This document is a Statement of Work (SOW) that describes the requirements for a contractor to remove existing carpet and install new vinyl flooring in the CO Cabin (04-33-0-L) of the USCGC HEALY, a U.S. Coast Guard cutter. The total area to be covered is 650 square feet.

The related federal contract opportunity is a Request for Quote (RFQ) for the carpet removal and vinyl flooring installation work. The RFQ, number 70Z08524PSEAT0033, is for a firm-fixed price purchase order with a needed completion date of June 2024. The work must be performed Monday through Friday, 7am to 4pm, at the U.S. Coast Guard Base in Seattle, WA. Interested vendors must submit a quote, have an active SAM.gov registration, and will be required to submit invoices through the Invoice Processing Platform (IPP). Payment terms are net 30 days.

View the file

Other files for this federal contract opportunity

Other files attached to USCGC HEALY Deck Covering, Vinyl Flooring Install, newest first.
File Type Posted
Coast Guard Drawing 420WAGB634001 Rev B Deck Covering Schedule.pdf PDF
Coast Guard Drawing 420 WABG612009Rev C Joiner Arrangement 04 Level and Above.pdf PDF
FAR Clauses 70Z08524PSEAT0033.docx DOCX document
KingWA WAGE DETERMINATIONS.txt TXT text file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Deck Covering, Vinyl Flooring Install

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to install vinyl flooring over polymeric surfaces at location identified in Table 1

TABLE 1: DECKING SYSTEM-VINYL FLOORING

LOCATION
AREA SQ FEET
DECK
COVE BASE
VINYL FLOORING
SUGGESTED SOURCE OF SUPPLY

CO Cabin (04-33-0-L)

650
Carpet over Steel Deck
Y
Barenaked Lt Plank (Sunrise 88074PLK) barenaked™ LT Plank™
TEKNOFLOR

1005 South 60th Street Milwaukee, WI 53214 hmtxcommercial.com Philip J. Hughes phughes@hmtx.global phughes@teknoflor.com pjhghs3@gmail.com O: 800.522.9166 M: 937.829.8316 Fax: 414.944.0550

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 420-WAGB-634-001, Rev B, Deck Covering Schedule Coast Guard Drawing 420-WABG-612-009, Rev C, Joiner Arrangement 04 Level and Above

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2014, Install Interior Deck Covering Systems Coast Guard Publications can be found at: Standard Specifications (uscg.mil)

OTHER REFERENCES

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2013, Power Tool Cleaning to Bare Metal

. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

None.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination,

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:

Furniture Chair Securing Clamps

3.1.5 To minimize distribution to Cutter’s personnel, the Contractor shall propose a work plan to the Contracting Officer.

3.1.6 Notification. The Contractor shall give written notification to the Contracting Officer, 48 hours before starting work on this item.

3.2 The Contractor shall remove and dispose carpet listed in the Table 2.

TABLE 2 – CARPET REMOVAL

LOCATION

CO Cabin (04-33-0-L)

3.2.1 Visual inspection. The Contractor shall perform a visual inspection of all existing underlayment following carpet removal. Submit a CFR. Any patching of existing damaged underlayment shall be the subject of a change request.

3.3 Vinyl flooring. The Contractor shall supply and install vinyl flooring listed in the Table 1 in accordance with SFLC Std Spec 6341 and manufacturer’s instruction.

3.3.1 Cleaning. Surfaces shall be completely free of corrosion products, mill scale, dirt, oil, grease, moisture, deteriorated paint, and other surface contaminants.

3.3.2 In the presence of the Coast Guard Inspector, conduct a visual inspection of the clean deck in the work area for corrosion and deterioration. Submit a CFR.

3.3.3 The Contractor shall perform all tasks specified in SFLC Std Spec 6341 and herein, to install a new vinyl flooring system listed in the Table 1

3.3.4 Underlayment. The Contractor shall remove existing underlayment completely and power tool clean to bare metal all steel decks in the work areas in accordance with SSPC-SP 11 (or SSPC-SP 10/NACE No. 2 with dust control). Surfaces shall be completely free of corrosion products, mill scale, dirt, oil, grease, moisture, deteriorated paint, and other surface contaminants.

3.3.4.1 The Contractor shall provide and install self-level epoxy underlayment to achieve level foundation in accordance with manufacturer instruction and MIL-PRF-32170. Underlayment shall be installed so that all installed deck fittings are flush with final decking.

3.4 Cove base. Install cove base molding at corners between deck and bulkhead in the work areas specified in Table 1 where applicable in accordance with SFLC Std Spec 6341. Unless otherwise specified, apply caulking compound at other corners.

3.5 Touch-up preservation. The Contractor shall prepare and coat all new and disturbed exterior and interior surfaces to match existing adjacent surfaces, in accordance with SFLC Std Spec) 6310. Abide by all touch-up requirements outlined in SFLC Std Spec) 6310.

4. NOTES

This section is not applicable to this work item.