This is a Task Assignment Notification Form executed under Florida Department of Environmental Protection (FDEP) Contract No. HW556 between the State of Florida and Cardno, Inc. for environmental remediation services at the Plaza Dry Cleaners facility (ERIC_5294) located at 934 Patricia Avenue, Dunedin, Pinellas County, Florida. The task assignment was authorized on June 7, 2021, with Walsta Jean-Baptiste serving as the FDEP Contract Manager and Eric Meyers as the Contractor Representative. The assignment is structured as a fixed-price contract with no cost-plus or reimbursement components.

The task authorizes Cardno to oversee the implementation of interim source removal activities, including soil vapor extraction (SVE) system installation, well construction, and remedial system startup in accordance with an approved work plan and bid documentation received on June 3, 2021. The contract value is $114,513.39 with no retainage, covering 270 hours of work through January 31, 2022. Deliverables include a Remedial Action Startup Report and ADaPT/GIS update due October 29, 2021, with an intermediate deliverable of construction documentation due August 31, 2021. The cost structure includes $106,769.64 for documentation of construction activities and $7,743.75 for the Remedial Action Startup Report. The scope encompasses field labor by Cardno staff, subcontractor services from Petrotech Southeast ($80,083.00 base bid), utility hookup fees ($450.00), laboratory analysis ($1,928.00), and associated travel, equipment, and overhead costs.

View the file

Other files

File Type Posted
CN-370000-HW556-A 9.pdf PDF
CN-370000-HW556-A10.pdf PDF
CN-370000-HW556-A5.pdf PDF
CN-370000-HW556-BF004F.pdf PDF
CN-370000-HW556-BF03ACO1.pdf PDF
CN-370000-HW556-BF03C.pdf PDF
CN-370000-HW556-BF04B.pdf PDF
CN-370000-HW556-BF04BCO3.pdf PDF
CN-370000-HW556-BF04CCO2.pdf PDF
CN-370000-HW556-BF04DCO2.pdf PDF
CN-370000-HW556-BF04DCO3.pdf PDF
CN-370000-HW556-BF04DCO4.pdf PDF
CN-370000-HW556-BF05A.pdf PDF
CN-370000-HW556-BF05B.pdf PDF
CN-370000-HW556-BF06BCO3.pdf PDF
CN-370000-HW556-BF06BCO4.pdf PDF
CN-370000-HW556-BF08B.pdf PDF
CN-370000-HW556-BF562E.pdf PDF
CN-370000-HW556-BF563A.pdf PDF
CN-370000-HW556-DC003F.pdf PDF
CN-370000-HW556-DC004E.pdf PDF
CN-370000-HW556-DC006C.pdf PDF
CN-370000-HW556-DC006E.pdf PDF
CN-370000-HW556-DC007E.pdf PDF
CN-370000-HW556-DC008A.pdf PDF
CN-370000-HW556-DC009C.pdf PDF
CN-370000-HW556-DC010E.pdf PDF
CN-370000-HW556-DC011A.pdf PDF
CN-370000-HW556-DC012A.pdf PDF
CN-370000-HW556-DC012C.pdf PDF
CN-370000-HW556-DC01ACO3.pdf PDF
CN-370000-HW556-DC01B.pdf PDF
CN-370000-HW556-DC01C.pdf PDF
CN-370000-HW556-DC01I.pdf PDF
CN-370000-HW556-DC027B.pdf PDF
CN-370000-HW556-DC027E.pdf PDF
CN-370000-HW556-DC027F.pdf PDF
CN-370000-HW556-DC028B.pdf PDF
CN-370000-HW556-DC029A.pdf PDF
CN-370000-HW556-DC029E.pdf PDF
CN-370000-HW556-DC02B.pdf PDF
CN-370000-HW556-DC02BCO1.pdf PDF
CN-370000-HW556-DC02E.pdf PDF
CN-370000-HW556-DC032A.pdf PDF
CN-370000-HW556-DC035A.pdf PDF
CN-370000-HW556-DC03A.pdf PDF
CN-370000-HW556-DC03B.pdf PDF
CN-370000-HW556-DC03C.pdf PDF
CN-370000-HW556-DC03CCO2.pdf PDF
CN-370000-HW556-DC03DCO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEP CONTRACT NO.

Task Assignment #: Module #: Grant #:

Contractor Name:

Contractor Representative:

DEP Contract Manager: Phone #:

DEP Site #:

Site Name:

Address(Street, City, County):

Phase:

Task Description [use additional pages if necessary]:

The Deliverable and Invoice Schedule is attached.

Final Deliverables:

Final Deliverable Due Date:

TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:

FIXED FEE

RETAINAGE:

TOTAL TASK ASSIGNMENT VALUE: $0.00

DEP Task Manager:

DEP Contract Manager:

Contractual Authority:

Contractor Representative:

CC: Procurement Section (MS 93) Section Representative ________

TASK ASSIGNMENT NOTIFICATION FORM

COST PLUS FIXED FEE

COST REIMBURSEMENT

FIXED PRICE FEE SCHEDULE

Period of Performance:

Execution of Task Assignment through:

DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

WCP TAFORM 01_18

HW556

D000 NADC026D

Cardno, Inc.

Eric Meyers

850-245-8705Walsta Jean-Baptiste

ERIC_5294

Plaza Dry Cleaners & Laundry

934 Patricia Ave, Dunedin, Pinellas County

Interim Source Removal

This Task Assignment authorizes Cardno to oversee interim source removal implementation in accordance with the approved work plan, Cardno scope of work, bid documentation, cost estimate, and schedule received on June 3, 2021.

Remedial Action Startup Report and ADaPT/GIS update

10/29/2021

01/31/2022

$ 114,513.39 $ 0.00 $ 0.00 $ 0.00

$ 0.00

Walsta Jean-Baptiste Digitally signed by Walsta Jean-Baptiste Date: 2021.06.07 10:17:03 -04'00'

Walsta Jean-Baptiste Digitally signed by Walsta Jean-Baptiste Date: 2021.06.07 10:17:10 -04'00'

Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2021.06.10 17:25:47 -04'00'

Eric Meyers Digitally signed by Eric Meyers Date: 2021.06.11 08:53:15 -04'00'

$ 114,513.39

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 01-2018

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Documentation of completion of construction activities including photo log of site conditions before and after installation, property transfer forms, field notes, investigation derived waste manifests, and SVE startup notes - Subtask 2

08/31/2021

Remedial Action Startup Report and ADaPT/GIS update - Subtasks 1 and 3 10/29/2021

FDEP approval of documentation of completion of construction activities including photo log of site conditions before and after installation, property transfer forms, field notes, investigation derived waste manifests, and SVE startup notes - Subtask 2

$ 106,769.64

FDEP approval of Remedial Action Startup Report and receipt of ADaPT/GIS update

- Subtasks 1 and 3 $ 7,743.75

$ 114,513.39

HW556

DC026D

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Noah Valenstein Secretary

Memorandum

TO: HW556 Contract File

FROM: Walsta Jean-Baptiste SUBJECT: Interim Source Removal Implementation; DC026D

Plaza Dry Cleaners & Laundry (ERIC_5294) DATE: June 7, 2021

This Task Assignment authorizes Cardno to oversee interim source removal implementation in accordance with the approved work plan, Cardno scope of work, bid documentation, cost estimate, and schedule received on June 3, 2021.

Cardno requested bids from three subcontractors but only received two responses. Based on overall cost as well as estimated time to complete the implementation work, Petrotech SE is the proposed subcontractor. A revised bid to include utility hookup and SVE transportation to the site was only requested from Petrotech, as the low bidder. A suitable FDEP system was located after bids were initially requested from implementation subcontractors. The number of days onsite estimated by the subcontractors even with the additional work (SVE transportation and electrical hookup) for Petrotech remains lower than Equipment with Experience resulting in a lower cost for Cardno oversight. Using Petrotech is also preferred because in addition to lower costs for Cardno oversight, the facility is currently a pharmacy so a pharmacist is required to be onsite for all interior work.

The subcontractor handling fee for Petrotech was calculated correctly at a rate of 10% for the first fifty thousand and 7% for the second fifty thousand. A utility handling fee of $450 is also included for account setup related to electric ($225) and telemetry ($225).

Changes include several corrections to equipment rates and usage to match the days onsite and allowable contract amounts. The PM also requested that Cardno adjust the Petrotech bid to show unit rate costs where appropriate. There was no change in the Petrotech cost related to the clarification.

The cost related to this Task Assignment is $114,513.39 with 270 hours.

Australia • Belgium • Canada • Colombia • Ecuador • Germany • Indonesia • Kenya • Myanmar • New Zealand • Nigeria • Papua New Guinea • Peru • Philippines • Singapore • Timor-Leste • United Kingdom • United States • Operations in over 100 countries

Cardno

2420 Lakeshore Drive Suite 100 Tallahassee

FL 32312 USA

Phone +1.850.385.8232 Fax 850.385.8233 www.cardno.com

June 3, 2021

Ms. Walsta Jean-Baptiste

Florida Department of Environmental Protection

Waste Site Cleanup Section

Drycleaning Solvent Cleanup Program

2600 Blairstone Road, MS 4520

Tallahassee, FL 32399

RE: Task Assignment Request for Soil Vapor Extraction System Installation and Construction Activities

Plaza Dry Cleaners

934 Patricia Ave., Dunedin, Pinellas County, Florida

FDEP Facility ID: ERIC_5294

Task Assignment: HW556-DC026D

Dear Walsta:

Cardno Inc. (Cardno) is pleased to submit this Task Assignment Request for Soil Vapor Extraction (SVE) modification and installation at the Plaza Dry Cleaners (ERIC_5294) site. Cardno completed an Interim Source

Removal Plan (ISRP), dated March 4, 2020 (revised August 5, 2020) for the above referenced site, and approved by the Florida Department of Environmental Protection (FDEP) on August 7, 2020.

The implementation of the ISRP requires the following tasks:

Permitting;

Schedule coordination with property owner and tenant;

Modification previously installed Modified Active Gas Sampling (MAGS) wells (M-1, M-6, and M-7) into vapor extraction (VE) wells (VE001 through VE003, respectively);

Installation of one (1) VE well (VE004) to a depth of approximately 24 feet below land surface (ft bls)

(adjustments to the total depth and screen interval may be required based on depth to water measured at

MW-Unk during the time of installation so the VE well is approximately 1 foot above the water table) and three (3) monitoring wells (MW-9 through MW-11) to a total depth of 70 ft bls terminating in 10 feet of

0.01-inch factory slotted screen;

Modification of previously installed MAGS wells (M-2 through M-5, M-8, and M-9) into vacuum measurement points (VMPs) with protective manhole completion;

Trenching and installation of underground and above ground piping and appurtenances (including pressure testing) to connect VE wells (VE001 through VE004) to the SVE system compound;

Mobilization of the McSherry’s SVE system (Property ID number: 138631) located at 11612 N Dale

Mabry Highway, Tampa, Hillsborough, to the Plaza Dry Cleaners site;

Construction of SVE system compound and manifold;

Utility account setup and utility hookup to the SVE system (electric and telemetry);

Baseline groundwater sampling (MW-2 to MW-4, MW-6, MW-9, MW-10, and MW-11, and a duplicate sample), per Table 1, and laboratory analysis of volatile organic halocarbons (VOHs) by United States

Environmental Protection Agency (USEPA) Method 8260;

Ms. Walsta Jean-Baptiste Waste Site Cleanup Section

Plaza Dry Cleaners (ERIC_5294) SVE Installation and Construction Activities Task Assignment Request

June 3, 2021

Australia • Belgium • Canada • Colombia • Ecuador • Germany • Indonesia • Kenya • Myanmar • New Zealand • Nigeria • Papua New Guinea • Peru • Philippines • Singapore • Timor-Leste • United Kingdom • United States • Operations in over 100 countries

Depth to water measurements from MW-3, MW-4, and MW-Unk during startup;

Vapor sample collection from VE001 to VE004, influent, and effluent (Table 1) for laboratory analysis of volatile organic carbons (VOCs) by USEPA Method TO-15 and field screening using an photoionization detector (PID);

Submittal of property reporting form, chain of custody (if applicable), and Attachment M Replacement of

Major Equipment (if applicable) and associated documentation; and, Prepare a Remedial Action System Startup Report to include updated tables, figures, laboratory data, summary of remedial actions, conclusions, and Construction Drawings.

Subcontractor Selection

For the onsite construction activities and the construction of the SVE system, bids were solicited from Preferred

Drilling Service, Equipment with Experience, and Petrotech SE. Preferred Drilling Service was deemed nonresponsive. As the lowest bidder and the lowest number of field days, Petrotech SE is selected to perform the onsite construction activities. At the time of bidding, an FDEP owned SVE system was not available to transport. As the system at McSherry’s Dry Cleaner Inc. (ERIC_4787) became available, Petrotech SE was requested to provide updated costs to transport and install electrical and electrical connections to the system. A copy of each bid, and the proposed subcontractor scope of work is provided in Appendix A.

Schedule to Complete

The proposed deliverables and due dates are summarized below and are based on the assumption the SVE system will take approximately 6 weeks to identify, mobilize, and install:

Subtask 1: Project Management

Subtask 2: SVE Construction and Installation

Deliverable: Submittal of field documentation, subcontractor submittals (permits, etc.), groundwater and vapor laboratory data, property reporting forms, and photodocumentation

Deliverable Due Date: August 31, 2021

Subtask 3: Remedial Action Startup Up Report; submittal of updated tables, figures, and a summary of remedial action construction activities, conclusions, and Construction Drawings

Deliverable Due Date: October 29, 2021

Period of Performance: January 31, 2022

If you have questions regarding this cost proposal, please call me at 850-629-2702 or by email

(eric.meyers@cardno.com).

Sincerely, Eric V. Meyers, P.E.

Project Engineer

For Cardno mailto:eric.meyers@cardno.com

Appendix A Subcontractor Costs

EXHIBIT 1

Scope of Work for

Remedial System Installation at the

Plaza Dry Cleaners (ERIC_5294)

934 Patricia Avenue

Dunedin, Pinellas County, Florida

Cardno, Inc. (Cardno), under contract (Contract HW556) with Florida Department of

Environmental Protection (FDEP), herein referred to as the Client, is seeking Subcontractor(s) to perform remedial system installation at the above-referenced site. These services include, well installation, well head and vault construction, sub-surface piping, trenching and backfilling, surface restoration, utility installation (electric and wireless), non-hazardous waste soil management and disposal.

The scope of work will be costed based on 10-hour working days Monday through Friday.

Weekends may be worked if agreed upon by Cardno project manager, property owner or the property representative, and the selected subcontractor.

The subcontractor shall obtain necessary permits and furnish the equipment and material for installation of a remedial system, waste management, and waste disposal. If overburden from the system trenches during construction cannot be used as backfill, then manifests indicating proper transportation and disposal will be required for final payment.

Not included in this scope of work as costs associated with procurement of a soil vapor extraction

(SVE) system or modification of an existing FDEP owned system.

Exhibit 2 is to be completed by the subcontractor to indicate the proposed costs to complete this

Scope of Work.

Interim Source Removal Design

The Interim Source Removal Plan prepared for the Client is available at:

https://prodenv.dep.state.fl.us/DepNexus/public/electronic-documents/ERIC_5294/facility!search

Site Access

The Client has obtained permission to enter the site from the property owner. Construction activities and facility access will be determined with a meeting with the property owner/property representative, facility operator, prior to commencement of construction activities.

Health and Safety

Subcontractor and their subcontractors, if applicable, shall work under the Subcontractor Health and Safety Plan (HASP). The HASP shall be in accordance with Occupational Safety and Health

Administration (OSHA) requirements specified in Title 29, Code of Federal Regulations.

Requirements

Trenchwork activities (including electrical and plumbing) will be performed in accordance with the OSHA requirements, the Florida Trench Safety Act (Section 553.60-553.64, Florida Statutes), https://prodenv.dep.state.fl.us/DepNexus/public/electronic-documents/ERIC_5294/facility!search

EXHIBIT 1 Scope of Work for Remedial System Installation Plaza Dry Cleaners (ERIC_5294) the Underground Facility Damage Prevention and Safety Act (556.101-556.111, Florida Statutes), and Federal and State regulations (including Chapter 489 and Chapter 553, Florida Statues).

Electrical and plumbing work, underground utility construction and excavation, and SVE system installation will be performed in accordance with Chapters 489 & 553, Florida Statutes and local requirements.

Electrical hookup, wiring, connections, grounding, etc. shall meet appropriate requirements of the

National Electrical Code.

Subsurface Features

The selected subcontractor is responsible to obtain underground utility searches (including U-Dig and ground penetrating radar, where appropriate) in accordance with the law. Subsurface work shall be conducted in a manner as to protect subsurface utilities and features. A ground penetrating radar (GPR) survey has been conducted at the property and can be provided upon request. Providing the GPR does not alleviate the subcontractor of liability for performing search or damage to underground structures or utilities.

Bid Sheet/Price Schedule Item Descriptions

The following are referenced to the item number on the preceding Subcontractor Rate Sheet and are intended to further define the corresponding cost items identified therein.

1. Mobilization, Site Preparation, and Demobilization (including all other costs not otherwise specified below).

This item is for the time and efforts of the Subcontractor in obtaining and transporting any of the equipment and supplies required for this project to and from the site required for installation of an SVE system. This item includes charges incidental to equipment set-up and removal as well as the furnishing of personnel, machinery, tools, and all other equipment necessary to perform and complete the work properly. Site cleanup (demobilization) and site restoration including repair of damage caused by installation or use of temporary facilities.

This item should not include the actual cost of purchased or rented equipment and supplies.

Equipment and supplies furnished under this item will remain the property of the

Subcontractor(s) and will be maintained, cared for, and disposed of by the Subcontractor(s).

The following costs are also included in this item:

Permitting and Utility Clearance

Permitting costs (application, fees, processing, well installation/completion, etc.);

Conduct underground utility clearances;

Schedule mandatory meetings and inspections with all the corresponding authorities;

Site Preparation

Provision of worker safety and sanitary facilities and enclosures as required by

OSHA;

Coordination of activities;

Place caution tape, traffic plates, traffic cones, and traffic signs where needed; and, Clear all work areas.

SVE Treatment System Startup

Coordinate the SVE treatment system startup activities with Cardno’s project manager. The Cardno project manager must receive notification of startup activities no less than 48 hours in advance

Provide SVE treatment system startup and run the SVE treatment system continuously for a minimum of 6 hours.

Startup shall be performed in accordance with the United States Army Corps of

Engineers publication EM 1110-1-4001 titled “Engineering and Design: Soil Vapor

Extraction and Bioventing.”

Items, installed by the Subcontractor(s),that do not meet the specifications or requirements must be satisfactorily resolved with concurrence of Cardno. Items deemed unacceptable by the Cardno project manager must be repaired or replaced prior to Cardno’s approval of work and acceptance of the SVE treatment system.

This item will be paid at the lump sum contract price.

2. Monitoring Well Installation.

Subcontractor, or sub-subcontractor, shall install three (3) monitoring wells (MW-9 through

MW-11) using sonic technology. Monitoring wells MW-9 through MW-11 will be installed to a total depth of 70 ft bls, terminating in 10 feet of 0.01-inch factory slotted screen and completed to land surface with blank riser pipe. The wells will be constructed of 2-inch schedule 40 polyvinyl chloride (PVC). The wells will be set within a 2 foot by 2 foot 6-inch thick concrete vault with a Florida Department of Transportation (FDOT) H20 rated 8-inch manhole.

The wells annulus space shall be filled with at least 11 feet of 20/30 sand, 1 feet of 30/65 fine sand seal, concrete grout to land surface.

The wells will be developed until free of fines. Well development water will be containerized in ne FDOT 55-gallon steel drums. Subcontractor will not be required to manage or dispose of the drums.

Locations of the monitoring wells are provided in Exhibit 3.

This item will be paid at the lump sum contract price.

3. Vapor Extraction Well Installation.

Subcontractor, or sub-subcontractor, shall install one (1) vapor extraction well (VE004) using sonic technology. The vapor extraction well will be installed to a total depth of 24 ft bls, terminating in 23 feet of 0.01-inch factory slotted screen and completed to land surface with blank riser pipe. The well will be constructed of 2-inch schedule 40 PVC. The well will be completed within a concrete vault with an FDOT manhole sufficient enough to contain the piping and appurtenances as indicated in the Exhibit 3. The location of the vapor extraction well are provided in Exhibit 3.

This item will be paid at the lump sum contract price.

4. Well Head Construction and Well Vaults.

This item shall include labor and materials associated with the installation of the construction of vapor extraction well heads and conversion of MAGS wells.

A total of four (4) well heads will be constructed as shown on the construction drawings

(Exhibit 3) at VE001/M-1, VE002/M-6, VE003/M-7, and newly installed VE004.

The remaining well heads M-2 through M-5, M-8, and M-9 will be converted into vacuum distribution monitoring points. The subcontractor shall remove the temporary grout patch, and install an 8-inch FDOT H20 rated manhole set within a 2 foot by 2 foot concrete pad.

Interior wells may have a smaller footprint on both pad and manhole to minimize impact to the facility. The subcontractor shall convert each of these well heads by installing a well plug fitted with a vacuum/sample port.

This item will be paid at a lump sum costs.

5. Earthwork (trenching and backfilling).

This item shall include labor and materials associated with trenching and backfilling.

Conduct trenching and backfilling activities as shown on the construction drawings. Saw cut asphalt and/or concrete prior to trenching. Provide protection (such as trench road plates) over and around excavated areas until backfill and surface restoration activities are complete.

Any field changes that deviate from the construction drawings shall be noted and submitted by the Subcontractor to the Cardno project manager.

Material removed from trenches shall be replaced in the trench following piping installation.

Installation of material shall be placed and compacted in 4 inch to 6 inch lifts. Subcontractor shall compact material to no less than 95% density of the modified Proctor. Subcontractor shall Proctor and field density test to determine the degree of compaction. It is the responsibility of the Subcontractor to have available an independent testing agency to complete the tests. Whenever test results indicate compaction densities are less than specified, the Contractor shall secure the specified compaction. The testing agency, so employed by the Subcontractor, shall submit a copy of testing reports directly to Cardno.

Subcontractor shall stop placement of backfill 6-inch below land surface bls at exterior trenching for surface restoration as described in Item 7.

Overburden generated during trenching that is not used as backfill will be disposed of as indicated in Item 12.

This item will be paid at lump sum price.

6. Piping and Appurtenances.

This item shall include labor and materials associated with both above grade and below grade surface piping installation. Vapor extraction well piping and controls, from the vapor extraction wells to the SVE treatment system, as shown on the construction drawings.

Additionally, this item includes the labor and materials associated with the SVE and air injection manifold (including flow meters and gauges) as shown in the construction drawings.

Above grade piping shall be 2-inch diameter schedule 80 PVC. Above grade piping and accessories shall affixed to walls by brackets set apart no greater than 6 feet. Piping shall be affixed at an above head height, at such a height as field determined. Additionally, Subcontractor shall be equipped to cut an opening through wall(s) to allow for piping. Any such drilling shall be sealed upon installation of the piping with a fire retardant insulation.

The walls at the property are known to be cinderblock.

Below grade piping shall be 2-inch diameter schedule 40 PVC.

Piping and manifold shall be pressure/vacuum tested during construction and slightly sloped toward the VEW to minimize water entrainment.

This item will be paid at a lump sum costs.

7. Surface Restoration.

This item shall include labor and materials associated with surface restoration. Conduct surface restoration activities as shown on the construction drawings.

Surface restoration on the interior of the building shall be no less than 3,000 pounds per square inch (psi) concrete with fiber mesh dyed to match the interior.

Surface restoration on the interior of the building shall be no less than 6-inches of no less than

3,000 psi concrete with fiber mesh dyed black to match asphalt conditions.

Well pads shall be no less than 6-inches thick and no less than 3,000 psi fiber mesh concrete.

This item will be paid at the lump sum contract price.

8. SVE System Compound.

Subcontractor shall construct a compound for the manifold and SVE system as indicated in the construction drawings (Exhibit 3).

This item will be paid at the lump sum contract price.

9. SVE System Transportation.

This item is for mobilizing an existing SVE system from the McSherry’s Cleaners site

(ERIC_4787) located at 11612 North Dale Mabry Highway, Tampa, FL to the Plaza Dry

Cleaners Site located at 934 Patricia Ave, Dunedin.

This item will be paid at the lump sum contract price.

10. SVE System Startup.

This item is for the subcontractor to perform startup and troubleshooting activities of the SVE system when permits and approvals for startup have been received.

This item will be paid at the lump sum contract price.

11. Utility Hook-up (Electric and Wireless).

This item shall include labor, equipment, and materials associated with electric and wireless utilities connections. This item includes installation of a utility drop, wiring, electrical box, inspections, and installation of utilities from the electrical drop to the SVE treatment system.

Coordinate utility connects with local utility owners/suppliers.

Utility accounts will be setup by Cardno.

This item will be paid at the lump sum contract price.

12. Waste Management and Disposal.

This item shall include labor and materials associated with waste management and disposal, if warranted.

Subcontractor shall:

Properly containerize mixed debris and soils excavated during trench work activities.

Properly manage and dispose of asphalt and concrete cuttings in an appropriate facility

(C and D landfill). Provide Cardno with manifests or bills of lading and final disposal certificates. Subcontractor shall provide Cardno with a list of any subcontractors, transporters and disposal facility(ies) utilized to dispose of the waste.

Properly manage and dispose of non-hazardous over burden cuttings in an appropriate facility. Provide Cardno with manifests or bills of lading and final disposal certificates.

Subcontractor shall provide Cardno with a list of any subcontractors, transporters and disposal facility(ies) utilized to dispose of the waste.

This item will be paid at the contract price per ton.

END SCOPE OF WORK.

ITEM DESCRIPTION UNIT

ESTIMATED

QUANTITY

UNIT PRICE TOTAL

1 Mobilization and all other costs not otherwise specified below. Lump Sum 1 $8,845.00 $8,845.00

2 Monitoring Well Installation per well 3 $4,000.00 $12,000.00

3 Vapor Extraction Well Installation per well 1 $4,000.00 $4,000.00

4 Well Head Construction and Well Vault per well 7 $218.57 $1,530.00

5 Earthwork (trenching and backfilling) per LF 82 $140.33 $11,507.00

6 Piping and Appurtenances per LF 464 $16.98 $7,881.00

7 Surface Restoration per CY 2 $2,761.50 $5,523.00

8 SVE System Compound Lump Sum 1 $9,657.00 $9,657.00

9 SVE System Transportation Lump Sum 1 $2,500.00 $2,500.00

10 SVE System Startup Lump Sum 1 $1,350.00 $1,350.00

11 Utility Hook-up (Electric and Wireless) Lump Sum 1 $14,000.00 $14,000.00

12 Waste Management and Disposal Ton 10 $129.00 $1,290.00

$80,083.00

TOTAL FIELDWORK DURATION REQUIRED 13 DAYS

TOTAL NOT TO EXCEED BID PRICE

Eighty thousand eighty-three dollars & zero cents ($80,083.00)

Corporate Entity: Petrotech Southeast, Inc.

Authorized Agent: Michael Bishop, Sr. Construction Manager

Costs Valid for: 60 (days)

Remedial System Installation for

Bid Form

EXHIBIT 2

Dunedin, Pinellas County, Florida

934 Patricia Avenue

Plaza Dry Cleaners (ERIC_5294) at the

Removal of Line Items 9 through 11 ($17,850.00) make the cost subtotal: $62,233.00

JeanBaptiste_W Highlight

EXHIBIT 2

Bid Form for

Remedial System Installation at the

Plaza Dry Cleaners (ERIC_5294)

ITEM DESCRIPTION UNIT ESTIMATED

QUANTITY UNIT PRICE TOTAL

1 Mobilization and all other costs not otherwise specified below. Lump Sum 1

2 Monitoring Well Installation Lump Sum 1

3 Vapor Extraction Well Installation Lump Sum 1

4 Well Head Construction and Well Vault Lump Sum 1

5 Earthwork (trenching and backfilling) Lump Sum 1

6 Piping and Appurtenances Lump Sum 1

7 Surface Restoration Lump Sum 1

8 SVE System Compound Lump Sum 1

9 SVE System Transportation Lump Sum To be change ordered in following SVE system identification

10 SVE System Modification Lump Sum To be change ordered in following SVE system identification

$3,500

$3,500

13,200 $13,200

5,500

$3,500

$3,500

$5,500

9,600 $9,600

5,200 $5,200

17,900 $17,900

10,800 $10,800

EXHIBIT 2 - Bid Form for Remedial System Installation

934 Patricia Ave.

ITEM DESCRIPTION UNIT ESTIMATED

QUANTITY UNIT PRICE TOTAL

11 Utility Hook-up (Electric and Wireless) Lump Sum To be change ordered in following SVE system identification

12 Waste Management and Disposal Ton

TOTAL FIELDWORK DURATION REQUIRED DAYS.

TOTAL NOT TO EXCEED BID PRICE

(use words) (figures)

Corporate Entity: ____________________________________________________

Authorized Agent: ___________________________________________________

Costs Valid for: _______________________________________(days)

10 75 $750

Equipment with Experience, LLC

Thomas Twitmyer

69,950.00Sixty-nine thousand nine hundred and fifty dollars

JeanBaptiste_W Highlight

FDEP COST ESTIMATEContractor: CARDNO, Inc.

Date:

Task #: HW556 DC026D SubTask 1 SubTask 6

Site: SubTask 2 SubTask 7

Activity/Phase: SubTask 3 SubTask 8

Project Manager: SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

CARDNO, Inc.

$43.32 Project Manager (EM) 19 19.1 $43.32 Project Engineer (EM) 37 17 20 0 0 0 0 0 0 0 $43.04 Project Engineer (JM) 14 14 0 0 0 0 0 0 0 0 $21.60 Staff Geologist (VG) 188 164 24 0 0 0 0 0 0 0 $29.63 CADD Technician (DJD) 12 0 12 0 0 0 0 0 0 0

Total Hours 270 19 195 56 0 0 0 0 0 0 0

CARDNO, Inc.

Direct Labor $7,449.48 $827.72 $4,881.40 $1,740.36 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 169.58% $12,632.83 $1,403.65 $8,277.88 $2,951.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sub-Total Labor (CARDNO) $20,082.31 $2,231.37 $13,159.28 $4,691.66 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Labor $20,082.31 $2,231.37 $13,159.28 $4,691.66 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Other Direct Costs $372.48 $41.39 $244.07 $87.02 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel

Vehicle Rental $1,464.00 $1,464.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $1,464.00 $1,464.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

6/3/2021

Project Management

Plaza Dry Cleaners (ERIC_5294)

SVE Installation and Startup

FDEP: W. Jean-Baptiste / Cardno: E. Meyers

Remedial Action System Startup Report

SVE Construction and Installation and Startup

REV: 05/2015 CEF: CARDNO HSW Page 1

FDEP COST ESTIMATEContractor: CARDNO, Inc.

Date:

Task #: HW556 DC026D SubTask 1 SubTask 6

Site: SubTask 2 SubTask 7

Activity/Phase: SubTask 3 SubTask 8

Project Manager: SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

6/3/2021

Project Management

Plaza Dry Cleaners (ERIC_5294)

SVE Installation and Startup

FDEP: W. Jean-Baptiste / Cardno: E. Meyers

Remedial Action System Startup Report

SVE Construction and Installation and Startup

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $450.00 $450.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Petrotech SE $80,083.00 $80,083.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $80,533.00 $80,533.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $7,105.81 $7,105.81 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $87,638.81 $87,638.81 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $1,860.00 $1,860.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $68.00 $68.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $1,928.00 $1,928.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $520.00 $520.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment $208.55 $208.55 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $291.00 $291.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,019.55 $1,019.55 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $112,505.15 $2,272.76 $105,453.71 $4,778.68 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $2,008.24 $223.14 $1,315.93 $469.17 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $114,513.39 $2,495.90 $106,769.64 $5,247.85 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 05/2015 CEF: CARDNO HSW Page 2

SITE :

FDEP NO:

SUBTASK 2:

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Engineer EM Technical Support (1 hour per day) - 13 days property owner and pharmacy pre- 17 kickoff meeting communications and scheduling; permitting

Project Engineer JM Weekly Site Inspections (3) - 4 hours each 12

Travel Time (Clearwater to Dunedin) - 3 inspections (0.25 hour 1 way) 2

Staff Geologist VG Travel Time (Clearwater to Dunedin) - 16 Days (0.25 hour 1 way) 8 Construction oversight, record keeping, photodocumentation - 13 days 130

SVE Startup - 1 day 8

TOTAL LABOR 195

TRAVEL TYPE RATE UNIT USEAGE Miles Free

Truck $420.00 week 3 $1,260.00 Automobile $68.00 day 3 $204.00

Hotel $85.00 day $0.00 Per Diem $36.00 day $0.00

TOTAL VEHICLE $1,464.00

SUBCONTRACTOR

Equipment Procurement

NAME PURPOSE COST UNIT USEAGE

$0.00 Services Procurement

NAME PURPOSE COST UNIT USEAGE

Petrotech SE SVE System Mobilization / startup $3,850.00 LS 1 $3,850.00 Petrotech SE VEW and MW Installation and Piping $62,233.00 LS 1 $62,233.00 Petrotech SE Electrial Hookup $14,000.00 LS 1 $14,000.00 Utility Account Setup Electric and Telemetry $225.00 ea 2 $450.00

TOTAL SUBS $80,533.00

LABORATORY

PARAMETER RATE # SAMPLES #QAQC

VOHs (EPA 8260) - 9 GW samples, 1 duplicate $66.00 9 1 $660.00 VOHs (TO-15) - VE001 to VE004, Influent, Effluent $200.00 6 $1,200.00

Shipping (small) $63.00 1 $63.00 Ice $5.00 1 $5.00

TOTAL LAB $1,928.00

FIELD EXPENSES ITEM RATE UNIT USEAGE TOTALS

Field Equipment

Shallow Groundwater Sampling Kit $208.55 day 1 $208.55 Construction/O&M/Pilot Test Kit $291.00 day 1 $291.00 Expendables $32.50 day 16 $520.00

Sub-Total $1,019.55

TOTAL EQUIPMENT $1,019.55

Warehouse Mob/Demob (GW sampling)

Plaza Dry Cleaners (ERIC_5294)

HW556 DC026D

SVE Construction and Installation and Startup 6/3/2021

Groundwater Sampling- 9 wells (MW-2 to MW-4, MW-6, and MW-9 to MW-11, MW- Unk and exfiltration) - 2 days

SITE :

FDEP NO:

SUBTASK 3:

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Engineer/Geologist EM Remedial Action Startup Report text, Record Drawings, Recommendations Conclusions, PE Certification 20

Staff Geologist VG Data Tabulation, Figure Development, GIS Data Tables 24

CADD Technician FN Record Drawing Development 12

Project Assistant GD Project Support 0

TOTAL LABOR 56

TRAVEL TYPE RATE UNIT USEAGE Miles Free

Truck $97.00 Day 0 $0.00

TOTAL VEHICLE $0.00

SUBCONTRACTOR

TOTAL SUBS $0.00

LABORATORY

PARAMETER RATE # SAMPLES #QAQC

TO-15 $200.00 0 $0.00

Shipping Small (0 to 25lbs); No Ice $63.00 0 $0.00 Ice $5.00 0 $0.00

TOTAL LAB $0.00

FIELD EXPENSES ITEM RATE UNIT USEAGE TOTALS

Field Equipment

Construction/O&M/Pilot Test Kit $291.00 day 0 $0.00 Expendables $32.50 day 0 $0.00

Sub-Total $0.00

TOTAL EQUIPMENT $0.00

Plaza Dry Cleaners (ERIC_5294)

HW556 DC026D

Startup and Remedial Action System Startup Rep 6/3/2021

Task Assignment Notification
BWC Task Assignment Form (Rev 02_17).pdf
Task Assignment Notification
BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf
Deliverable & Invoice Schedule
EXHIBIT 2_rev.pdf
264004810
Plaza Cleaners Construction CEF 05042021.pdf
Cost Estimate-Original
sub 2-Original
sub 3-Original
EXHIBIT 2_rev.pdf
264004810

File details come from the government source that posted it. Updated .