This solicitation is for a firm fixed-price construction contract to perform a Coyote Pit Crush and Stockpile project on the Coconino National Forest in Arizona. The project scope includes mobilization, clearing and grubbing, drilling, blasting, sampling and testing, stockpile surveying for quality control, and crushing and stockpiling aggregate materials according to plans and specifications. The contract is a 100% small business set-aside for NAICS code 212319 with a size standard of 500 employees. The submission deadline is June 7, 2022. The award will be determined by best value tradeoffs evaluating technical and price factors. Site visits are scheduled for May 11, 2022 to review the Ruin Pit and Coyote Pit locations. Questions must be submitted by May 17, 2022 to the contracting officer. The Department of Agriculture Forest Service Region 3 Southwestern Region is the contracting agency.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
C.1 – STATEMENT OF WORK
Coyote Pit Crush and Stockpile Project: This project will include mobilization, clearing and grubbing, drilling, blasting, sampling and testing, stockpile surveying for quality control and crushing and stockpiling of an aggregate material in accordance with the plans and specifications.
Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.
SUBMITTAL/NOTIFICATION TIMELINES
Required Submittal/Notification
Deadline for Receipt by the Government
Applicable Specification
Work Schedule At Pre-Work Meeting 151 - Mobilization
Hazardous Spill Plan Before beginning any work 107 – Legal Relations & Responsibility to the Public
Contractor Quality Control Plan
Before beginning any work 153.02 Contractor Quality Control Plan
Equipment Mobilization Notification
1 week prior to moving equipment onto Coconino National Forest
151 - Mobilization
Traffic Control Plan 14-days prior to prework conference
156-Public Traffic
Aggregate Gradation*** During aggregate production FSSS 703 Soil Erosion Control Plan 14-days prior to prework conferenc.
157-Soil Erosion Control
Plan of Operations 14-days prior to prework conference.
FSSS 314
Blasting Plan 14-days prior to drilling and blasting operations
205 – Rock Blasting; FSSS 205
*** Items to be tested:
1. Gradation (AASHTO T 11)
2. Gradation (AASHTO T 27)
3. Liquid Limit (AASHTO T 89)
4. Plastic Limit (AASHTO T 90)
5. LA Abrasion (AASHTO T 96)
6. Sodium Sulfate Soundness (AASHTO T 104)
7. Durability (AASHTO T 210)
8. Fractured Faces (ASTM D 5821)
9. Specific Gravity and Absorption of Course Aggregate
C.2 – LOCATION OF PROJECT
The project is located on the Flagstaff Ranger District of the Coconino National Forest located in Coconino County, Arizona. From the Coconino SO:
COCONINO NATIONAL FOREST SUPERVISOR'S OFFICE
1824 S THOMPSON ST, FLAGSTAFF, AZ 86001
TAKE W FOREST MEADOWS ST TO AZ-89A 4 MIN (1.2 MI)
FOLLOW I-17 S TO PINEWOOD RD IN MUNDS PARK. TAKE EXIT 322 FROM I-17 S 16 MIN (17.8 MI)
TAKE E OAK DR TO HILLSIDE DR 4 MIN (1.4 MI)25
MIN (20.5 MI)
MUNDS PARK ARIZONA
HEAD EAST ON HILLSIDE DR TOWARD BIG SKY DR/PINE TRAIL DR 0.2 MI
TURN RIGHT ONTO E OAK DR 0.2 MI
CONTINUE ONTO E CRESTLINE RD 0.5 MI
TURN LEFT ONTO PINEWOOD BLVD 1.0 MI
CONTINUE ONTO FOREST SERVICE RD 240 2.1 MI
TURN LEFT ONTO FOREST SERVICE RD 133A 1.8 MI
23 MIN (6.0 MI)
MUNDS PARK ARIZONA
HEAD NORTHWEST ON FOREST SERVICE RD 700 TOWARD FOREST SERVICE RD 133
DESTINATION WILL BE ON THE LEFT