This document is a Task Assignment Change Order Form (Change Order No. 2) issued by the Florida Department of Environmental Protection (FDEP) for the Lovers Key State Park Park Redevelopment project in Fort Myers, Florida. The contract involves multiple design and engineering firms, primarily Gresham Smith as the lead consultant, with subconsultants including DRMP (surveying), Terracon (geotechnical), and Haskell (architectural services). The change order was executed on April 24, 2023, and is authorized under FDEP Contract No. CN215, Task Assignment No. 3, following damage sustained by Hurricane Ian in September 2022.

The change order adds $29,502.00 to the task amount, increasing the total contract value from $855,908.61 to $885,410.61 (inclusive of all previous change orders and reimbursables). The scope encompasses design, permitting, and inspection services for replacement structures including tram bridges, timber boardwalks, utility systems, geotechnical investigations, and design documents for a tram station pavilion, residence building, concession/gift shop, ranger station, gazebo, and roadway improvements. Services are structured as a lump sum agreement with reimbursable expenses not to exceed $29,502.00, including field costs, travel, and per diem. Payment is made upon FDEP approval of deliverables for each task. The project schedule extends through multiple concurrent design phases (30%, 60%, 90%, and final construction documents) with completion tied to permitting milestones and interdependent deliverables across multiple structures and utility systems.

Text of this file

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

(Revised 9-26-2018) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN215 3 CO2 6I402C

Lovers Key State Park Park Redevelopment

Gresham Smith

Tyler Strickland 850.219.8404 tyler.strickland@greshamsmith.com

Ralph Perkins or successor 850.245.2460 Ralph.Perkins@FloridaDEP.gov

Added design, permit and construction for tram bridges inspection and for new structures damaged from Hurricane Ian: gazebo, residence, ranger station, sewer, tram shelter,roads, concession building, walkway bridge . See proposal dated 4.21.23

$ 0.00 $ 10,185.42 $ 10,185.42 $ 0.00 $ 19,087.23 $ 19,087.23

$ 29,502.00 $ 855,908.61 $ 885,410.61 $ 29,502.00 $ 874,995.84 $ 904,497.84

2.08.04

6.30.25

6.30.25

6.30.25

Diane Langston Diane Langston Digitally signed by Diane Langston Date: 2023.04.24 12:59:55 -04'00'

Garland Sandel Garland Sandel Digitally signed by Garland Sandel Date: 2023.04.24 13:09:57 -04'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.04.24 13:22:33 -04'00'

Tyler Strickland Strickland, Tyler Digitally signed by Strickland, Tyler Date: 2023.04.24 16:37:21 -04'00'

Mara Gambineri Mara Gambineri Digitally signed by Mara Gambineri Date: 2023.05.22 12:01:52 -04'00'

6I402C FD091 37800000000 088040/23 408001 U3200 131500 PF $ 885,410.61

$ 885,410.61

Mr. Garland S andel - FDEP April 21, 20 23

Page | 1

Project Description: Lover's Key State Park

Park Redevelopment Project

CN 215

Task Assignment 3

Change Order 2

This Task Order Change Order 2 is to perform the necessary tasks to design replacement structures at Lovers Key

State Park. On September 23, 2022, Hurricane Ian made landfall in Florida and affected many attractions within the state. One of these is Lover's Key State Park. The damage was considered major, with anticipated work needed for existing bridges, boardwalks, pavilions, roadways, utilities, tram stops, ranger stations, residences, and beach restoration.

This task order includes the services and design of the following structures and facilities at Lovers Key State Park:

3. Project Coordination

4. Post Beach Renourishment Bridge Inspection and Rating – 2 Tram Bridges

5. Survey for Structures

6. Timber Boardwalk

7. Utility Design

8. Geotechnical Investigations

9. Tram Station at Beach

10. Residence Building

11. Concession Stand / Gift Shop (Adjacent to Existing Restroom Facility)

12. Ranger Station – Main Entrance Road

13. Gazebo at Beach

14. Survey for Roadway Improvements

15. Roadway Design

16. Permitting

Task 3: Project Coordination

Description: Gresham Smith will perform project management and coordination duties for the duration of this contract. This includes internal coordination with the subconsultants and coordination with the Department.

Deliverables: Final progress report in PDF format

Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection (FDEP) within two weeks of submittal to confirm they are complete, accurate, and timely.

Task 3 – Project Coordination

Company Classification Hours Billable Rate Revenue

Gresham Smith (GS) Chief Engineer 40 $226.27 $9,050.80

Gresham Smith (GS) Project Manager 54 $171.92 $9,283.68

Gresham Smith (GS) Administrative 18 $83.38 $1,500.84

Page | 2

Total $19,835.32

Subtotal Task 3 $19,835.32

Reimbursable Total Cost for Task 3 $0.00

Total for Subtask 3 $19,835.32

Task 4: Post Beach Restoration Inspection and Load Rating

Description:

4A– Superstructure Load Rating: The Gresham Smith team will perform load rating of the existing superstructure for both Tram Bridges No. 1 and No. 2 based on the inspection after the beach renourishment project to verify the long-term suitability of the structure and to identify any required repairs. Primary load members are the precast concrete slabs.

4B – Substructure Load Rating: The Gresham Smith team will perform load rating of the existing substructure units for Tram Bridges No. 1 and No. 2 based on the inspection after the beach renourishment to verify the long-term suitability of the substructure and to identify any required repairs.

Primary load members are prestressed concrete piles and concrete pier caps.

4C – Post Beach Restoration Inspection: The Gresham Smith Team will provide an inspection of the two

Tram Bridges following the beach restoration project and verify that no additional damage has occurred based on previously documented conditions.

Deliverables:

4A: Bridge rating memorandum of the evaluation findings for the superstructure in PDF Format.

4B: A bridge rating memorandum of the evaluation findings for the substructure in PDF format.

4C: Bridge inspection report formatted similarly to December 2022 report by JGP Structures Group.

Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection (FDEP)

Subtask 4A – Superstructure Load Rating

Gresham Smith (GS) Chief Engineer 4 $226.27 $905.08

Gresham Smith (GS) Project Manager 4 $171.92 $687.68

Gresham Smith (GS) Project Engineer 24 $180.77 $4,338.48

Gresham Smith (GS) Engineer 32 $117.95 $3,774.40

Gresham Smith (GS) Structural Engineer 8 $202.01 $1,616.08

Total $11,321.72

Subtask 4B – Substructure Load Rating

Page | 3

Gresham Smith (GS) Chief Engineer 2 $226.27 $452.54

Gresham Smith (GS) Project Manager 4 $171.92 $687.68

Gresham Smith (GS) Project Engineer 20 $180.77 $3,615.40

Gresham Smith (GS) Engineer 24 $117.95 $2,830.80

Gresham Smith (GS) Structural Engineer 8 $202.01 $1,616.08

Total $9,202.50

Subtask 4C – Post Beach Restoration Inspection

Company Classification Hours Billable Rate Revenue

Gresham Smith (GS) Chief Engineer 3 $226.27 $678.81

Gresham Smith (GS) Project Manager 4 $171.92 $687.68

Gresham Smith (GS) Project Engineer 44 $180.77 $7,953.88

Gresham Smith (GS) Engineer 16 $117.95 $1,887.20

Gresham Smith (GS) Structural Engineer 24 $202.01 $4,848.24

Gresham Smith (GS) Administrative 4 $83.38 $333.52

Total $16,389.33

Subtotal Task 4 $36,913.55

Reimbursable Total Cost

Task Task Description Quantity Unit Unit Cost Total Cost

Subtask 4C – Post

Beach Restoration

Inspection

Rental Car 4 Days $80.000 $320.00

Fuel for Rental 40 gal $4.00 $160.00

Kayak Rental for

Pier Inspection 2 days $48.00 $96.00

Lodging (2staff/2 nights) 4 days $200.00 $800.00

Per Diem @staff/3

Days 6 days $40.00 $240.00

Total $1,616.00

Total for Task 4 $38,529.55

Task 5: Survey for Structural Improvements

Description: LiDAR Scanning & Bathymetric Survey

DRMP will be performing terrestrial LiDAR scans of a portion of the project site on Lover’s Key in Fort Myers, Florida. Utilizing a Trimble X7 scanner, DRMP will collect data on the four (4) areas as shown in the attached

Exhibit “A”. The resulting scans will be delivered as registered color point clouds in .LAS file format for each site.

DRMP shall also perform a bathymetric survey for the area shown on the attached exhibits below. The survey and

Page | 4 subsurface utility mapping effort will be performed in accordance with the State of Florida Standards of Practice, as set forth by the Board of Professional Surveyors and Mappers, Chapter 5J-17, Florida Administrative Code, pursuant to Section 472.027, Florida Statutes, and Underground Facility Damage Prevention and Safety Act, Chapter 556, Florida Statutes. All work shall conform to ASCE C-1 38 -02 utilizing quality levels A, B, C and D.

Services Include:

Terrestrial LiDAR Scanning of the four (4) of the five (5) individual sites (No scanning at the Tram Shelter

Site.)

QLB utility designation of the five (5) individual sites

Up to eight (8) soft digs - VVHs (Verified Vertical and Horizontal) o Please note – Fees listed for test holes are based on a single mobilization to address all conflicts.

Additional mobilizations (after the first request) for test holes will incur an additional mobilization fee to be agreed upon prior to any additional field work is performed.

Mapping of utilities/Drafting of designates within the project limits into an AutoCAD deliverable for all project services listed above

Page | 5

Registered color point clouds delivered in .LAS file format for each of the four (4) scan sites

ORD (DGN) file containing utility and bathymetric information

Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection

(FDEP) within two weeks of submittal to confirm they are complete, accurate, and timely.

Task 5 – Survey for Structural Improvements

DRMP Sr. Project Surveyor 2 $138.71 $277.42

DRMP Project Surveyor 8 $110.01 $880.08

DRMP

Staff Surveyor

(Surveyor in

Training)

80 $74.62 $5,969.60

DRMP

Three Man Survey

Crew 205 $150.00 $30,750.00

DRMP Secretary 1 $47.83 $47.83

Total $37,924.93

Subtotal Task 5 $37,924.93

Hotel (Total) at $175/night/person $6,475.00

Page | 6

Per Diem (Total) at $36 per person $1,512.00

Total Reimbursablefor Subtask 4 $7,987.00

Total for Task 5 $45,911.93

Subtask 6: Timber Boardwalk Design

Subtask 6A– 30% Design – Timber Boardwalk: The Gresham Smith team will perform the preliminary design for a timber boardwalk to replace the previous structure located between the western end of

Tram Bridge #1 and the beach. The boardwalk is anticipated to be approximately 400' long, a minimum of 8' wide, with a wider resting area located approximately midway on the boardwalk, similar to the previous structure. This task will include coordination with the surveyor to establish the survey needs and for file setup. A horizontal baseline will be established to minimize trimming of the existing mangrove trees. Vertical alignments will be investigated to compare the previous alignment and a higher alignment to minimize flooding potential. This subtask will include developing typical sections and establishing rail heights and cost estimates. Cost estimates will be developed for a full timber structure with a composite handrail and an option with a full composite deck and composite railing. A proposed design vehicle with axle loads will be submitted for approval, anticipated to be similar to a fully loaded 4-passenger John Deere Crossover XUV.

Subtask 6B – 60% Design – Timber Boardwalk – The Gresham Smith team will refine the preliminary bridge design based on 30% design review comments and selection of the final typical sections, construction materials, and final alignment. Gresham Smith will coordinate with the geotechnical engineer to establish the design parameters for the pilings and perform the final design of the bridge substructure. Evaluation of tie-down points will be completed, including the alignment of any ramps and approaches required, including a possible ADA ramp at the beach abutment to transition the bridge over any proposed dunes constructed as part of the beach renourishment project.

Subtask 6C –90% Design – Timber Boardwalk – The Gresham Smith Team will develop revised bridge plans, incorporating all required revisions and recommendations from the 60% design. A refined cost estimate, construction schedule, and contract special provisions will be developed.

Subtask 6D – Final Plan Submission – Timber Boardwalk – The Gresham Smith Team will provide final, sealed construction plans, including copies of all design calculations and reports developed for the design.

6A: 30% Bridge Plans will be delivered for review, including cost estimates and comparisons for timber and composite deck designs.

6B: 60% Bridge Plans will be delivered for review, including the results from the geotechnical evaluation.

6C: 90% Bridge Plans will be delivered for final approval by FDEP, including required special provisions and construction requirements.

6D: Final sealed construction plans and special provisions, suitable for bidding.

Page | 7

Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection

Subtask 6A – 30% Design - Timber Boardwalk

Gresham Smith (GS) Chief Engineer 6 $226.27 $1,357.62

Gresham Smith (GS) Project Manager 6 $171.92 $1,031.52

Gresham Smith (GS) Project Engineer 68 $180.77 $12,292.36

Gresham Smith (GS) Engineer 140 $117.95 $16,513.00

Gresham Smith (GS) Structural Engineer 44 $202.01 $8,888.44

Gresham Smith (GS) Administrative 2 $83.38 $166.76

Total $40,249.70

Subtask 6B – 60% Design - Timber Boardwalk

Company Classification Hours Billable Rate Revenue

Gresham Smith (GS) Chief Engineer 4 $226.27 $905.08

Gresham Smith (GS) Project Manager 8 $171.92 $1,375.36

Gresham Smith (GS) Project Engineer 100 $180.77 $18,077.00

Gresham Smith (GS) Engineer 156 $117.95 $18,400.20

Gresham Smith (GS) Structural Engineer 68 $202.01 $13,736.68

336 Total $52,494.32

Gresham Smith (GS) Chief Engineer 2 $226.27 $452.54

Gresham Smith (GS) Project Manager 4 $171.92 $687.68

Gresham Smith (GS) Project Engineer 44 $180.77 $7,953.88

Gresham Smith (GS) Engineer 152 $117.95 $17,928.40

Gresham Smith (GS) Structural Engineer 56 $202.01 $11,312.56

Gresham Smith (GS) Administrative 4 $83.38 $333.52

Total $38,668.58

Subtask 6D – Final Plan Submission - Timber Boardwalk

Company Classification Hours Billable Rate Revenue

Gresham Smith (GS) Chief Engineer 4 $226.27 $905.08

Gresham Smith (GS) Project Engineer 44 $180.77 $7,953.88

Gresham Smith (GS) Engineer 48 $117.95 $5,661.60

Gresham Smith (GS) Structural Engineer 20 $202.01 $4,040.20

Total $18,560.76

Subtotal Task 6 $149,973.36

Reimbursable Total Cost for Task 6 $0.00

Total for Task 6 $149,973.36

Page | 8

Task 7: Utilities

Subtask 7A -Utility Design: Design of approximately 3,200 linear feet of force main to connect the new residence to the existing lift station and 1,500 linear feet of force main to connect the new ranger station to the existing county system along Estero Boulevard. Design of water service connections for the new residence, ranger station, and gift shop/concession building.

Subtask 7B - Provide utility coordination with the Bonita Springs Utilities, Lee County Utilities, Centurylink, Comcast, Crown Castle, and Florida Power and Light. Provide Utility conflict matrix.

7A: Copies of utility plans and design documents in PDF format

7B: Copies of all Utility Coordination and Utility Matrix in PDF format

Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection (FDEP)

Subtask 7A – Utility Design

Gresham Smith (GS) Chief Engineer 6 $226.27 $1,357.62

Gresham Smith (GS) Project Manager 44 $171.92 $7,564.48

Gresham Smith (GS) Project Engineer 50 $180.77 $9,038.50

Gresham Smith (GS) Engineer 60 $117.95 $7,077.00

Gresham Smith (GS) Administrative 0 $83.38 $0.00

Total $25,037.60

Subtask 7B – Utility Coordination

Company Classification Hours Billable Rate Revenue

Gresham Smith (GS) Chief Engineer 10 $226.27 $2,262.70

Gresham Smith (GS) Project Manager 50 $171.92 $8,596.00

Gresham Smith (GS) Project Engineer 44 $180.77 $7,953.88

Gresham Smith (GS) Engineer 34 $117.95 $4,010.30

Gresham Smith (GS) Administrative 0 $83.38 $0.00

Total $22,822.88

Subtotal Task 7 $47,860.48

Reimbursable Total Cost for Task 7 $0.00

Total for Task 7 $47,860.48

Page | 9

Task 8: Geotechnical Services

Description: As part of the geotechnical services, Terracon will:

Obtain Lee County Soil Boring and Vegetation Removal Permits

Perform two (2) borings to a depth of 50 feet each for the HDD. These borings will include continuous sampling at 2-foot intervals.

Perform two (2) borings to a depth of 50 feet each for the boardwalk

Perform one (1) boring to a depth of 50 feet for the ranger station

Perform one (1) boring to a depth of 50 feet for the residence building

Perform three (3) borings to a depth of 50 feet each for the gift shop

Perform laboratory testing services

Provide earthwork recommendations for subgrade preparation

Provide geotechnical recommendations for floor slabs

Provide geotechnical recommendations for either driven or augercast pile foundations. We will include axial and lateral capacity for up to 3 pile diameters for each pile type.

Provide geotechnical recommendations for lateral earth pressures and shear modulus associated with the HDD

Deliverables: Copy of all geotechnical service documents

Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection

Task 8– Geotechnical Engineering

Terracon Principal Engineer 8 $181.74 $1,453.92

Terracon Senior Project

Engineer 16 $145.47 $2,327.52

Terracon Staff Engineer 30 $60.84 $1,825.20

Terracon Secretary 2 $54.75 $109.50

Total $5,716.14

Laboratory Testing Services EA

Terracon 816 - Moisture

Content 20 $20.00 $400.00

Terracon 812 - Wash #200 20 $75.00 $1,500.00

Terracon 811 - Liquid Limits 5 $60.00 $300.00

Terracon 826 - Plastic Limits and Plasticity Index 5 $60.00 $300.00

Total $2,500.00

Standard Penetration Test Borings FEET

Terracon 473 - 9 Borings @

50' Deep 450 $23.00 $10,350.00

Page | 10

Terracon 422 - Extra Samples 24 $60.00 $1,440.00

Terracon 483 - Temporary 3”

Casing 270 $14.00 $3,780.00

Terracon 419 - Hole-to-Hole

Moves 12 $200.00 $2,400.00

Terracon

435 - Grout Seal

Boreholes (less than

4") 0 to 50' borings

450 $8.00 $3,600.00

Total $21,570.00

GEO Drill Crew DAY

Terracon

610 - Mobilization

Drill Rig Track

Mount

1 $3,000.00 $3,000.00

Terracon 418 - Geo Drill Crew

Support Vehicle 7 $175.00 $1,225.00

Terracon Total $4,225.00

Private Utility Locating DAY

Terracon PUI Locate 2 $1,500.00 $3,000.00

Total $3,000.00

Subtotal Task 8 $37,011.14

Per Diem for Drill Crew + Hotel (47days) $3,500.00

Lee County Drilling Permitting (first 4 borings) $200.00

Lee County Drilling Permitting (every boring after first 4) ($50 each x 5) $250.00

Lee County Vegetation Permitting $39.00

Total Reimbursable for Task 8 $3,989.00

Total for Task 8 $41,000.14

Task 9 – Tram Station Pavilion

Description

Subtask 9A - Tram Station 30% Design Documents: This phase includes the Architectural and services necessary to develop the design for the Tram Station Pavilion. More specifically, the work of this sub-phase includes the following:

o Procure As-Built drawings from the client for the existing Tram Station Pavilion.

o Due diligence investigations, preliminary code research, and evaluation.

o Identify all permitting requirements.

Page | 11 o 30% In-House Rough Order of Magnitude (ROM) Cost Estimate.

Subtask 9B - Tram Station 90% Design Documents (Permit Issuance): This phase includes the Architectural and Structural services necessary to further develop the design for the Tram Station Pavilion after review and approval of the 30% design documents by the client. Haskell will proceed with this phase of the work upon completion of Subtask 9A. More specifically, the work includes the following:

o Complete all design drawings and specifications.

o Finalize peer review checks.

o Present permit design package to the client for approval.

o Submit 90% Permit Issue Drawing package for Permit.

o Complete 90% (Final) In-House Cost Estimate.

Subtask 9C - Tram Station Final Construction Documents: This phase includes the Architectural and Structural services necessary to finalize the design for the Tram Station Pavilion after the review and approval of 90% design documents by the client. Haskell will proceed with this phase of the work upon completion of Subtask

9B. More specifically, the work includes the following:

o Incorporate all final permit comments and resubmit documents if necessary.

o Obtain Final Building Permit.

o Issue Construction Documents after final building permit approval, to include 100% design drawings and specifications. Present the completed design to the client for final approval.

Deliverables

9A: 30% Design Documents will be provided for the Tram Station Pavilion. The following documents/drawings will be submitted to the client for review at 30%. Preliminary plans will be developed in a digital BIM model using REVIT software. The drawings will be produced as native 24x36 documents, and copies of the 30% design documents will be provided to the client in electronic format as PDF files. They will likely include, but are not limited to the following:

o Architectural: Specifications TOC, Preliminary Cover sheet, General Information & Notes, Pavilion

Plan, Reflected Ceiling Plan, Roof Plan, and Elevations.

o Structural: Specifications TOC, General Notes, Foundation Plan, Roof Framing Plan, Foundation

Details and Roof Framing Details.

o Estimating: 30% Cost Estimate report with CSI Divisional cost breakdown.

9B: 90% (Permit Issue) Design Documents will be provided for the Tram Station Pavilion. The following documents/drawings will be submitted to the client for review at 90%. The drawings will be produced as native 24x36 documents, and copies of the 90% design documents will be provided to the client in electronic format as PDF files. They will likely include, but are not limited to the following:

o Architectural: Final Specifications, Cover sheet, General Information & Notes, Pavilion Plan, Reflected Ceiling Plan, Roof Plan, Elevations, and Roof & Column Details.

o Structural: Final Specifications, General Notes, Foundation Plan, Roof Framing Plan, Foundation

Page | 12

Details and Roof Framing Details.

o Estimating: Final Cost Estimate report with CSI Divisional cost breakdown.

9C: Final Construction Design Documents will be provided for the Tram Station Pavilion. The following documents/drawings will be submitted to the client for review at 100%. The drawings will be produced as native 24x36 documents, and copies of the Final Construction design documents will be provided to the client in electronic format as PDF files. A signed and sealed set will be provided upon request. They will include the following:

o Revised Permit Package Documents.

o Receipt of all permits for construction.

o Final Construction Drawing Package and Specifications delivered to the client.

Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection

Subtask 9A - Tram Station 30% Design Documents

Haskell Design Director 2 $235.00 $470.00

Haskell Design Manager 10 $161.99 $1,619.90

Haskell BIM Specialist 6 $144.98 $869.88

Haskell SME Architect 5 $206.99 $1,034.95

Haskell Project Architect II 8 $121.00 $968.00

Haskell Arch. Design

Associate II 16 $94.00 $1,504.00

Haskell Group Lead Struct.

Engineer 8 $213.00 $1,704.00

Haskell Project Coordinator 3 $119.98 $359.94

Haskell Administrative

Support 4 $80.00 $320.00

Total $8,850.67

Subtask 9B - Tram Station 90% Design Documents (Permit Issuance)

Company Classification Hours Billable Rate Revenue

Haskell Design Director 2 $235.00 $470.00

Haskell Design Manager 26 $161.99 $4,211.74

Haskell SME Architect 3 $206.99 $620.97

Haskell Project Architect II 12 $121.00 $1,452.00

Haskell Arch. Design

Associate II 24 $94.00 $2,256.00

Haskell Group Lead Struct.

Engineer 6 $213.00 $1,278.00

Page | 13

Haskell Sr. Structural

Designer 32 $152.00 $4,864.00

Haskell Project Coordinator 4 $119.98 $479.92

Haskell Administrative

Support 8 $80.00 $640.00

Total $16,272.63

Subtask 9C - Tram Station Final Construction Documents

Company Classification Hours Billable Rate Revenue

Haskell Design Director 1 $235.00 $235.00

Haskell Design Manager 12 $161.99 $1,943.88

Haskell SME Architect 1 $206.99 $206.99

Haskell Project Architect II 4 $121.00 $484.00

Haskell Arch. Design

Associate II 8 $94.00 $752.00

Haskell Group Lead Struct.

Engineer 1 $213.00 $213.00

Haskell Sr. Structural

Designer 13 $152.00 $1,976.00

Haskell Project Coordinator 3 $119.98 $359.94

Haskell Administrative

Support 6 $80.00 $480.00

Total $6,650.81

Subtotal Task 9 $31,774.11

9A -Printing, Postage, Reprographics $500.00

9B - Printing, Postage, Reprographics $500.00

9C - Printing, Postage, Reprographics $500.00

Total Reimbursablefor Subtask 8 $1,500.00

Total for Task 9 $33,274.11

Task 10 – Residence Building

Subtask 10A - Residence Concepts: Based on the initial site visit and the client's expressed goals and vision for the proposed restorations, Haskell will provide the Architectural services necessary to produce two (2) conceptual design options for the Residence Building. More specifically, the work of this sub-phase includes the following:

Page | 14 o Coordination with Lee County Building Department to determine the allowability of double occupancy duplex residence.

o Confirm the design program with the client for the Residence building option(s).

o Procure "Keys" concept floor plans from the client.

o Produce two (2) conceptual design options for a single occupancy residence and a double occupancy duplex residence (Preferred- if Lee County Building Department approves).

Subtask 10B - Residence 30% Design Documents: This phase includes the Architectural, Structural, and MEP, and Estimateing services necessary to develop further the design for the chosen concept of the Residence

Building. Haskell will proceed with this phase of the work upon completion and approval of deliverable items listed in Subtask 10A. More specifically, the work of this sub-phase includes the following:

o Procure Geotechnical report and site survey information from Gresham Smith.

o Due diligence investigations, preliminary code research, and evaluation.

Subtask 10C - Residence 90% Design Documents (Permit Issuance): This phase includes the Architectural, Structural, MEP, and Estimating services necessary to further develop the design for the Residential Building after review and approval of 30% design documents by the client. Haskell will proceed with this phase of the work upon completion of Subtask 10B. More specifically, the work includes the following:

o Complete all design drawings and specifications.

o Finalize peer review checks.

o Present permit design package to client for approval.

Subtask 10D - Residence Final Construction Documents: This phase includes the Architectural, Structural, MEP, and Estimating ervices necessary to finalize the design for the Residence Building after the review and approval of 90% design documents by the client. Haskell will proceed with this phase of the work upon completion of Subtask 10C. More specifically, the work includes the following:

o Incorporate all final permit comments and resubmit documents if necessary.

o Obtain Final Building Permit.

o Issue Construction Documents after final building permit approval, to include 100% design drawings and specifications. Present completed design to client for final approval.

10A: The following documents/drawings will be provided for two (2) conceptual options for the Residence

Building. The following drawings will be submitted to the client for review and approval before proceeding to the next phase. Preliminary plans will be developed in a digital BIM model using REVIT software. The drawings will be produced as native 24x36 documents, and copies of the Pre-Design documents will be

Page | 15 provided to the client in electronic format as PDF files:

o Scaled and dimensioned concept Floor Plan of the 3 bedroom/2 bathroom Single Occupancy

Residence Building (approx. 1,400sf) based on "Keys" template (provided by client) with companion square foot spreadsheet tabulation.

o Scaled and dimensioned concept Floor Plan of the 2 bedroom/2 bathroom Double Occupancy

Duplex Building (approx. 1,100sf each) based on the "Keys" template (provided by client) with companion square foot spreadsheet tabulation.

10B: 30% Design Documents will be provided for the selected option of the Residence Building. The following drawings will be submitted to the client for review at 30%. The drawings will be produced as native

24x36 documents, and copies of the 30% design documents will be provided to the client in electronic format as PDF files. They will likely include, but are not limited to the following:

o Architectural: Specification TOC, Preliminary Cover sheet, General Information & Notes, Life Safety

Cover Sheet & Plan, Floor Plan, Reflected Ceiling Plan, Roof Plan, Building Elevations, Wall Sections, Enlarged Plans (if required), Casework Plans (if required), Roof Details, Wall Types, ADA

Requirements, Door, Window, and Hardware Schedules, and Interior Finishes Plan & Schedule.

o Structural: Specifications TOC, General Notes, Foundation Plan, Elevated Floor Plan Sheet, Roof

Framing Plan, Foundation Details, and Roof Framing Details.

o Mechanical: Specifications TOC, Legend, Abbreviations, & General Notes, and HVAC Floor Plan.

o Electrical: Specifications TOC, Preliminary Symbol Legend, General Notes, Plans, Load Calculations, and Power Riser Diagram(s).

o Plumbing: Specifications TOC, Legend, Abbreviations, & General Notes, and Plumbing Gravity Piping

Floor Plan.

o 30% Cost Estimate report with CSI Divisional cost breakdown.

10C: 90% (Permit Issue) Design Documents will be provided for the Residence Building. The following documents/drawings will be submitted to the client for review at 90%. The drawings will be produced as native 24x36 documents, and copies of the 90% design documents will be provided to the client in electronic format as PDF files. They will likely include, but are not limited to the following:

o Architectural: Final Specifications, Cover sheet, General Information & Notes, Life Safety Cover Sheet

& Plan, Floor Plan, Reflected Ceiling Plan, Roof Plan, Building Elevations, Wall Sections, Enlarged

Plans (if required), Casework Plans (if required), Roof Details, Wall Types, ADA Requirements, Door, Window, and Hardware Schedules, and Interior Finishes Plan & Schedule.

o Structural: Final Specifications, General Notes, Foundation Plan, Elevated Floor Plan Sheet, Roof

Framing Plan, Foundation Details, and Roof Framing Details.

o Mechanical: Final Specifications, Legend, Abbreviations, & General Notes, HVAC Floor Plan, HVAC

Equipment Schedule, and HVAC Details.

o Electrical: Final Specifications on Drawings, Symbol Legend, General Notes, Plans, Load Calculations, Power Riser Diagram(s), Schedule, and Details.

o Plumbing: Final Specifications, Legend, Abbreviations, & General Notes, Plumbing Gravity Piping

Floor Plan, Plumbing Pressure Piping Plan, Plumbing Fixture Schedule, and Plumbing Details.

Page | 16

10D: Final Construction Design Documents will be provided for the Residence Building. The following documents/drawings will be submitted to the client for review at 100%. The drawings will be produced as native 24x36 documents, and copies of the Final Construction design documents will be provided to the client in electronic format as PDF files. A signed and sealed set will be provided upon request. They will include the following:

o Revised Permit Package Documents.

o Receipt of all permits for construction.

o Final Construction Drawing Package and Specifications delivered to the client.

Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection

Subtask 10A - Residence Concepts

Haskell Design Director 1 $235.00 $235.00

Haskell Design Manager 8 $161.99 $1,295.92

Haskell BIM Specialist 10 $144.98 $1,449.80

Haskell SME Architect 1 $206.99 $206.99

Haskell Project Architect II 4 $121.00 $484.00

Haskell Arch. Design

Associate II 16 $94.00 $1,504.00

Haskell Project Coordinator 2 $119.98 $239.96

Haskell Administrative

Support 4 $80.00 $320.00

Total $5,735.67

Subtask 10B - Residence 30% DesignDocuments

Company Classification Hours Billable Rate Revenue

Haskell Design Director 4 $235.00 $940.00

Haskell Design Manager 23 $161.99 $3,725.77

Haskell SME Architect 8 $206.99 $1,655.92

Haskell Project Architect II 8 $121.00 $968.00

Haskell Arch. Design

Associate II 32 $94.00 $3,008.00

Haskell Sr. Fire Protection

Engineer 8 $177.99 $1,423.92

Haskell Group Lead Struct.

8 $213.00 $1,704.00

Page | 17

Sr. Electrical

Engineer 4 $190.00 $760.00

Haskell Elect. Design

Associate I 8 $85.00 $680.00

Haskell Group Lead Mech.

Engineer 16 $208.00 $3,328.00

Haskell Sr. Mechanical

Designer 16 $152.00 $2,432.00

Haskell Group Lead Plumb.

Engineer 10 $208.00 $2,080.00

Haskell Plumbing Design

Associate I 16 $85.00 $1,360.00

Haskell Project Coordinator 8 $119.98 $959.84

Haskell Administrative

Support 6 $80.00 $480.00

Total $25,505.45

Subtask 10C - 90% Residence Design Documents (Permit Issuance)

Company Classification Hours Billable Rate Revenue

Haskell Design Director 4 $235.00 $940.00

Haskell Design Manager 36 $161.99 $5,831.64

Haskell SME Architect 12 $206.99 $2,483.88

Haskell Project Architect II 20 $121.00 $2,420.00

Haskell Arch. Design

Associate II 60 $94.00 $5,640.00

Haskell Sr. Fire Protection

Engineer 4 $177.99 $711.96

Haskell Group Lead Struct.

Engineer 14 $213.00 $2,982.00

Haskell Sr. Structural

Designer 52 $152.00 $7,904.00

Haskell Sr. Electrical

Engineer 12 $190.00 $2,280.00

Haskell Elect. Design

Associate I 24 $85.00 $2,040.00

Haskell Group Lead Mech.

Engineer 8 $208.00 $1,664.00

Haskell Sr. Mechanical

Designer 24 $152.00 $3,648.00

Haskell Group Lead Plumb.

12 $208.00 $2,496.00

Page | 18

Plumbing Design

Associate I 32 $85.00 $2,720.00

Haskell Project Coordinator 12 $119.98 $1,439.76

Haskell Administrative

Support 16 $80.00 $1,280.00

Total $46,481.24

Subtask 10D - Residence Final Construction Documents

Company Classification Hours Billable Rate Revenue

Haskell Design Director 1 $235.00 $235.00

Haskell Design Manager 8 $161.99 $1,295.92

Haskell SME Architect 2 $206.99 $413.98

Haskell Project Architect II 8 $121.00 $968.00

Haskell Arch. Design

Associate II 20 $94.00 $1,880.00

Haskell Sr. Fire Protection

Engineer 1 $177.99 $177.99

Haskell Group Lead Struct.

Engineer 2 $213.00 $426.00

Haskell Sr. Structural

Designer 22 $152.00 $3,344.00

Haskell Sr. Electrical

Engineer 4 $190.00 $760.00

Haskell Elect. Design

Associate I 8 $85.00 $680.00

Haskell Group Lead Mech.

Engineer 8 $208.00 $1,664.00

Haskell Sr. Mechanical

Designer 8 $152.00 $1,216.00

Haskell Group Lead Plumb.

Engineer 8 $208.00 $1,664.00

Haskell Plumbing Design

Associate I 8 $85.00 $680.00

Haskell Project Coordinator 2 $119.98 $239.96

Haskell Administrative 6 $80.00 $480.00

Total $16,124.85

Subtotal Task 10 $93,847.21

10A - Printing, Postage, Reprographics $500.00

10B - Printing, Postage, Reprographics $750.00

Page | 19

10C - Printing, Postage, Reprographics $750.00

10D - Printing, Postage, Reprographics $750.00

Total Reimbursablefor Task 10 $2,750.00

Total for Task 10 $96,597.21

Task 11 – Concession/Gift Shop Building

Subtask 11A - Concession/Gift Shop Concepts: Based on the initial site visit and the client's expressed goals and vision for the proposed restorations, Haskell will provide the Architectural services necessary to produce a conceptual plan for the Concession/Gift Shop Building showing a floor plan and connections to existing raised restrooms adjacent to the proposed location of the building. More specifically, the work of this sub-phase includes the following:

o Procure concept floor plan from the client.

o Produce concept plan for review and approval by the client.

Subtask 11B - Concession/Gift Shop 30% Design Documents: This phase includes the Architectural, Structural, and MEP services necessary to develop further the design for the Concession/Gift Shop Building. Haskell will proceed with this phase of the work upon completion and approval of deliverable items listed in Subtask 10A.

More specifically, the work of this sub-phase includes the following:

o Procure Geotechnical report and site survey information from Gresham Smith.

o Due diligence investigations, preliminary code research, and evaluation.

Subtask 11C - Concession/Gift Shop 90% Design Documents (Permit Issuance): This phase includes the

Architectural, Structural, and MEP services necessary to further develop the design for the Concession/Gift

Shop Building after review and approval of 30% design documents by the client. Haskell will proceed with this phase of the work upon completion of Subtask 11B. More specifically, the work includes the following:

o Advance and complete all specifications and design drawings listed in Task 11B to incorporate review comments from the client from the previous phase.

o Finalize peer review checks.

o Present permit design package to the client for approval.

Subtask 11D - Concession/Gift Shop Final Construction Documents: This phase includes the Architectural, Structural, and MEP services necessary to finalize the design for the Concession/Gift Shop Building after review and approval of 90% design documents by the client. Haskell will proceed with this phase of the work

Page | 20 upon completion of Subtask 11C. More specifically, the work includes the following:

o Incorporate all final permit comments and resubmit documents if necessary.

o Obtain Final Building Permit.

and specifications. Present the completed design to the client for final approval.

11A: Conceptual Pre-Design Documents will be provided for the Concession/Gift Shop Building. The following drawing(s) will be submitted to the client for review and approval before proceeding to the next phase. Preliminary plans will be developed in a digital BIM model using REVIT software. The drawings will be produced as native 24x36 documents, and copies of the Pre-Design documents will be provided to the client in electronic format as PDF files:

o Scaled and dimensioned concept Floor Plan with companion square foot spreadsheet tabulation to include conceptual layout for raised walkways connecting to existing restroom facility and ramps down to grade.

11B: 30% Design Documents will be provided for the Concession/Gift Shop Building. The following drawings will be submitted to the client for review at 30%. The drawings will be produced as native 24x36 documents, and copies of the 30% design documents will be provided to the client in electronic format as PDF files. They will likely include, but are not limited to the following:

o Architectural: Specifications TOC, Preliminary Cover sheet, General Information & Notes, Life Safety

Cover Sheet & Plan, Floor Plan, Reflected Ceiling Plan, Roof Plan, Building Elevations, Wall Sections, Plans, Elevations, & Sections for Elevated Walkways/Ramps, Enlarged Plans (if required), Casework

Plans (if required), Roof Details, Wall Types, ADA Requirements, Door, Window, and Hardware

Schedules, and Interior Finishes Plan & Schedule.

o Structural: Specifications TOC, General Notes, Foundation Plan, Elevated Floor Plan Sheet, Roof

Framing Plan, Foundation Details, and Roof Framing Details.

o Mechanical: Specifications TOC, Legend, Abbreviations, & General Notes, and HVAC Floor Plan o Electrical: Specifications TOC, Symbols Legend, General Notes, Lighting Plans, Power Plans, System

Plan, Load Calculations, and Preliminary Power Riser Diagram(s).

o Plumbing: Specifications TOC, Legend, Abbreviations, & General Notes, and Plumbing Gravity Piping

11C: 90% (Permit Issue) Design Documents will be provided for the Concession/Gift Shop Building. The following documents/drawings will be submitted to the client for review at 90%. The drawings will be produced as native 24x36 documents, and copies of the 90% design documents will be provided to the client in electronic format as PDF files. They will likely include, but are not limited to the following:

o Architectural: Final Specifications, Cover sheet, General Information & Notes, Life Safety Cover Sheet

& Plan, Floor Plan, Reflected Ceiling Plan, Roof Plan, Building Elevations, Wall Sections, Plans, Page | 21

Elevations, & Sections for Elevated Walkways/Ramps, Enlarged Plans (if required), Casework Plans (if required), Roof Details, Wall Types, ADA Requirements, Door, Window, and Hardware Schedules, and Interior Finishes Plan & Schedule.

o Structural: Final Specifications, General Notes, Foundation Plan, Elevated Floor Plan Sheet, Roof

Framing Plan, Foundation Details, and Roof Framing Details.

o Mechanical: Final Specifications, Legend, Abbreviations, & General Notes, HVAC Floor Plan, HVAC

Equipment Schedule, and HVAC Details.

o Electrical: Final Specifications on Drawings, Symbols Legend, General Notes, Lighting Plans, Power

Plans, System Plan, Load Calculations, Power Riser Diagram(s), Schedule, and Details.

o Plumbing: Final Specifications, Legend, Abbreviations, & General Notes, Plumbing Gravity Piping

11D: Final Construction Design Documents will be provided for the Concession/Gift Shop Building. The following documents/drawings will be submitted to the client for review at 100%. The drawings will be produced as native 24x36 documents, and copies of the Final Construction design documents will be provided to the client in electronic format as PDF files. A signed and sealed set will be provided upon request.

They will include the following:

o Revised Permit Package Documents.

o Final Construction Drawing Package and Specifications delivered to client.

Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection

Subtask 11A - Concession/Gift Shop Concepts

Haskell Design Director 1 $235.00 $235.00

Haskell Design Manager 8 $161.99 $1,295.92

Haskell BIM Specialist 10 $144.98 $1,449.80

Haskell SME Architect 1 $206.99 $206.99

Haskell Project Architect II 20 $121.00 $2,420.00

Haskell Arch. Design

Associate II 40 $94.00 $3,760.00

Haskell Project Coordinator 2 $119.98 $239.96

Haskell Administrative

Support 4 $80.00 $320.00

Total $9,927.67

Subtask 11B Concession/Gift Shop 30% Design

Haskell Design Director 4 $235.00 $940.00

Page | 22

Haskell Design Manager 23 $161.99 $3,725.77

Haskell SME Architect 8 $206.99 $1,655.92

Haskell Project Architect II 24 $121.00 $2,904.00

Haskell Arch. Design

Associate II 80 $94.00 $7,520.00

Haskell Sr. Fire Protection

Engineer 8 $177.99 $1,423.92

Haskell Group Lead Struct.

Engineer 8 $213.00 $1,704.00

Haskell Sr. Electrical

Engineer 12 $190.00 $2,280.00

Haskell Elect. Design

Associate I 8 $85.00 $680.00

Haskell Group Lead Mech.

Engineer 8 $208.00 $1,664.00

Haskell Sr. Mechanical

Designer 16 $152.00 $2,432.00

Haskell Group Lead Plumb.

Engineer 12 $208.00 $2,496.00

Haskell Plumbing Design

Associate I 16 $85.00 $1,360.00

Haskell Project Coordinator 8 $119.98 $959.84

Haskell Administrative

Support 6 $80.00 $480.00

Total $32,225.45

Subtask 11C Concession/Gift Shop 90% Design (Permit Issuance)

Company Classification Hours Billable Rate Revenue

Haskell Design Director 4 $235.00 $940.00

Haskell Design Manager 36 $161.99 $5,831.64

Haskell SME Architect 12 $206.99 $2,483.88

Haskell Project Architect II 40 $121.00 $4,840.00

Haskell Arch. Design

Associate II 180 $94.00 $16,920.00

Haskell Sr. Fire Protection

Engineer 4 $177.99 $711.96

Haskell Group Lead Struct.

Engineer 14 $213.00 $2,982.00

Haskell Sr. Structural

Designer 52 $152.00 $7,904.00

Page | 23

Sr. Electrical

Engineer 30 $190.00 $5,700.00

Haskell Elect. Design

Associate I 32 $85.00 $2,720.00

Haskell Group Lead Mech.

Engineer 16 $208.00 $3,328.00

Haskell Sr. Mechanical

Designer 12 $152.00 $1,824.00

Haskell Group Lead Plumb.

Engineer 8 $208.00 $1,664.00

Haskell Plumbing Design

Associate I 16 $85.00 $1,360.00

Haskell Project

Coordination 12 $119.98 $1,439.76

Haskell Administrative

Support 16 $80.00 $1,280.00

Total $61,929.24

Subtask 11D Concession/Gift Shop Final Construction Documents

Company Classification Hours Billable Rate Revenue

Haskell Design Director 1 $235.00 $235.00

Haskell Design Manager 8 $161.99 $1,295.92

Haskell SME Architect 2 $206.99 $413.98

Haskell Project Architect II 24 $121.00 $2,904.00

Haskell Arch. Design

Associate II 40 $94.00 $3,760.00

Haskell Sr. Fire Protection

Engineer 1 $177.99 $177.99

Haskell Group Lead Struct.

Engineer 2 $213.00 $426.00

Haskell Sr. Structural

Designer 22 $152.00 $3,344.00

Haskell Sr. Electrical

Engineer 8 $190.00 $1,520.00

Haskell Elect. Design

Associate I 8 $85.00 $680.00

Haskell Group Lead Mech.

Engineer 4 $208.00 $832.00

Haskell Sr. Mechanical

Designer 8 $152.00 $1,216.00

Page | 24

Group Lead Plumb.

Engineer 4 $208.00 $832.00

Haskell Plumbing Design

Associate I 8 $85.00 $680.00

Haskell Project

Coordination 2 $119.98 $239.96

Haskell Administrative

Support 6 $80.00 $480.00

Total $19,036.85

Subtotal Task 11 $123,119.21

11A -Printing, Postage, Reprographics $500.00

11B - Printing, Postage, Reprographics $750.00

11D - Printing, Postage, Reprographics $750.00

11C - Printing, Postage, Reprographics $750.00

Total Reimbursablefor Task 11 $2,750.00

Total for Task 11 $125,869.21

Task 12 – Ranger Station

Subtask 12A - Ranger Station 30% Design Documents: This phase includes the Architectural, Structural, and

MEP services necessary to develop the design for the Ranger Station Building. More specifically, the work of this sub-phase includes the following:

o Procure Geotechnical report and site survey information from Gresham Smith.

o Due diligence investigations, preliminary code research, and evaluation.

o Identify all permitting requirements.

o Procure Ranger Station Concept Plan from the client.

Subtask 12B - Ranger Station 90% Design Documents (Permit Issuance): This phase includes the Architectural, Structural, and MEP services necessary to further develop the design for the Ranger Station Building after review and approval of 30% design documents by the client. Haskell will proceed with this phase of the work upon completion of Subtask 12A. More specifically, the work includes the following:

o Advance and complete all specifications and design drawings listed in Task 12A to incorporate review comments from the client from the previous phase.

o Finalize peer review checks.

o Present permit design package to the client for approval.

Page | 25

Subtask 12C - Ranger Station Final Construction Documents: This phase includes the Architectural, Structural, and MEP services necessary to finalize the design for the Ranger Station Building after the client's review and approval of the 90% design documents. Haskell will proceed with this phase of the work upon completion of

Subtask 11B. More specifically, the work includes the following:

o Incorporate all final permit comments and resubmit documents if necessary.

o Obtain Final Building Permit.

12A: 30% Design Documents will be provided for the Ranger Station Building. The following drawings will be submitted to the client for review at 30%. Preliminary plans will be developed in a digital BIM model using

REVIT software. The drawings will be produced as native 24x36 documents, and copies of the 30% design documents will be provided to the client in electronic format as PDF files. They will likely include, but are not limited to the following:

o Architectural: Outline Specifications, Cover sheet, General Information & Notes, Life Safety Cover

Sheet & Plan, Floor Plan, Reflected Ceiling Plan, Roof Plan, Building Elevations, Wall Sections, Enlarged Plans (if required), Casework Plans (if required), Roof Details, Wall Types, ADA

Requirements, Door, Window, and Hardware Schedules, and Interior Finishes Plan & Schedule.

o Structural: Specifications TOC, Preliminary General Notes, Foundation Plan, Roof Framing Plan, Foundation Details, and Roof Framing Details.

o Mechanical: Specifications TOC, Legend, Abbreviations, & General Notes, and HVAC Floor Plan o Electrical: Specifications TOC, Symbol Legend, General Notes, Lighting Plans, Power Plans, System

Plans, Load Calculations, and Preliminary Power Riser Diagram(s).

o Plumbing: Specifications TOC, Legend, Abbreviations, & General Notes, and Plumbing Gravity Piping

12B: 90% (Permit Issue) Design Documents will be provided for the Ranger Station Building. The following documents/drawings will be submitted to the client for review at 90%. The drawings will be produced as native 24x36 documents, and copies of the 90% design documents will be provided to the client in electronic format as PDF files. They will likely include, but are not limited to the following:

o Architectural: Final Specifications, Cover sheet, General Information & Notes, Life Safety Cover Sheet

& Plan, Floor Plan, Reflected Ceiling Plan, Roof Plan, Building Elevations, Wall Sections, Enlarged

Plans (if required), Casework Plans (if required), Roof Details, Wall Types, ADA Requirements, Door, Window, and Hardware Schedules, and Interior Finishes Plan & Schedule o Structural: Final Specifications, General Notes, Foundation Plan, Roof Framing Plan, Foundation

Page | 26

Details, and Roof Framing Details.

o Mechanical: Final Specifications, Legend, Abbreviations, & General Notes, HVAC Floor Plan, HVAC

Equipment Schedule, and HVAC Details.

o Electrical: Final Specifications on Drawings, Symbol Legend, General Notes, Lighting Plans, Power

Plans, System Plans, Load Calculations, Power Riser Diagram, Schedule, and Details.

o Plumbing: Final Specifications, Legend, Abbreviations, & General Notes, Plumbing Gravity Piping

12C: Final Construction Design Documents will be provided for the Ranger Station Building. The following documents/drawings will be submitted to the client for review at 100%. The drawings will be produced as native 24x36 documents, and copies of the Final Construction design documents will be provided to the client in electronic format as PDF files. A signed and sealed set will be provided upon request. They will include the following:

o Revised Permit Package Documents.

Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection

Subtask 12A Ranger Station 30% Design

Haskell Design Director 4 $235.00 $940.00

Haskell Design Manager 23 $161.99 $3,725.77

Haskell BIM Specialist 8 $144.98 $1,159.84

Haskell SME Architect 8 $206.99 $1,655.92

Haskell Project Architect II 16 $121.00 $1,936.00

Haskell Arch. Design

Associate II 32 $94.00 $3,008.00

Haskell Sr. Fire Protection

Engineer 8 $177.99 $1,423.92

Haskell Group Lead Struct.

Engineer 10 $213.00 $2,130.00

Haskell Sr. Electrical

Engineer 8 $190.00 $1,520.00

Haskell Elect. Design

Associate I 8 $85.00 $680.00

Haskell Group Lead Mech.

8 $208.00 $1,664.00

Page | 27

Sr. Mechanical

Designer 24 $152.00 $3,648.00

Haskell Group Lead Plumb.

Engineer 8 $208.00 $1,664.00

Haskell Plumbing Design

Associate I 24 $85.00 $2,040.00

Haskell Project Coordinator 8 $119.98 $959.84

Haskell Administrative

Support 6 $80.00 $480.00

Total $28,635.29

Subtask 12B Ranger…

This is the start of the file's text. The full file is on GovTribe.

Other files

File Type Posted
CN-370000-CN215-T1.pdf PDF
CN-370000-CN215-T2.pdf PDF
CN-370000-CN215-T2CO1.pdf PDF
CN-370000-CN215-T3.pdf PDF
CN-370000-CN215-T4.pdf PDF
CN-370000-CN215-CMC1.pdf PDF
CN-370000-CN215-T6.pdf PDF
CN-370000-CN215-CMC3.pdf PDF
CN-370000-CN215-T3CO1.pdf PDF
CN-370000-CN215-T3CO3.pdf PDF
CN-370000-CN215-T5.pdf PDF
CN-370000-CN215.pdf PDF
CN-370000-CN215-A1.pdf PDF
CN-370000-CN215-CMC2.pdf PDF
CN-370000-CN215-T3CO2.pdf PDF
CN-370000-CN215-T7.pdf PDF
CN-370000-PL302-TA6.pdf PDF
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .