About this file
This is a Task Assignment Notification Form for Florida Department of Environmental Protection (FDEP) Contract No. HW556, issued on July 27, 2021. The task assignment authorizes Cardno, Inc. (through HSW Consulting, LLC) to conduct six months of operation and maintenance activities at the Peterson Cleaners site located at 850 N Broadway Avenue, Bartow, Polk County, Florida (ERIC_5380). The assignment is managed by FDEP Contract Manager Walsta Jean-Baptiste and Contractor Representative Joe Marsh. The work encompasses soil vapor extraction (SVE) system operation and maintenance activities conducted in accordance with the Interim Source Removal Plan approved by FDEP on June 9, 2020.
The task assignment includes four subtasks: Project Management (Subtask 1), SVE Operation and Maintenance for Quarter Three with quarterly documentation due November 24, 2021 (Subtask 2), SVE Operation and Maintenance for Quarter Four with Annual Remedial Action Status Report due February 22, 2022 (Subtask 3), and utility costs for six months from August 2021 through January 2022 (Subtask 4). The total contract value is $26,758.53, comprising $23,158.53 in fixed price costs and $3,720.00 in cost-plus fixed fee costs for utilities (not to exceed $3,600.00 in actual utility charges plus a $120 handling fee). No retainage was assessed. The work encompasses 146 total labor hours distributed across project management, field operations, documentation, and utility payments. Payment is contingent upon FDEP approval of deliverables, with invoicing triggered upon approval of the quarterly O&M submittal and Annual Remedial Action Status Report, and upon receipt of utility invoices.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
HW556
D000 NADC027F
Cardno, Inc.
Joe Marsh
850-245-8705Walsta Jean-Baptiste
ERIC_5380
Peterson Cleaners
850 N Broadway Avenue, Bartow, Polk County
Operation and Maintenance
This Task Assignment authorizes HSW to conduct six months of operation and maintenance in accordance with the HSW scope of work, schedule, and cost estimate received on July 23, 2021.
The payment of utilities is the only part of this Task Assignment that is Cost Plus Fixed Fee.
Annual Remedial Action Status Report
02/22/2022
05/31/2022
$ 23,158.53 $ 0.00 $ 3,600.00 $ 0.00
$ 0.00
Walsta Jean-Baptiste Digitally signed by Walsta Jean-Baptiste Date: 2021.07.27 18:26:06 -04'00'
Walsta Jean-Baptiste Digitally signed by Walsta Jean-Baptiste Date: 2021.07.27 18:26:15 -04'00'
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2021.07.28 11:20:55 -04'00'
Digitally signed by Joe L. Marsh Date: 2021.08.02 10:29:17 -04'00'
$ 26,758.53
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 01-2018
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Quarterly O&M submittal including field documentation, laboratory reports and tables
- Subtask 2 11/24/2021
Annual Remedial Action Status Report - Subtask 3 02/22/2022
FDEP approval of quarterly O&M submittal including field documentation, laboratory reports and tables - Subtask 2; AND FDEP approval of Annual Remedial Action Status Report - Subtasks 1 and 3
$ 23,038.53
FDEP receipt of utility invoices for 6 months (August 2021 to January 2022); Utilities (Cost Plus Fixed Fee) = not to exceed $3,600; Utilities Handling Fee = $120 - Subtask 4
$ 3,720.00
$ 26,758.53
HW556
DC027F
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Interim Secretary
Memorandum
TO: HW556 Contract File FROM: Walsta Jean-Baptiste, Contract Manager SUBJECT: Peterson Cleaners; Operation and Maintenance; DC027F DATE: July 27, 2021
This Task Assignment authorizes HSW to conduct six months of operation and maintenance in accordance with the HSW scope of work, schedule, and cost estimate received on July 23, 2021.
This Task Assignment also includes 6 months of utilities from August 2021 to January 2022.
There were no changes to the proposed costs.
The final cost associated with this Task Assignment is $26,758.53 with 146 hours.
(813) 968-7722 ■ 15711 Mapledale Blvd., Suite B ■ Tampa, FL 33624 ■ www.hsweng.com Innovative Solutions Within Your Reach…
P:\Tampa\1CB6 Cardno\1CB6022XX Peterson Cleaners\1CB602203 Peterson Cleaners - SVE\01 Proposals\TA Request_O&M 07-2021.docx
July 23, 2021
Sent via Electronic Mail
Ms. Walsta Jean-Baptiste, P.G.
Florida Department of Environmental Protection Waste Site Cleanup Section 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400
Re: Task Assignment Request – SVE Operation & Maintenance (Six Months) Peterson Cleaners 850 N. Broadway Avenue, Bartow, FL
ERIC_5380
Dear Walsta:
HSW Consulting, LLC. (HSW) is pleased to submit this Task Assignment request for Soil Vapor Extraction System Operation and Maintenance (SVE O&M) activities at the former Peterson Cleaners site (Site) in accordance with the Interim Source Removal Plan approved by FDEP on June 9, 2020. The following presents a proposed schedule and associated cost estimate for implementation of these activities.
Subtask 1: Project Management;
Subtask 2: SVE O&M Quarter Three; submittal of Quarterly O&M Documentation.
Deliverable Date: November 24, 2021
Subtask 3: SVE O&M Quarter Four; Submittal of Annual Remedial Action Status Report, including updated tables, figures and laboratory data.
Deliverable Date: February 22, 2022
Sincerely, HSW ENGINEERING, INC.
Nicholas Barnes, P.E.
Senior Engineer
Attachments: Subcontractor Quotes
Level of Effort/Cost Estimate Forms (native file attached)
FDEP COST ESTIMATEContractor: CARDNO, Inc. / HSW Eng., Inc
Date: TBD
Task #: TBD SubTask 1 Project Management SubTask 6
Site: Peterson Cleaners SubTask 2 O&M - Quarter 3 SubTask 7
Activity/Phase: O&M SubTask 3 O&M - Quarter 4, Annual Status Report SubTask 8
Project Manager: Steven Folsom SubTask 4 Utilities SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
HSW Engineering, Inc.
$66.35 Project Manager SDF 10 10.3
Principal 0 0 0 0 0 0 0 0 0 0 $66.35 Project Manager SDF 12 4 8 0 0 0 0 0 0 0
Senior Geologist 0 0 0 0 0 0 0 0 0 0 Senior Engineer 0 0 0 0 0 0 0 0 0 0 Project Geologist 0 0 0 0 0 0 0 0 0 0
$45.20 Senior Engineer NSB 38 10 28 0 0 0 0 0 0 0 Project Scientist 0 0 0 0 0 0 0 0 0 0 Staff Engineer/Geologist 0 0 0 0 0 0 0 0 0 0
$33.66 Staff Engineer JAB 80 30 50 0 0 0 0 0 0 0 Field Technician 0 0 0 0 0 0 0 0 0 0
$45.68 Senior Scientist CLW 2 0 2 0 0 0 0 0 0 0 $39.67 CADD Technician BLA 4 0 4 0 0 0 0 0 0 0
Project Assistant 0 0 0 0 0 0 0 0 0 0 $0.00 CADD Technician 0 0 0 0 0 0 0 0 0 0 $0.00 Surveyor (PLS) 0 0 0 0 0 0 0 0 0 0 $0.00 Survey Party chief 0 0 0 0 0 0 0 0 0 0 $0.00 Survey Crew 0 0 0 0 0 0 0 0 0 0 $0.00 Subsurface Utility Location (SUE) Tech 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0
Total Hours 146 10 44 92 0 0 0 0 0 0 0
HSW Engineering, Inc.
Direct Labor $6,138.72 $682.08 $1,727.20 $3,729.44 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 170.00% $10,435.83 $1,159.54 $2,936.24 $6,340.05 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sub-Total Labor (HSW) $16,574.55 $1,841.62 $4,663.44 $10,069.49 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Labor $16,574.55 $1,841.62 $4,663.44 $10,069.49 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Other Direct Costs $306.93 $34.10 $86.36 $186.47 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 05/2015 CEF: CARDNO HSW Page 1
FDEP COST ESTIMATEContractor: CARDNO, Inc. / HSW Eng., Inc
Date: TBD
Task #: TBD SubTask 1 Project Management SubTask 6
Site: Peterson Cleaners SubTask 2 O&M - Quarter 3 SubTask 7
Activity/Phase: O&M SubTask 3 O&M - Quarter 4, Annual Status Report SubTask 8
Project Manager: Steven Folsom SubTask 4 Utilities SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle Rental $776.00 $291.00 $485.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $776.00 $291.00 $485.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $100.00 $0.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $3,600.00 $0.00 $0.00 $3,600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $3,700.00 $0.00 $100.00 $3,600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $130.00 $0.00 $10.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $3,830.00 $0.00 $110.00 $3,720.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $1,794.00 $200.00 $1,594.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $189.00 $63.00 $126.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $1,983.00 $263.00 $1,720.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $195.00 $97.50 $97.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $1,435.60 $480.15 $955.45 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,630.60 $577.65 $1,052.95 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $25,101.08 $1,875.72 $5,881.45 $13,623.91 $3,720.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $1,657.45 $184.16 $466.34 $1,006.95 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $26,758.53 $2,059.88 $6,347.79 $14,630.86 $3,720.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 05/2015 CEF: CARDNO HSW Page 2
SITE : Peterson Cleaners
FDEP NO: ERIC_5380
SUBTASK: O&M - Quarter Three
DATE: 7/27/2021
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager SDF System Operation Review 4
Senior Engieer NSB Field Correspondence 4 Documentation of O&M Preparation 6
Staff Engineer JAB Mobilization/Demobilization - Month 1, Month 2, Month 3 6 System O&M, Field Measurements, Sample Collection 24
TOTAL LABOR 44
TRAVEL
TYPE RATE UNIT USEAGE Miles Free Truck $97.00 day 3 $291.00
TOTAL VEHICLE $291.00
SUBCONTRACTOR
Equipment Procurement
NAME PURPOSE COST UNIT USEAGE
Services Procurement
NAME PURPOSE COST UNIT USEAGE
TOTAL SUBS $0.00
LABORATORY
PARAMETER RATE # SAMPLES #QAQC
TO-15 $200.00 1 $200.00
Sample Shipment/Preparation Small (0 to 25 lbs), Overnight $63.00 1 $63.00
TOTAL LAB $263.00
FIELD EXPENSES
ITEM RATE UNIT USEAGE TOTALS
Field Equipment
Construction/O&M/Pilot Test Kit $291.00 day 1 $291.00 Construction/O&M Supplies $63.05 day 3 $189.15
Sub-Total $480.15
Expendables $32.50 day 3 $97.50
Sub-Total $97.50
Total Equipment $577.65
SUBTASK: O&M - Quarter 4
DATE: 7/27/2021
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager SDF System Operation Review 2 Senior Review 6
Senior Engineer NSB Field Correspondence 4 Annual Status Report 24
CAD Technician BLA Figures 4
Senior Scientist CLW Data Review, ADaPT/GIS Update 2
Staff Engineer JAB Mobilization/Demobilization - Month 4, Month 5, Month 6 10 System O&M, Field Measurements, Sample Collection 24 Groundwater Sampling Collection 16
TOTAL LABOR 92
TRAVEL
TYPE RATE UNIT USEAGE Miles Free Truck $97.00 day 5 $485.00
TOTAL VEHICLE $485.00
SUBCONTRACTOR
Equipment Procurement
NAME PURPOSE COST UNIT USEAGE
Services Procurement
NAME PURPOSE COST UNIT USEAGE
Erwin Remediation IDW Disposal $100.00 drum 1 $100.00
TOTAL SUBS $100.00
LABORATORY
PARAMETER RATE # SAMPLES #QAQC
TO-15 $200.00 5 $1,000.00
VOHs (aqueous) EPA 8260 $66.00 8 1 $594.00 Sample Shipment/Preparation Small (0 to 25 lbs), Overnight $63.00 2 $126.00
TOTAL LAB $1,720.00
FIELD EXPENSES
ITEM RATE UNIT USEAGE TOTALS
Field Equipment
Construction/O&M/Pilot Test Kit $291.00 day 1 $291.00 Construction/O&M Supplies $63.05 day 3 $189.15 Shallow Groundwater Sampling Kit $208.55 day 2 $417.10
Sub-Total $897.25
Expendables $32.50 day 3 $97.50 Drum $58.20 each 1 $58.20
Sub-Total $155.70
Total Equipment $1,052.95
SUBTASK: O&M - Utilities
DATE: 7/27/2021
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
FIELD EXPENSES
ITEM RATE UNIT USEAGE TOTALS
O&M Quarter 1 Utilities August to October 2021
Utility Charges (Electric) $600.00 month 3 $1,800.00 Utility Handling Fee $20.00 month 3 $60.00
Sub-Total $1,860.00 O&M Quarter 2 Utilities November 2021 to January 2022
Utility Charges (Electric) $600.00 month 3 $1,800.00 Utility Handling Fee $20.00 month 3 $60.00
Sub-Total $1,860.00
Total Equipment $3,720.00
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To: Mr. Eric Meyers
Cardno
2420 Lakeside Drive, Suite 100
Tallahassee, FL 32312
October 2, 2018
Re: Drum Disposal – Non-Hazardous Soil or Water Impacted with Dry Cleaning Solvents
Mr. Meyers:
The price to dispose of a 55-gallon drum of non-hazardous soil or water impacted with drycleaning solvents located within the State of Florida will be $100.00 per drum.
This price is a flat-rate that includes both the transportation and disposal for non-hazardous material and is valid for 12-months from the date of this letter.
If the soil or water is deemed to be hazardous additional charges will apply.
We appreciate the opportunity to work with you on this. Should you have any questions, please contact me directly at (850) 292-6511.
Respectfully, Jonathan Erwin
Erwin Remediation, Inc.
Email: ErwinRemediation@Gmail.com
Office: (850) 292-6511 mailto:Remediation@Gmail.com NBarnes Text Box Confirmed applicable to HSW and pricing valid.
NSB
October 25, 2017
Nick Barnes HSW Enginering 15711 Mapledale Blvd Suite B Tampa Fl 33624 813-549-1016
RE: Drum disposal
Dear Nick:
Petrotech Southeast, Inc. would like to take this opportunity to thank you for your interest in our services. Per your request, please find our proposal for the services you require.
Description of work: Petrotech Southeast, Inc. proposes to provide the equipment and personnel to remove IDW drums from sites in Central Fl. Drums must be placed on hard surface, IE concrete or asphalt. Additional loading charge may apply. All non-hazardous waste material will be recycled and/or disposed of according to Florida’s Department of Environmental Protection’s regulations. All rates are based upon standard working hours 8 AM to 5 PM Monday through Friday.
Product / Service Unit Type Unit Price Non Haz, Solid Drum Disposal with Trans and fuel charge Per Drum $125.00
Non Hazardous Waters W/ T&D Per Drum $115.00 With approved Analytical / profile. Water 8260 Volatiles, Solids 8 RCRA metals & Volatiles.
Estimate is for budgetary purpose only actual Quantities invoiced.
Payment Terms: Net 30 days.
All other Petrotech Southeast, Inc. standard terms and conditions shall apply. Any applicable taxes and fuel surcharges shall be invoiced accordingly. Quoted pricing is good for 90 days.
If you have any questions regarding this service agreement, please do not hesitate to call me 407-656-8114. Otherwise, please return a signed copy.
Best regards, PETROTECH SOUTHEAST, INC. HSW Engineering
Mike Anderson Mike Anderson Date Signature Date Sales Title
NBarnes Text Box Confirmed valid.
NSB
| Task Assignment Notification |
| BWC Task Assignment Form (Rev 02_17).pdf |
| Task Assignment Notification |
| BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf |
| Deliverable & Invoice Schedule |
| 2021_07 SVE O&M.pdf |
| Cost Estimate |
| sub 2 |
| sub 3 |
| sub 4 |
File details come from the government source that posted it. Updated .