This document consists of two Task Assignment Notification Change Orders for DEP Contract No. HW561, involving the State of Florida Department of Environmental Protection (DEP) and contractor Golder Associates. The contract is managed by DEP Contract Manager Ben Grubbs, with Matt Crews as the Contractor Representative and Donald Miller as the Contractor's authorized signatory. The work relates to critical response activities at an unnamed facility (Site ID: NA) referred to as "Critical Response."
Both change orders authorize time extensions to maintain the Task Assignment open for critical response activities. Change Order No. 7, dated December 15, 2020, extends the completion date from December 28, 2020 to June 28, 2021 (6-month extension), while Change Order No. 8, dated May 25, 2021, further extends the completion date to December 28, 2021 (additional 6-month extension). The task amount remains fixed at $18,692.60 across all change orders with no cost increases. The final deliverable for both change orders is "Documentation of completed site activities." The invoice schedule itemizes eight deliverables including air monitoring reports, site visit letters, system shutdown and restart documentation for Hurricane Hermine and Hurricane Irma events, and assessment documentation at fuel service stations in Putnam County. Previously invoiced amounts total $16,192.60, with the remaining $2,500.00 due upon DEP approval of the completed site activities documentation.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Change Order No.:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
Site Name:
Site ID / Facility ID::
Description of Change [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverable:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
Cost Reimbursement Fixed Fee
Original Task Amount
Task Amount Prior to this Change Order Net Increase/decrease in task amount Task amount with all change orders $0.00 $0.00 $0.00 $0.00
Original Task Completion Date:
Completion Date Prior to this Change:
Net Increase/Decrease in Task Period:
Completion Date with all Change Orders:
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
FIXED PRICE
TASK ASSIGNMENT NOTIFICATION CHANGE ORDER FORM
ITEM
$0.00
$0.00
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
Final Deliverable Due Date:
$0.00
$0.00
CHANGE IN TASK TIME
FEE SCHEDULE
COST PLUS FIXED FEE
TOTAL
WCP TAFORM 01_18
HW561
8DC001G
Golder Associates
Matt Crews
(850) 245-8992Ben Grubbs
Critical Response
NA
This Task Assignment Change Order authorizes a time extension to keep this Task Assignment open should critical response activities be warranted.
Documentation of completed site activities 12/28/2021
$ 2,500.00 $ 0.00 $ 0.00 $ 0.00
$ 18,692.60 $ 0.00 $ 0.00 $ 0.00 $ 18,692.60
$ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00
$ 18,692.60
12/28/2020
06/28/2021
6 months
12/28/2021
Benjamin Grubbs Digitally signed by Benjamin Grubbs Date: 2021.05.25 14:16:01 -04'00'
Benjamin Grubbs Digitally signed by Benjamin Grubbs Date: 2021.05.25 14:16:11 -04'00'
William Burns Digitally signed by William Burns Date: 2021.05.25 14:57:29 -04'00'
Donald Miller Digitally signed by Donald Miller Date: 2021.05.25 16:08:04 -04'00'
$ 18,692.60 $ 0.00 $ 0.00 $ 0.00
$ 2,500.00
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number: HW561 Task Assignment #: DC001G
Change Order #: 8
Deliverables:
Deliverable Deliverable Due Date Air Monitoring Report Completed
Site Visit Letter Report Completed
Offsite notification packages Completed
Email documentation of System Shutdown and Restart Completed
Documentation of SVE systems shutdown for Hurricane Hermine Completed
Documentation of completed site activities 28-Dec-21
Documentation of SVE systems shutdown and restart for Hurricane Irma
Completed
Documentation of assessment at fuel service stations in Putnam County
Completed
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced DEP approval of Air Monitoring Report - Previously Invoiced
$1,527.18
DEP approval of Site Visit Letter Report and Offsite Notification Package - Previously Invoiced $6,673.16
DEP approval of Tropical Storm System Shutdown and Restart - Previously Invoiced $637.65
DEP approval of SVE Systems shutdown for Hurricane Hermine - Previously Invoiced $273.62
DEP approval of Documentation of completed site activities $2,500.00
DEP approval of Documentation of SVE systems shutdown and restart for Hurricane Irma - Previously Invoiced $1,927.59
DEP approval of Documentation of assessment at fuel service stations in Putnam County - Previously Invoiced $5,153.40
TOTAL COST $18,692.60
BWC TAFORM 01_18
DEP CONTRACT NO.
Task Assignment #: Change Order No.:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
Site Name:
Site ID / Facility ID::
Description of Change [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverable:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
Cost Reimbursement Fixed Fee
Original Task Amount
Task Amount Prior to this Change Order Net Increase/decrease in task amount Task amount with all change orders
$0.00 $0.00 $0.00 $0.00
Original Task Completion Date:
Completion Date Prior to this Change:
Net Increase/Decrease in Task Period:
Completion Date with all Change Orders:
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
FIXED PRICE
TASK ASSIGNMENT NOTIFICATION CHANGE ORDER FORM
ITEM
$0.00
$0.00
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
Final Deliverable Due Date:
$0.00
$0.00
CHANGE IN TASK TIME
FEE SCHEDULE
COST PLUS FIXED FEE
TOTAL
WCP TAFORM 01_18
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number: HW561 Task Assignment #: DC001G
Change Order #: 7
Deliverables:
Deliverable Deliverable Due Date Air Monitoring Report Completed
Site Visit Letter Report Completed
Offsite notification packages Completed
Email documentation of System Shutdown and Restart Completed
Documentation of SVE systems shutdown for Hurricane Hermine Completed
Documentation of completed site activities 28-Jun-21
Documentation of SVE systems shutdown and restart for Hurricane Irma
Completed
Documentation of assessment at fuel service stations in Putnam County
Completed
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced DEP approval of Air Monitoring Report - Previously Invoiced
$1,527.18
DEP approval of Site Visit Letter Report and Offsite Notification Package - Previously Invoiced $6,673.16
DEP approval of Tropical Storm System Shutdown and Restart - Previously Invoiced $637.65
DEP approval of SVE Systems shutdown for Hurricane Hermine - Previously Invoiced $273.62
DEP approval of Documentation of completed site activities $2,500.00
DEP approval of Documentation of SVE systems shutdown and restart for Hurricane Irma - Previously Invoiced $1,927.59
DEP approval of Documentation of assessment at fuel service stations in Putnam County - Previously Invoiced $5,153.40
TOTAL COST $18,692.60
BWC TAFORM 01_18
| Task Assignment CHANGE ORDER |
| BWC Task Assignment Change Order Form (Rev 02-17).pdf |
| Task Assignment CHANGE ORDER |
| BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf |
| Deliverable & Invoice Schedule |