
Carbon-Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for
ASTM C31/C31M (2019a) Standard Practice for Making and
Curing Concrete Test Specimens in the Field
ASTM C33/C33M (2018) Standard Specification for Concrete Aggregates
ASTM C39/C39M (2020) Standard Test Method for
Compressive Strength of Cylindrical Concrete Specimens
ASTM C94/C94M (2020) Standard Specification for
Ready-Mixed Concrete
ASTM C143/C143M (2015) Standard Test Method for Slump of Hydraulic-Cement Concrete
ASTM C150/C150M (2020) Standard Specification for Portland
Cement
ASTM C172/C172M (2017) Standard Practice for Sampling Freshly Mixed Concrete
ASTM C173/C173M (2016) Standard Test Method for Air Content of Freshly Mixed Concrete by the Volumetric Method
ASTM C231/C231M (2017a) Standard Test Method for Air
Pressure Method
ASTM C260/C260M (2010a; R 2016) Standard Specification for
Air-Entraining Admixtures for Concrete
ASTM C309 (2011) Standard Specification for Liquid Membrane-Forming Compounds for Curing
ASTM C494/C494M (2019) Standard Specification for Chemical
Admixtures for Concrete
ASTM C595/C595M (2020) Standard Specification for Blended Hydraulic Cements
ASTM C618 (2019) Standard Specification for Coal Fly
Ash and Raw or Calcined Natural Pozzolan for Use in Concrete
ASTM C685/C685M (2017) Standard Specification for Concrete
Made by Volumetric Batching and Continuous Mixing
ASTM C920 (2018) Standard Specification for
Elastomeric Joint Sealants
ASTM C989/C989M (2018a) Standard Specification for Slag Cement for Use in Concrete and Mortars
ASTM C1064/C1064M (2017) Standard Test Method for
Temperature of Freshly Mixed
ASTM C1157/C1157M (2020) Standard Performance Specification for Hydraulic Cement
ASTM C1260 (2014) Standard Test Method for Potential Alkali Reactivity of Aggregates (Mortar-Bar Method)
ASTM C1567 (2013) Standard Test Method for Potential
Alkali-Silica Reactivity of Combinations of Cementitious Materials and Aggregate (Accelerated Mortar-Bar Method)
ASTM C1602/C1602M (2018) Standard Specification for Mixing
Water Used in Production of Hydraulic Cement Concrete
ASTM D75/D75M (2019) Standard Practice for Sampling
ASTM D98 (2015) Calcium Chloride
ASTM D412 (2016) Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers - Tension
ASTM D471 (2016a) Standard Test Method for Rubber
Property - Effect of Liquids
ASTM D1752 (2018) Standard Specification for Preformed Sponge Rubber, Cork and Recycled PVC Expansion Joint Fillers for Concrete Paving and Structural Construction
ASTM E96/E96M (2016) Standard Test Methods for Water
Vapor Transmission of Materials
ASTM E1155 (2014) Standard Test Method for Determining Floor Flatness and Floor Levelness Numbers
ASTM E1155M (2014) Standard Test Method for
Levelness Numbers (Metric)
ASTM E1643 (2018a) Standard Practice for Selection, Design, Installation, and Inspection of Water Vapor Retarders Used in Contact with Earth or Granular Fill Under Concrete Slabs
ASTM E1745 (2017) Standard Specification for Water
Vapor Retarders Used in Contact with Soil or Granular Fill under Concrete Slabs
ASTM E1993/E1993M (1998; R 2020) Standard Specification for
Bituminous Water Vapor Retarders Used in Contact with Soil or Granular Fill Under Concrete Slabs
U.S. ARMY CORPS OF ENGINEERS (USACE)
COE CRD-C 513 (1974) Corps of Engineers Specifications for Rubber Waterstops
COE CRD-C 572 (1974) Corps of Engineers Specifications for Polyvinylchloride Waterstops
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 247 Comprehensive Procurement Guideline for
Products Containing Recovered Materials
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for [Contractor Quality Control approval.] [information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Installation Drawings; G
SD-03 Product Data
Air-Entraining Admixture Accelerating Admixture Water-Reducing or Retarding Admixture Curing Materials Expansion Joint Filler Strips, Premolded Joint Sealants - Field Molded Sealants Waterstops Chemical Floor Hardener Batching and Mixing Equipment Conveying and Placing Concrete Formwork Mix Design Data; G Ready-Mix Concrete Curing Compound Mechanical Reinforcing Bar Connectors
SD-06 Test Reports
Aggregates Concrete Mixture Proportions; G Measurement of Floor Tolerances Compressive Strength Testing; G Slump; G Air Content Water
SD-07 Certificates
Cementitious Materials Pozzolan CPG for recycled materials or appropriate Waiver Form
Delivery Tickets
SD-08 Manufacturer's Instructions
Chemical Floor Hardener Curing Compound
1.5 QUALITY ASSURANCE
Indicate specific locations of Concrete Placement, Forms, Steel Reinforcement, Accessories, Expansion Joints, Construction Joints, Contraction Joints, Control Joints on installation drawings and include, but not be limited to, square feet of concrete placements, thicknesses and widths, plan dimensions, and arrangement of cast-in-place concrete section.
PART 2 PRODUCTS
2.1 SYSTEM DESCRIPTION
The Government retains the option to sample and test aggregates and concrete to determine compliance with the specifications. Provide facilities and labor as may be necessary to assist the Government in procurement of representative test samples. Obtain samples of aggregates at the point of batching in accordance with ASTM D75/D75M. Sample concrete in accordance with ASTM C172/C172M. Determine slump and air content in accordance with ASTM C143/C143M and ASTM C231/C231M, respectively, when cylinders are molded. Prepare, cure, and transport compression test specimens in accordance with ASTM C31/C31M. Test compression test specimens in accordance with ASTM C39/C39M. Take samples for strength tests not less than once each shift in which concrete is produced [from each strength of concrete required]. Provide a minimum of five specimens from each sample; two to be tested at 28 days for acceptance, two will be tested at 7 days for information and one held in reserve.
2.1.1 Strength
Acceptance test results are the average strengths of two specimens tested at 28 days. The strength of the concrete is considered satisfactory so long as the average of three consecutive acceptance test results equal or exceed the specified compressive strength, f'c, but not more than 20 percent, and no individual acceptance test result falls below f'c by more than500 psi.
2.1.2 Construction Tolerances
Apply a Class "C" finish to all surfaces except those specified to receive a Class "D" finish. Apply a Class "D" finish to all post-construction surfaces which will be permanently concealed. Surface requirements for the classes of finish required are as specified in ACI 117.
2.1.3 Concrete Mixture Proportions
Concrete mixture proportions are the responsibility of the Contractor.
Mixture proportions must include the dry weights of cementitious material(s); the nominal maximum size of the coarse aggregate; the specific gravities, absorptions, and saturated surface-dry weights of fine and coarse aggregates; the quantities, types, and names of admixtures; and quantity of water per cubic meter yard of concrete. Provide materials included in the mixture proportions of the same type and from the same source as will be used on the project. The specified compressive strength f'c is 4,000 psi at 28 days. The maximum nominal size coarse aggregate is 3/4 inch, in accordance with ACI 304R. The air content must be between 4.5 and 7.5 percent with a slump between2 and 5 inches. The maximum water-cementitious material ratio is 0.50. Submit the applicable test reports and mixture proportions that will produce concrete of the quality required, ten days prior to placement of concrete.
2.2 MATERIALS
Submit manufacturer's literature from suppliers which demonstrates compliance with applicable specifications for the specified materials.
2.2.1 Cementitious Materials
Submit Manufacturer's certificates of compliance, accompanied by mill test reports, attesting that the concrete materials meet the requirements of the specifications in accordance with the Special Clause "CERTIFICATES OF COMPLIANCE". Also, certificates for all material conforming to EPA's Comprehensive Procurement Guidelines (CPG), in accordance with 40 CFR 247.
Provide cementitious materials that conform to the appropriate specifications listed:
2.2.1.1 Portland Cement
ASTM C150/C150M, Type [I][II][III][V], [low alkali] [including false set requirements] with tri-calcium aluminates (C3A) content less than 10 percent and a maximum cement-alkali content of 0.80 percent Na2Oe (sodium oxide) equivalent.
2.2.1.2 Blended Hydraulic Cement
Provide blended cement conforming to ASTM C595/C595M and ASTM C1157/C1157M, Type IP or IS, including the optional requirement for mortar expansion [and sulfate soundness] and consist of a mixture of ASTM C150/C150M Type I, or Type II cement and a complementary cementing material. The slag added to the Type IS blend must be ASTM C989/C989M ground granulated blast-furnace slag. The pozzolan added to the Type IP blend must be ASTM C618 Class F, interground with the cement clinker. Provide the manufacturer's written statement that the amount of pozzolan in the finished cement will not vary more than plus or minus 5 mass percent of the finished cement from lot-to-lot or within a lot. Do not change the percentage and type of mineral admixture used in the blend from that submitted for the aggregate evaluation and mixture proportioning.
2.2.1.3 Pozzolan
Provide pozzolan that conforms to ASTM C618, Class F, including requirements of Tables 1A and 2A.
2.2.2 Aggregates
For fine and coarse aggregates meet the quality and grading requirements of ASTM C33/C33M[ and test and evaluate for alkali-aggregate reactivity in accordance with ASTM C1260. Perform evaluation of fine and coarse aggregates separately and in combination, matching the proposed mix design proportioning. All results of the separate and combination testing must have a measured expansion less than 0.08 percent at 28 days after casting.
If the test data indicates an expansion of 0.08 percent or greater, reject the aggregate(s) or perform additional testing using ASTM C1260 and ASTM C1567. Perform the additional testing using ASTM C1260 and ASTM C1567 using the low alkali portland cement in combination with ground granulated blast furnace (GGBF) slag, or Class F fly ash. Use GGBF slag in the range of 40 to 50 percent of the total cementitious material by mass. Use Class F fly ash in the range of 25 to 40 percent of the total cementitious material by mass]. Submit certificates of compliance and test reports for aggregates showing the material(s) meets the quality and grading requirements of the specifications under which it is furnished.
2.2.3 Admixtures
Provide admixtures, when required or approved, in compliance with the appropriate specification listed. Retest chemical admixtures that have been in storage at the project site, for longer than 6 months or that have been subjected to freezing, at the expense of the Contractor at the request of the Contracting Officer and will be rejected if test results are not satisfactory.
2.2.3.1 Air-Entraining Admixture
Provide air-entraining admixture that meets the requirements of
ASTM C260/C260M.
2.2.3.2 Accelerating Admixture
Provide calcium chloride meeting the requirements of ASTM D98. Other accelerators must meet the requirements of ASTM C494/C494M, Type C or E.
2.2.3.3 Water-Reducing or Retarding Admixture
Provide water-reducing or retarding admixture meeting the requirements of ASTM C494/C494M, Type A, B, or D.
2.2.4 Water
Mixing and curing water in compliance with the requirements of ASTM C1602/C1602M; free of injurious amounts of oil, acid, salt, or alkali. Submit test report showing water complies with ASTM C1602/C1602M.
2.2.5 Reinforcing Steel
Provide reinforcing bars conforming to the requirements of ASTM A615/A615M, Grade 60, deformed. Provide welded steel wire reinforcement conforming to the requirements of ASTM A1064/A1064M. Detail reinforcement not indicated in accordance with ACI 301M ACI 301 and ACI SP-66. Provide mechanical reinforcing bar connectors in accordance with ACI 301M ACI 301 and provide 125 percent minimum yield strength of the reinforcement bar.
2.2.6 Formwork
Design and engineer the formwork as well as its construction in accordance with ACI 301M ACI 301 Section 2 and 5 and ACI 347R. Fabricate of wood, steel, or other approved material. Submit formwork design prior to the first concrete placement.
2.2.7 Form Coatings
Provide form coating in accordance with ACI 301M ACI 301.
2.2.8 Curing Materials
Provide curing materials in accordance with ACI 301M ACI 301, Section 5.
2.3 READY-MIX CONCRETE
Provide ready-mix concrete with mix design data conforming to ACI 301M
ACI 301 Part 2. Submit delivery tickets in accordance with ASTM C94/C94M for each ready-mix concrete delivery, include the following additional information: .
a. Type and brand cement
b. Cement content in 94-pound bags per cubic meter yard of concrete
c. Maximum size of aggregate
d. Amount and brand name of admixture
e. Total water content expressed by water cementitious material ratio
2.4 ACCESSORIES
2.4.1 Waterstops
2.4.1.1 PVC Waterstop
Polyvinylchloride waterstops conforming to COE CRD-C 572.
2.4.1.2 Rubber Waterstop
Rubber waterstops conforming to COE CRD-C 513.
2.4.1.3 Thermoplastic Elastomeric Rubber Waterstop
Thermoplastic elastomeric rubber waterstops conforming to ASTM D471.
2.4.1.4 Hydrophilic Waterstop
Swellable strip type compound of polymer modified chloroprene rubber that swells upon contact with water conforming to ASTM D412 as follows: Tensile strength420 psi minimum; ultimate elongation 600 percent minimum. Minimum hardness of 50 on the type A durometer and the volumetric expansion ratio in distilled water at70 degrees F; 3 to 1 minimum.
PART 3 EXECUTION
3.1 PREPARATION
Prepare construction joints to expose coarse aggregate. The surface must be clean, damp, and free of laitance. Construct ramps and walkways, as necessary, to allow safe and expeditious access for concrete and workmen.
Remove snow, ice, standing or flowing water, loose particles, debris, and foreign matter. Satisfactorily compact earth foundations. Make spare vibrators available. Placement cannot begin until the entire preparation has been accepted by the Government.
3.1.1 Embedded Items
Secure reinforcement in place after joints, anchors, and other embedded items have been positioned. Arrange internal ties so that when the forms are removed the metal part of the tie is not less than2 inches from concrete surfaces permanently exposed to view or exposed to water on the finished structures. Prepare embedded items so they are be free of oil and other foreign matters such as loose coatings or rust, paint, and scale.
The embedding of wood in concrete is permitted only when specifically authorized or directed. Provide all equipment needed to place, consolidate, protect, and cure the concrete at the placement site and in good operating condition.
3.1.2 Formwork Installation
Forms must be properly aligned, adequately supported, and mortar-tight.
Provide smooth form surfaces, free from irregularities, dents, sags, or holes when used for permanently exposed faces. Chamfer all exposed joints and edges , unless otherwise indicated.
3.1.3 Production of Concrete
3.1.3.1 Ready-Mixed Concrete
Provide ready-mixed concrete conforming to ASTM C94/C94M except as otherwise specified.
3.1.3.2 Concrete Made by Volumetric Batching and Continuous Mixing
Conform to ASTM C685/C685M.
3.1.3.3 Batching and Mixing Equipment
The option of using an on-site batching and mixing facility is available.
The facility must provide sufficient batching and mixing equipment capacity to prevent cold joints. Submit the method of measuring materials, batching operation, and mixer for review, and manufacturer's data for batching and mixing equipment demonstrating compliance with the applicable specifications.
3.2 CONVEYING AND PLACING CONCRETE
Convey and place concrete in accordance with ACI 301M ACI 301, Section 5.
3.2.1 Cold-Weather Requirements
Place concrete in cold weather in accordance with ACI 306R
3.2.2 Hot-Weather Requirements
Place concrete in hot weather in accordance with ACI 305R
3.3 FINISHING
3.3.1 Finishing Formed Surfaces
Remove all fins and loose materials , and surface defects including filling of tie holes. Repair all honeycomb areas and other defects. Remove all unsound concrete from areas to be repaired. Ream or chip surface defects greater than1/2 inch in diameter and holes left by removal of tie rods in all surfaces not to receive additional concrete and fill with dry-pack mortar. Brush-coat the prepared area with an approved epoxy resin or latex bonding compound or with a neat cement grout after dampening and filling with mortar or concrete. Use a blend of portland cement and white cement in mortar or concrete for repairs to all surfaces permanently exposed to view shall be so that the final color when cured is the same as adjacent concrete.
3.4 CURING AND PROTECTION
Cure and protect in accordance with ACI 301M ACI 301, Section 5.
3.5 FORM WORK
Provide form work in accordance with ACI 301M ACI 301, Section 2 and Section 5.
3.5.1 Removal of Forms
Remove forms in accordance with ACI 301M ACI 301, Section 2.
3.6 STEEL REINFORCING
Reinforcement must be free from loose, flaky rust and scale, and free from oil, grease, or other coating which might destroy or reduce the reinforcement's bond with the concrete.
3.6.1 Fabrication
Shop fabricate steel reinforcement in accordance with ACI 318 and ACI SP-66.
Provide shop details and bending in accordance with ACI 318 and ACI SP-66.
3.6.2 Splicing
Perform splices in accordance with ACI 318 and ACI SP-66.
3.6.3 Supports
Secure reinforcement in place by the use of metal or concrete supports, spacers, or ties.
3.7 EMBEDDED ITEMS
Before placing concrete, take care to determine that all embedded items are firmly and securely fastened in place. Provide embedded items free of oil and other foreign matter, such as loose coatings of rust, paint and scale.
Embedding of wood in concrete is permitted only when specifically authorized or directed.
3.8 TESTING AND INSPECTING
Report the results of all tests and inspections conducted at the project site informally at the end of each shift. Submit written reports weekly.
Deliver within three days after the end of each weekly reporting period.
See Section 01 45 00.00 10 QUALITY CONTROL.
3.8.1 Field Testing Technicians
The individuals who sample and test concrete must have demonstrated a knowledge and ability to perform the necessary test procedures equivalent to the ACI minimum guidelines for certification of Concrete Field Testing
Technicians, Grade I.
3.8.2 Preparations for Placing
Inspect foundation or construction joints, forms, and embedded items in sufficient time prior to each concrete placement to certify that it is ready to receive concrete.
3.8.3 Sampling and Testing
a. Obtain samples and test concrete for quality control during placement.
Sample fresh concrete for testing in accordance with ASTM C172/C172M.
Make six test cylinders.
b. Test concrete for compressive strength at 7 and 28 days for each design mix and for every100 cubic yards of concrete. Test two cylinders at 7 days; two cylinders at 28 days; and hold two cylinders in reserve.
Conform test specimens to ASTM C31/C31M. Perform compressive strength testing conforming to ASTM C39/C39M.
c. Test slump at the site of discharge for each design mix in accordance with ASTM C143/C143M. Check slump once during each shift that concrete is produced for each strength of concrete required.
d. Test air content for air-entrained concrete in accordance with
ASTM C231/C231M. Test concrete using lightweight or extremely porous aggregates in accordance with ASTM C173/C173M. Check air content at least once during each shift that concrete is placed for each strength of concrete required.
e. Determine temperature of concrete at time of placement in accordance with ASTM C1064/C1064M. Check concrete temperature at least once during each shift that concrete is placed for each strength of concrete required.
3.8.4 Action Required
3.8.4.1 Placing
Do not begin placement until the availability of an adequate number of acceptable vibrators, which are in working order and have competent operators, has been verified. Discontinue placing if any lift is inadequately consolidated.
3.8.4.2 Air Content
Whenever an air content test result is outside the specification limits, adjust the dosage of the air-entrainment admixture prior to delivery of concrete to forms.
3.8.4.3 Slump
Whenever a slump test result is outside the specification limits, adjust the batch weights of water and fine aggregate prior to delivery of concrete to the forms. Make the adjustments so that the water-cementitious material ratio does not exceed that specified in the submitted concrete mixture proportion and the required concrete strength is still met.
-- End of Section --
SECTION 05 30 00
STEEL DECKS
05/15
1.1 REFERENCES
AMERICAN IRON AND STEEL INSTITUTE (AISI)
AISI D100 (2017) Cold-Formed Steel Design Manual
AMERICAN WELDING SOCIETY (AWS)
AWS D1.1/D1.1M (2020) Structural Welding Code - Steel
AWS D1.3/D1.3M (2018) Structural Welding Code - Sheet Steel
ASTM A36/A36M (2019) Standard Specification for Carbon
Structural Steel
ASTM A123/A123M (2017) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
ASTM A653/A653M (2020) Standard Specification for Steel
Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process
ASTM A780/A780M (2009; R 2015) Standard Practice for
Repair of Damaged and Uncoated Areas of Hot-Dip Galvanized Coatings
ASTM A792/A792M (2010; R 2015) Standard Specification for
Steel Sheet, 55% Aluminum-Zinc Alloy-Coated by the Hot-Dip Process
ASTM A1008/A1008M (2018) Standard Specification for Steel, Sheet, Cold-Rolled, Carbon, Structural, High-Strength Low-Alloy, High-Strength Low-Alloy with Improved Formability, Solution Hardened, and Bake Hardenable
ASTM C423 (2009a) Sound Absorption and Sound
Absorption Coefficients by the Reverberation Room Method
ASTM D746 (2014) Standard Test Method for Brittleness Temperature of Plastics and Elastomers by Impact
ASTM D1056 (2014) Standard Specification for Flexible
Cellular Materials - Sponge or Expanded Rubber
ASTM D1149 (2007; R 2012) Standard Test Method for
Rubber Deterioration - Surface Ozone Cracking in a Chamber
ASTM E84 (2020) Standard Test Method for Surface
Burning Characteristics of Building Materials
FM GLOBAL (FM)
FM APP GUIDE (updated on-line) Approval Guide http://www.approvalguide.com/
FM DS 1-28R (1998) Data Sheet: Roof Systems
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2020; ERTA 20-1 2020; ERTA 20-2 2020; TIA
20-1; TIA 20-2; TIA 20-3; TIA 20-4)
National Electrical Code
SOCIETY FOR PROTECTIVE COATINGS (SSPC)
SSPC Paint 20 (2019) Zinc-Rich Primers (Type I, Inorganic, and Type II, Organic)
STEEL DECK INSTITUTE (SDI)
ANSI/SDI C (2017) Standard for Composite Steel Floor
Deck - Slabs
ANSI/SDI NC (2017) Standard for Non-Composite Steel Floor Deck
ANSI/SDI QA/QC (2017) Standard for Quality Control and
Quality Assurance for Installation of Steel Deck
ANSI/SDI RD (2017) Standard for Steel Roof Deck
SDI DDM04 (2015; Errata 1-3 2016; Add 1 2015; Add 2
20162006) Diaphragm Design Manual; 4th Edition
SDI DDP (1987; R 2000) Deck Damage and Penetrations
SDI MOC3 (2016) Manual of Construction with Steel
Deck (3rd Edition)
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 3-301-01 (2019) Structural Engineering
29 CFR 1926 Safety and Health Regulations for
UNDERWRITERS LABORATORIES (UL)
UL 209 (2011; Reprint May 2016) UL Standard for
Safety Cellular Metal Floor Raceways and Fittings
UL 580 (2006; Reprint Mar 2019) UL Standard for
Safety Tests for Uplift Resistance of Roof Assemblies
UL Fire Resistance (2014) Fire Resistance Directory
1.2 SUBMITTALS
submittals not having a "G" designation are [for Contractor QC approval.][for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29, SUSTAINABITY
Fabrication Drawings; G
SD-03 Product Data
Accessories
Deck Units
Galvanizing Repair Paint
[ Mechanical Fasteners
Touch-Up Paint
Sound Absorbing Materials
Welding Equipment
Welding Rods and Accessories
Recycled Content of Steel Products; S
SD-04 Samples
Metal Roof Deck Units
Cellular Metal Floor Deck Units
Flexible Closure Strips
Acoustical Material
SD-05 Design Data
Deck Units; G
Powder-Actuated Tool Operator
Welder Qualifications
Welding Procedures
Fire Safety
Wind Storm Resistance
Manufacturer's Certificate
Stud Manufacture's Certification
Stud Manufacture's Test Reports
1.3 QUALITY ASSURANCE
1.3.1 Deck Units
Furnish deck units and accessory products from a manufacturer regularly engaged in manufacture of steel decking. Provide manufacturer's certificate s attesting that the decking material meets the specified requirements.
1.3.2 Certification of Powder-Actuated Tool Operator
Provide manufacturer's certificate attesting that the operators are authorized to use the low velocity powder-actuated tool.
1.3.3 Qualifications for Welding Work
Follow Welding Procedures of AWS D1.3/D1.3M for sheet steel and AWS D1.1/D1.1M for stud welding.
Submit qualified Welder Qualifications in accordance with AWS D1.3/D1.3M for sheet steel and AWS D1.1/D1.1M for stud welding, or under an equivalent approved qualification test. Perform tests on test pieces in positions and with clearances equivalent to those actually encountered. [Test specimens shall be made in the presence of Contracting Officer and shall be tested by an approved testing laboratory at the Contractor's expense.] If a test weld fails to meet requirements, perform an immediate retest of two test welds until each test weld passes. Failure in the immediate retest will require the welder be retested after further practice or training, performing a complete set of test welds.
Submit manufacturer's catalog data for Welding Equipment and Welding Rods and Accessories.
1.3.4 Regulatory Requirements
1.3.4.1 Fire Safety
Test roof deck as a part of a roof deck construction assembly of the type used for this project, listing as fire classified in the UL Fire Resistance, or listing as Class I construction in the FM APP GUIDE, and so labeled.
1.3.4.2 Wind Storm Resistance
As listed in scope of work or on the drawings.
1.3.5 Fabrication Drawings
Show type and location of units, location and sequence of connections, bearing on supports, methods of anchoring, attachment of accessories, adjusting plate details, cant strips, ridge and valley plates, metal closure strips, size and location of holes to be cut and reinforcement to be provided, the manufacturer's erection instructions and other pertinent details.
1.4 DELIVERY, STORAGE, AND HANDLING
Deliver deck units to the site in a dry and undamaged condition. Store and handle steel deck in a manner to protect it from corrosion, deformation, and other types of damage. Do not use decking for storage or as working platform until units have been fastened into position. Exercise care not to damage material or overload decking during construction. The maximum uniform distributed storage load must not exceed the design live load.
Stack decking on platforms or pallets and cover with weathertight ventilated covering. Elevate one end during storage to provide drainage.
Maintain deck finish at all times to prevent formation of rust. Repair deck finish using touch-up paint. Replace damaged material.
1.5 DESIGN REQUIREMENTS FOR ROOF DECKS
1.5.1 Properties of Sections
Properties of metal roof deck sections must comply with engineering design width as limited by the provisions of AISI D100.
1.5.2 Allowable Loads
Indicate total uniform dead and live load for detailing purposes.
2.1 DECK UNITS
Submit manufacturer's design calculations, or applicable published literature for the structural properties of the proposed deck units.
Provide products with an average recycled content of steel products so postconsumer recycled content plus one half of preconsumer recycled content not less than 0 percent.
2.1.1 Roof Deck
Conform to ASTM A792/A792M or ASTM A1008/A1008M for deck used in conjunction with insulation and built-up roofing. Fabricate roof deck units the steel design thickness required by the design drawings and galvanized or zinc-coated in conformance with ASTM A653/A653M, Z275 G90 coating class or aluminum-zinc coated in accordance with ASTM A792/A792M Coating Designation AZM165 AZ55.
2.1.2 Length of Deck Units
Provide deck units of sufficient length to span three or more spacings where possible.
2.1.3 Shop Priming
Shop prime accessories and underside of deck at the factory after coating.
Clean surfaces in accordance with the manufacturer's standard procedure followed by a spray, dip or roller coat of rust-inhibitive primer, oven cured.
2.2 ACCESSORIES
Provide accessories of same material as deck, unless specified otherwise.
Provide manufacturer's standard type accessories, as specified.
2.2.1 Adjusting Plates
Provide adjusting plates, or segments of deck units, of same thickness and configuration as deck units in locations too narrow to accommodate full size units. Provide factory cut plates of predetermined size where possible.
2.2.2 End Closures
Fabricated of sheet metal by the deck manufacturer. Provide end closures minimum0.0295 inch thick to close open ends at exposed edges of floors, parapets, end walls, eaves, and openings through deck.
2.2.3 Flexible Closure Strips for Roof Decks
Provide strips made of vulcanized, closed-cell, synthetic rubber material specified and premolded to the configuration required to provide tight-fitting closures at open ends and sides of steel roof decking.
[Furnish one sample of each type Flexible Closure Strips, 300 millimeter 12 inch long.]
Conforming to ASTM D1056, Grade 2A1, with the following additional properties:
Brittleness temperature ofminus 40 degrees F when tested in accordance with ASTM D746.
Flammability resistance with a flame spread rating of less than 25 when tested in accordance with ASTM E84.
Resistance to ozone must be "no cracks" after exposure of a sample kept under a surface tensile strain of 25 percent to an ozone concentration of 100 parts per million of air by volume in air for 100 hours at 104 degrees F and tested in accordance with ASTM D1149.
Provide a elastomeric type adhesive as recommended by the manufacturer of the flexible closure strips.
2.2.4 Sheet Metal Collar
Where deck is cut for passage of pipes, ducts, columns, etc., and deck is to remain exposed, provide a neatly cut sheet metal collar to cover edges of deck. Do not cut deck until after installation of supplemental supports.
2.2.5 Cover Plates
Sheet metal to close panel edge and end conditions, and where panels change direction or butt. Polyethylene-coated, self-adhesive, 50 mm 2 inch wide joint tape may be provided in lieu of cover plates on flat-surfaced decking butt joints.
Fabricate cover plates for abutting floor deck units from the specified structural-quality steel sheets not less than nominal 1.3 millimeter 18 gage thick before galvanizing. Provide 150 millimeter 6 inch wide cover plates and form to match the contour of the floor deck units.
2.2.6 Cant Strips for Roof Decks
Fabricate cant strips from the specified commercial-quality steel sheets not less than nominal0.0358 inch thick before galvanizing. Bend strips to form a 45-degree cant not less than 5 inch wide, with top and bottom flanges a minimum 3 inch wide. Length of strips 10 feet.
2.2.7 Ridge and Valley Plates for Roof Decks
Fabricate plates from the specified structural-quality steel sheets, not less than nominal 0.0358 inch thick before galvanizing. Provide plates of minimum4-1/2 inch wide and bent to provide tight fitting closures at ridges and valleys. Provide a minimum length of ridge and valley plates of 10 feet.
2.2.8 Metal Closure Strips for Roof Decks
Fabricate strips from the specified commercial-quality steel sheets not less than nominal0.0358 inch thick before galvanizing. Provide strips from the configuration required to provide tight-fitting closures at open ends and sides of steel roof decking.
2.2.9 Galvanized Steel Angles for Roof Decks
Provide hot-rolled carbon steel angles conforming to ASTM A36/A36M, and hot-dip galvanized in accordance with ASTM A123/A123M.
2.2.10 Sound Absorbing Material
Provide [glass fiber in roll or premolded form for acoustical noncellular steel roof deck] [and] [glass fiber rigid strip for acoustical cellular steel deck] in accordance with the manufacturer's standards. Provide a sample of acoustical material to be used.
2.2.11 Mechanical Fasteners
Provide mechanical fasteners, such as powder actuated fasteners, pneumatically driven fasteners or self-drilling screws, for anchoring the deck to structural supports and adjoining units[ as indicated][ that are designed to meet the loads indicated].
2.2.12 Miscellaneous Accessories
Furnish the manufacturer's standard accessories to complete the deck installation. Furnish metal accessories of the same material as the deck and with the minimum design thickness as follows: saddles, 1.204 mm 0.0474 inch welding washers, 1.519 mm 0.0598 inch other metal accessories, 0.909 mm
0.0358 inch unless otherwise indicated.
3.1 EXAMINATION
Prior to installation of decking units and accessories, examine worksite to verify that as-built structure will permit installation of decking system without modification.
3.2 INSTALLATION
Install steel deck units in accordance with 29 CFR 1926, Subpart R – Steel Erection, ANSI/SDI QA/QC, and approved shop drawings. Place units on structural supports, properly adjusted, leveled, and aligned at right angles to supports before permanently securing in place. Damaged deck and accessories including material which is permanently stained or contaminated, deformed, or with burned holes shall not be installed.
Extend deck units over three or more supports unless absolutely impractical. Report inaccuracies in alignment or leveling to the Contracting Officer and make necessary corrections before permanently anchoring deck units. Locate deck ends over supports only. Lap 2 inch deck ends. Do not use unanchored deck units as a work or storage platform. Do not fill unanchored deck with concrete. Permanently anchor units placed by the end of each working day. Do not support suspended ceilings, light fixtures, ducts, utilities, or other loads by steel deck unless indicated. Distribute loads by appropriate means to prevent damage. Prepare shoring in position before concrete placement begins in composite or form deck. Size cellular decking provided as electrical raceways to accommodate indicated wiring systems. Chip off burrs and eliminate sharp edges which may damage wiring. Mesh decking panels accurately and place in accordance with UL 209. Neatly fit acoustical material into the rib voids.
3.2.1 Attachment
Immediately after placement and alignment, and after correcting inaccuracies, permanently fasten steel deck units to structural supports and to adjacent deck units by welding with normal5/8 inchdiameter puddle welds, fastened with screws, powder-actuated fasteners, or pneumatically driven fasteners as indicated on the design drawings and in accordance with manufacturer's recommended procedure. Clamp or weight deck units to provide firm contact between deck units and structural supports while performing welding or fastening. Attachment of adjacent deck units by button-punching is prohibited.
3.2.1.1 Welding
Perform welding in accordance with AWS D1.3/D1.3M using methods and electrodes recommended by the manufacturers of the base metal alloys being used. Ensure only operators previously qualified by tests prescribed in AWS D1.3/D1.3M make welds. Immediately recertify, or replace qualified welders, that are producing unsatisfactory welding. Conform to the recommendations of the Steel Deck Institute and the steel deck manufacturerfor location, size, and spacing of fastening. Do not use welding washers at sidelaps. Holes and similar defects will not be acceptable. Attach all partial or segments of deck units to structural supports in accordance with Section 2.5 of SDI DDM04. Immediately clean welds by chipping and wire brushing. Heavily coat welds, cut edges and damaged portions of [coated finish with zinc-dust paint conforming to ASTM A780/A780M] finish with the manufacturer's standard touch-up paint].
3.2.1.2 Mechanical Fastening
Anchor deck to structural supports and adjoining units with mechanical fasteners. Drive the powder-actuated fasteners with a low-velocity piston tool by an operator authorized by the manufacturer of the powder-actuated tool. Drive pneumatically fasteners with a low-velocity fastening tool and comply with the manufacturer's recommendations. Drive screws to properly clamp desk to supporting steel.
3.2.1.3 Sidelap Fastening
Lock sidelaps between adjacent floor deck units together by welding or screws as indicated.
3.2.2 Openings
Cut or drill all holes and openings required and be coordinated with the drawings, specifications, and other trades. Frame and reinforce openings through the deck in conformance with SDI DDP. Reinforce holes and openings 6 to 12 inch across by0.0474 inch thick steel sheet at least12 inch wider and longer than the opening and be fastened to the steel deck at each corner of the sheet and at a maximum of6 inch on center. Reinforce holes and openings larger than12 inch by steel channels or angles installed perpendicular to the steel joists and supported by the adjacent steel joists. Install steel channels or angles perpendicular to the deck ribs and fasten to the channels or angles perpendicular to the steel joists.
Deck manufacturer shall approve holes or openings larger than6 inch in diameter prior to drilling or cutting. Openings must not interfere with seismic members such as chords and drag struts.
3.2.3 Deck Damage
SDI MOC3, for repair of deck damage.
3.2.4 Touch-Up Paint
3.2.4.1 Roof Deck
After roof decking installation, wire brush, clean, and touchup paint the scarred areas on top and bottom surfaces of metal roof decking. The scarred areas include welds, weld scars, bruises, and rust spots. Touchup galvanized surfaces with galvanizing repair paint. Touchup painted surfaces with repair paint of painted surfaces.
3.2.5 Accessory Installation
3.2.5.1 Adjusting Plates
Provide in locations too narrow to accommodate full-size deck units and install as shown on shop drawings.
3.2.5.2 End Closures
Provide end closure to close open ends of cells at columns, walls, and openings in deck.
3.2.5.3 Closures Above Partitions
Provide for closing voids between cells over partitions that are perpendicular to direction of cells. Provide a one-piece closure strip for partitions4 inch nominal or less in thickness and two-piece closure strips for wider partitions. Provide sheet metal closures above fire-rated partitions at both sides of partition with space between filled with fiberglass insulation. Provide flexible rubber closures above acoustic-rated partitions at both sides of partition with space between filled with blanket insulation.
3.2.6 Preparation of Fire-Proofed Surfaces
Provide deck surfaces, both composite and noncomposite, which are to receive sprayed-on fireproofing, galvanized and free of all grease, mill oil, paraffin, dirt, salt, and other contaminants which impair adhesion of the fireproofing. Complete any required cleaning prior to steel deck installation using a cleaning method that is compatible with the sprayed-on fireproofing.
3.3 CANT STRIPS FOR ROOF DECKS
Provide strips to be fusion welded to surface of roof decking, secured to wood nailers by galvanized screws or to steel framing by galvanized self-tapping screws or welds. Do not exceed spacing of welds and fasteners of12 inch. Lap end joints a minimum 3 inch and secure with galvanized sheet metal screws spaced a maximum4 inch on center.
3.4 RIDGE AND VALLEY PLATES FOR ROOF DECKS
Provide plates to be fusion welded to top surface of roof decking. Lap end joints a minimum3 inch. For valley plates, provide endlaps to be in the direction of water flow.
3.5 CLOSURE STRIPS FOR ROOF DECKS
Provide closure strips at open, uncovered ends and edges of the roof decking and in voids between roof decking and top of walls and partitions where indicated. Install closure strips in position in a manner to provide a weathertight installation.
3.6 ROOF INSULATION SUPPORT FOR ROOF DECKS
Provide metal closure strips for support of roof insulation where rib openings in top surface of metal roof decking occur adjacent to edges and openings. Weld metal closure strips in position.
3.7 CLEANING AND PROTECTION FOR ROOF DECKS
Upon completion of the deck, sweep surfaces clean and prepare for installation of the roofing.
3.8 FIELD QUALITY CONTROL
3.8.1 Headed Stud Inspection
In addition to visual inspection, test and inspect shop-welded shear connectors according to requirements in AWS D1.1/D1.1M for stud welding and as follows:
a. Perform bend tests if visual inspections reveal either a less-than-continuous 360-degree flash or welding repairs to any shear connector.
b. Conduct tests according to requirements in AWS D1.1/D1.1M on additional shear connectors if weld fracture occurs on shear connectors already tested.
3.8.2 Deck Weld Inspection
Visual inspect welds in accordance with AWS D1.3/D1.3M.
3.8.3 Decks Not Receiving Concrete
Inspect the decking top surface for distortion after installation. For roof decks not receiving concrete, verify distortion by placing a straight edge across three adjacent top flanges. The maximum allowable gap between the straight edge and the top flanges should not exceed manufacturing and construction tolerances of supporting members. When gap is more than the allowable, provide corrective measures or replacement. Reinspect decking after performing corrective measures or replacement.
] -- End of Section --
SECTION 05 30 00
STEEL DECKS
05/15
AMERICAN IRON AND STEEL INSTITUTE (AISI)
AISI D100 (2017) Cold-Formed Steel Design Manual
AMERICAN WELDING SOCIETY (AWS)
AWS D1.1/D1.1M (2020) Structural Welding Code - Steel
AWS D1.3/D1.3M (2018) Structural Welding Code - Sheet
Steel
ASTM A36/A36M (2019) Standard Specification for Carbon
Structural Steel
ASTM A123/A123M (2017) Standard Specification for Zinc
(Hot-Dip Galvanized) Coatings on Iron and
Steel Products
ASTM A653/A653M (2020) Standard Specification for Steel
Sheet, Zinc-Coated (Galvanized) or
Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process
ASTM A780/A780M (2009; R 2015) Standard Practice for
Repair of Damaged and Uncoated Areas of
Hot-Dip Galvanized Coatings
ASTM A792/A792M (2010; R 2015) Standard Specification for
Steel Sheet, 55% Aluminum-Zinc
Alloy-Coated by the Hot-Dip Process
ASTM A1008/A1008M (2018) Standard Specification for Steel, Sheet, Cold-Rolled, Carbon, Structural, High-Strength Low-Alloy, High-Strength
Low-Alloy with Improved Formability, Solution Hardened, and Bake Hardenable
ASTM C423 (2009a) Sound Absorption and Sound
Absorption Coefficients by the
Reverberation Room Method
ASTM D746 (2014) Standard Test Method for
Brittleness Temperature of Plastics and
Elastomers by Impact
ASTM D1056 (2014) Standard Specification for Flexible
Cellular Materials - Sponge or Expanded
Rubber
ASTM D1149 (2007; R 2012) Standard Test Method for
Rubber Deterioration - Surface Ozone
Cracking in a Chamber
ASTM E84 (2020) Standard Test Method for Surface
Burning Characteristics of Building
FM GLOBAL (FM)
FM APP GUIDE (updated on-line) Approval Guide
FM DS 1-28R (1998) Data Sheet: Roof Systems
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2020; ERTA 20-1 2020; ERTA 20-2 2020; TIA
20-1; TIA 20-2; TIA 20-3; TIA 20-4)
National Electrical Code
SOCIETY FOR PROTECTIVE COATINGS (SSPC)
SSPC Paint 20 (2019) Zinc-Rich Primers (Type I, Inorganic, and Type II, Organic)
STEEL DECK INSTITUTE (SDI)
ANSI/SDI C (2017) Standard for Composite Steel Floor
Deck - Slabs
ANSI/SDI NC (2017) Standard for Non-Composite Steel
Floor Deck
ANSI/SDI QA/QC (2017) Standard for Quality Control and
Quality Assurance for Installation of
Steel Deck
ANSI/SDI RD (2017) Standard for Steel Roof Deck
SDI DDM04 (2015; Errata 1-3 2016; Add 1 2015; Add 2
20162006) Diaphragm Design Manual; 4th
SDI DDP (1987; R 2000) Deck Damage and Penetrations
SDI MOC3 (2016) Manual of Construction with Steel
Deck (3rd Edition)
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 3-301-01 (2019) Structural Engineering
29 CFR 1926 Safety and Health Regulations for
UNDERWRITERS LABORATORIES (UL)
UL 209 (2011; Reprint May 2016) UL Standard for
Safety Cellular Metal Floor Raceways and
Fittings
UL 580 (2006; Reprint Mar 2019) UL Standard for
Safety Tests for Uplift Resistance of Roof
Assemblies
UL Fire Resistance (2014) Fire Resistance Directory
1.2 SUBMITTALS
submittals not having a "G" designation are [for Contractor QC approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for the Government.] Submittals with an "S" are for inclusion in the
Sustainability eNotebook, in conformance to Section 01 33 29, SUSTAINABITY
Fabrication Drawings; G
SD-03 Product Data
Accessories
Deck Units
Galvanizing Repair Paint
[ Mechanical Fasteners
Touch-Up Paint
Sound Absorbing Materials
Welding Equipment
Welding Rods and Accessories
Recycled Content of Steel Products; S
SD-04 Samples
Metal Roof Deck Units
Cellular Metal Floor Deck Units
Flexible Closure Strips
Acoustical Material
SD-05 Design Data
Deck Units; G
Powder-Actuated Tool Operator
Welder Qualifications
Welding Procedures
Fire Safety
Wind Storm Resistance
Manufacturer's Certificate
Stud Manufacture's Certification
Stud Manufacture's Test Reports
1.3 QUALITY ASSURANCE
1.3.1 Deck Units
Furnish deck units and accessory products from a manufacturer regularly engaged in manufacture of steel decking. Provide manufacturer's certificate s attesting that the decking material meets the specified requirements.
1.3.2 Certification of Powder-Actuated Tool Operator
Provide manufacturer's certificate attesting that the operators are authorized to use the low velocity powder-actuated tool.
1.3.3 Qualifications for Welding Work
Follow Welding Procedures of AWS D1.3/D1.3M for sheet steel and
AWS D1.1/D1.1M for stud welding.
Submit qualified Welder Qualifications in accordance with AWS D1.3/D1.3M for sheet steel and AWS D1.1/D1.1M for stud welding, or under an equivalent approved qualification test. Perform tests on test pieces in positions and with clearances equivalent to those actually encountered. [Test specimens shall be made in the presence of Contracting Officer and shall be tested by an approved testing laboratory at the Contractor's expense.] If a test weld fails to meet requirements, perform an immediate retest of two test welds until each test weld passes. Failure in the immediate retest will require the welder be retested after further practice or training, performing a complete set of test welds.
Submit manufacturer's catalog data for Welding Equipment and Welding Rods and Accessories.
1.3.4 Regulatory Requirements
1.3.4.1 Fire Safety
Test roof deck as a part of a roof deck construction assembly of the type used for this project, listing as fire classified in the UL Fire Resistance, or listing as Class I construction in the FM APP GUIDE, and so labeled.
1.3.4.2…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .