Task Assignment Notification and Proposal Summary
This document is a Task Assignment Notification Form and supporting proposal from the Florida Department of Environmental Protection (FDEP) awarding a task order to Gresham Smith, a consulting engineering firm. The contract is designated as FDEP Contract No. CN215, Task Assignment No. 1, Project No. 61332, and covers bridge evaluations for the Florida Keys Overseas Historical Trails (FKOHT) project. The project manager is Wayne Thomas of FDEP, with consultant representative Tyler Strickland, P.E. serving as the project executive for Gresham Smith. The contract was executed on March 6, 2021, with a completion date of June 30, 2022.
The scope of work consists of three primary tasks: (1) Preparation, Mobilization and Project Management; (2) Bridge Field Evaluations of the Bahia Honda Bridge (approximately 1 mile) and the Seven Mile Bridge (approximately 4.5-mile portion); and (3) Bridge Evaluation Report preparation. The evaluation utilizes visual inspection from boats with binoculars and drone photography to document deterioration and provide recommendations for immediate, short-term, and long-term demolition or rehabilitation options. The total fixed price cost is $123,078.80 for labor, with reimbursable expenses not to exceed $26,788.00, for a total task amount of $149,866.80. Reimbursable expenses include airfare, vehicle rental, lodging, meals, boat rental, and incidentals, all submitted at actual cost with receipts in accordance with FDEP travel regulations. Payment is made upon FDEP approval of deliverables for each task.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-CN215-CMC1.pdf | ||
| CN-370000-CN215-T6.pdf | ||
| CN-370000-CN215-CMC3.pdf | ||
| CN-370000-CN215-T3CO1.pdf | ||
| CN-370000-CN215-T3CO3.pdf | ||
| CN-370000-CN215-T5.pdf | ||
| CN-370000-CN215.pdf | ||
| CN-370000-CN215-A1.pdf | ||
| CN-370000-CN215-CMC2.pdf | ||
| CN-370000-CN215-T3CO2.pdf | ||
| CN-370000-CN215-T7.pdf | ||
| CN-370000-PL302-TA6.pdf | ||
| CN-370000-CN215-T2.pdf | ||
| CN-370000-CN215-T2CO1.pdf | ||
| CN-370000-CN215-T3.pdf | ||
| CN-370000-CN215-T3CO2.pdf.crdownload | CRDOWNLOAD file | |
| CN-370000-CN215-T4.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN215 1 FDEP 61332
Florida Keys Overseas Historical Trails (FKOHT) Bridge Inspection
Gresham Smith
Tyler Strickland, PE 850.219.8404 tyler.strickland@greshamsmith.com
Alyssa Skehan or successor 850-245-2781 Alyssa Skehan@FloridaDEP.gov
Consultant is to coordinate and do evaluations of the Bahia Honda Bridge (approximately 1 mile long) and the Seven Miles Bridge (approximately 4.5 mile portion). After evaluations are completed consultant is to provide FDEP with an evaluation report as per proposal dated 3/2/21.
Wayne Thomas
Upon execution $ 123,078.80 06/30/2022 $ 26,788.00
$ 149,866.80
Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2021.03.04 14:40:45 -05'00'
Wayne Thomas Wayne Thomas Digitally signed by Wayne Thomas Date: 2021.03.04 14:44:04 -05'00'
Alyssa Skehan Alyssa Skehan Digitally signed by Alyssa Skehan Date: 2021.03.04 14:49:41 -05'00'
Tyler Strickland, PE R. Tyler Strickland, P.E., J.D.
2021.03.06 10:02:02 -05'00'
Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2021.03.09 10:53:28 -05'00'
61332 37505000263 080039/21 675002 U3200 131500 XR $ 149,886.80
$ 0.00
Mr. Wayne Thomas - FDEP March 2, 2021
Page | 1
Project Description: FKOHT Bridge Evaluations Bahia Honda Bridge & Seven Mile Bridge
This Task Order is to coordinate and prepare the necessary documentation for an evaluation of the historic Bahia Honda Bridge (approximately 1 mile long) and the southern portion of the historic Seven Mile Bridge (approximately 4.5-mile portion). The field evaluation would be performed visually from a boat, with binoculars, and with the use of drone photography. The intent of the evaluation is to determine the most critically deteriorated portions of the structures and provide recommendations on immediate, short-term, and long-term plans for demolition or salvage of all or portions of the structures. This evaluation does NOT include underwater survey or inspection, National Highway Institute (NHI) inspection and element inspection, no LiDAR, and no environmental or SHPO related studies and findings.
Task 1: Preparation, Mobilization and Project Management
Description: Evaluation team will review available information and past reports to familiarize themselves with the project, will conduct periodic coordination meetings as well as a kick-off meeting with FDEP prior to field activities.
The team will prepare a safety plan and determine any required traffic control requirements. Project staff will mobilize to the site prior to field evaluations. Travel time will be incurred at 1 day each direction per field employee.
Any additional travel time will not be charged to the project.
• Subtask 1A – Kickoff Meeting and Staff Coordination o A kickoff meeting will be held with FDEP staff and other stakeholders identified by FDEP prior to field activities.
o Gresham Smith staff will conduct weekly coordination meetings to prepare for the field evaluation activities.
• Subtask 1B – Mobilization Preparation o Will include arrangement for boat rental, staff travel and lodging; and for 1 day of travel time for all staff members. Staff will prepare a safety plan and work plan for the field evaluations.
• Subtask 1C – Project Management o Gresham Smith management and administrative staff will establish organizational, quality control, and cost control measures for the project.
Deliverables:
• Subtask 1A – Meeting notes for kickoff and coordination meeting.
• Subtask 1B – Submit safety plan and work plan to FDEP.
• Subtask 1C – Progress report/letter will be submitted to summarize completed Task 1 activities.
Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection (FDEP) within two weeks of submittal to confirm they are complete, accurate, and timely.
Page | 2
Task 1A ‐ Kickoff Meeting and Staff Coordination
Anticipated Staff Member Position Classification Weighted
Hourly Rate
Hours Total Fixed Price
Cost
Strickland, Tyler Chief Engineer $226.27 4 $905.08 Tran, Tom Chief Engineer $226.27 2 $452.54 Weres, John Structural Engineer (Team
Leader/TL) $202.01 12 $2,424.12
Wells, Braden Engineer $117.95 4 $471.80 Horn, Ryan Engineer $117.95 4 $471.80 Yantis, Levi Engineer $117.95 2 $235.90 Hill, Josh Engineering Tech $90.98 2 $181.96 TBD (Drone Operator) Environmental
$131.81
2 $263.62
Serles, Amy Administrative $83.38 6 $500.28 Sub‐Total 38 $5,907.10
Task 1B ‐ Mobilization Preparation
Weighted
Hourly Rate
Hours Total Fixed Price Cost
Strickland, Tyler Chief Engineer $226.27 2 $452.54 Tran, Tom Chief Engineer $226.27 2 $452.54 Weres, John Structural Engineer (TL) $202.01 36 $7,272.36 Wells, Braden Engineer $117.95 32 $3,774.40 Horn, Ryan Engineer $117.95 20 $2,359.00 Yantis, Levi Engineer $117.95 10 $1,179.50 TBD (Drone Operator) Environmental
$131.81
18 $2,372.58
Sub‐Total 120 $17,862.92
Task 1B Expenses (Estimated Airfare for Out-of-State Staff)
Category Notes Unit Costs Unit Total Expense
Cost
Airfare (Wells) Nashville to Key West $850.00 1 Trip
$850.00 Airfare (Horn) Atlanta to Key West $850.00 1 Trip
Airfare (Drone Operator) Nashville to Key West $850.00 1 Trip
Excess Baggage Fees Tools, Supplies & Drone $60.00 2 - Trips
$120.00 Sub‐Total $2,670.00
Page | 3
Subtask 1C ‐ Project Management
Weighted
Hourly Rate
Hours Total Fixed Price Cost
Strickland, Tyler Chief Engineer
$226.27 2 $452.54 Weres, John Structural Engineer (TL) $202.01 8 $1,616.08 Serles, Amy Administrative $83.38 8 $667.04 Sub‐Total 18 $2,735.66
Total for Task 1: Fixed Price Cost (Labor Only) $26,505.68
Reimbursable Expenses (At Cost with Receipts) $2,670.00
Task 1 Total (Fixed Fee + Reimbursables) $29,175.68
Page | 4
Task 2: Bridge Evaluations Description: Perform an evaluation of the Bahia Honda Bridge (approximately 1 mile length) and the southern portion of the Seven Mile Bridge (approximately 4.5 miles length) to observe and document the apparent bridge condition and to determine potential locations for immediate demolition, short-term remediation and a long-term plan for preserving any possible portions of the bridges. Visual evaluation will be conducted by boat with supplemental binoculars. Drone coverage of the structures including video and still photography will be obtained during the second week.
• Subtask 2A – Bridge Field Evaluation o For the Bahia Honda Bridge, the evaluation limits will include the 9-span girder system to the south and the truss spans from Span 10 thru 33. The northern 2 spans (35 and 36) are not included, as these are planned for reconstruction by others. We will visually observe and document all apparent deterioration. No form of sounding or physical testing of the elements will be performed due to the advanced deterioration of the structure.
o For the Seven Mile Bridge Structure, the evaluation limits include the steel girder segments south of Pigeon Key (approximately 16,000’) and the concrete arch segment (approximately 5,600’) south to the rehabilitated fishing pier segment. The most southern segment that was previously rehabilitated as a fishing pier is not included. Particular attention will be given to the overhangs, brackets, and failing portions of the deck. No form of sounding or physical testing of the elements will be performed due to the advanced deterioration of the structure.
o Local boat rental will be coordinated to provide visual access.
o Field work is estimated to require 14 days of evaluation and investigation, including the drone flights and documentation. Extended workdays are estimated, and all field work will be conducted in consecutive days, including weekends. Two bridge engineers will be present at all times, including at least 1 National Highway Institute (NHI) Certified Bridge Inspection Team Leader.
o Upon mobilization to the sites, all work is budgeted to be completed in consecutive days.
Should unplanned weather events, such as a tropical storm, excessive wind, or other safety concerns cause delays in the field investigations, additional fees would be warranted and requested to account for extended lodging costs and non-productive time.
• Subtask 2B – Drone with Video/Photos o A Gresham Smith FAA certified drone operator will be utilized for an estimated 4 days in the field, plus editing time. Drone coverage will be completed utilizing a DJI Phantom 4 Pro portable drone, or similar device.
o Drone coverage will include a video of the entire deck surface to document the existing condition. Photographs of each span and selected detail of severe deterioration will be taken from each side. Digital copies of the videos and photographs will be provided to FDEP.
o Time is included in the Environmental/Drone Operator category to edit the video and to edit and categorize all of the digital files and photos.
• Subtask 2C – Quality Control o Gresham Smith’s Project Executive/Chief Engineer (Tyler Strickland) will perform a QC review of the field activities to ensure that all safety requirements are met and that the field evaluations are being performed in accordance with the agreement and company requirements.
Page | 5
• Subtask 2A – Evaluation notes and photo logs will be included in the bridge evaluation report. A progress report will be submitted at the conclusion of the field activities to document the durations and critical findings. The progress report will verify the completion of Task 2 activities.
• Subtask 2B – All drone video and digital photographs will be submitted along with the Task 3 evaluation reports.
• Subtask 2C – A letter report will be submitted to document the QC inspection.
Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection
Subtask 2A ‐ Bridge Evaluation
Weighted
Hourly Rate Hours Total Fixed Price Cost
Weres, John Structural Engineer (TL) $202.01 100 $20,201.00 Wells, Braden Engineer $117.95 80 $9,436.00 Horn, Ryan
Engineer $117.95 100 $11,795.00
Sub‐Total 280 $41,432.00
Task 2A Expenses (Autos, Lodging, Subsistence, and Miscellaneous)
Costs Unit Total Expense
Rental Truck (Weres) Travel to and On-Site / Week $700.00 3 Weeks
$2,100.00 Rental Car (Engineers) Airport to Site (Days) $32.00 4 Days
$128.00 Fuel (Vehicles & Boat) Travel, On-Site, On-Water $2.50 300 Gal.
$750.00 Excess Baggage Fees Tools, Supplies & Drone $60.00 2 Trips
$120.00 Meals – Inspection and
Travel Days Based on full day – prorate for travel days
36.00
Travel D
$1,116.00
Per Diem (Class A) Field Engineers/Last Travel Day $80.00 3 Days $240.00
Lodging (Marathon FL) Field Engineers/Night $230.00
Nights $6,440.00
Boat Rental 22’ Deck Boat / Week $1,600.00
Weeks 3,200.00
Local Boat Operator Boat Operator/Day $463.00 14 Days 6,482.00 Incidentals (Ice, water, Gatoraid, etc) Based on actual costs with receipts 200.00
1 At Cost 200.00
Sub‐Total $20,776.00
Page | 6
Subtask 2B ‐ Drone Video/Photos
Anticipated Staff Member Position Classification Weighted Hourly Rate Hours Total Fixed
Price Cost
TBD (Drone Operator) Environmental $131.81 60 $7,908.60 Sub‐Total 12 $7,908.60
Task 2B Expenses (Drone Operator)
Costs Unit Total Expense
Rental Car (Drone Opp.) Airport to Marathon $32.00 5 Days
$160.00 Meals - Travel Based on full day – prorate for travel days
$36.00 5 Days
180.00
Per Diem (Class A) Drone Operator/Day $80.00 1 Days $80.00 Lodging (Marathon FL) Drone Operator/Night
$230.00
Nights $1,150.00
Drone Rental Daily Fee (Privately Owned) $125.00 4 Days $500.00 Sub‐Total $2,070.00
Subtask 2C ‐ Quality Control
Hourly Rate Hours Total Fixed
Price Cost
Strickland, Tyler Chief Engineer $226.27
16 $3,620.32 Sub‐Total 16 $3,620.32
Task 2C Expenses (Quality Control – On-Site)
Category Notes Unit Costs Unit
Total Expense
Airfare (Chief Engineer) Tallahassee to Key West $640.00 1 Trip
$640.00 Meals – Inspection and
Travel Days Based on full day – prorate for actual travel times
36.00 3 Days
108.00
Per Diem (Class A) Chief Engineer/Day $80.00 0 Days $0.00 Lodging (Marathon FL) QC/Night $230.00
Nights $460.00
Rental Car (QC) Airport to Marathon $32.00 2 Days
$64.00 Sub‐Total $1,272.00
Page | 7
Total for Task 2: Fixed Price Cost (Labor Only) $52,960.92
Reimbursable Expenses (At Cost with Receipts) $24,118.00
Task 2 Total (Fixed Fee + Reimbursables) $77,078.92
Page | 8
Task 3: Bridge Evaluation Report Description: A report will be prepared and submitted for each bridge to document the findings of the field evaluation as well as to provide recommendations for immediate, short-term, and long-term time frames on potential demolition and rehabilitation options.
• Subtask 3A – Bridge Evaluation Report Preparation o A separate report will be compiled for each bridge. The report will include a description of the bridge and the major components, sketches of major deterioration, a span-by-span documentation of the apparent current condition and recommendations for potential future repairs or demolition. Recommendations will include immediate, short-term, and long-term options for the basis of budget development and future planning purposes only – it is anticipated that any additional work that may be required to implement such recommendations would be completed under a separate task order or by others.
Immediate Repairs – Repairs to address immediate safety concerns that can be completed by maintenance staff or under an emergency contract (by others), such as falling concrete and loose steel members.
Short-Term Repairs - Similar safety repairs, potentially developed into a bid package for planned letting (by others). Include removal of select portions of the structure or site protection.
Long-Term Options – Develop potential options to demolish and/or rehabilitate portions of the structures to be used for future planning and budgeting. Historic impacts and NEPA requirements and review would require a separate, future study to obtain environmental clearance.
o Cost estimates will be included for each option. Cost estimates will be a high-level based on average past costs for similar work; similar to the cost estimates provided in earlier studies for these bridges, in order to sensibly establish program budgets and compare options.
o Copies of all field notes and support information will be included.
o The report will not include typical AASHTO Element Level Inspection or Condition Assessment
Scores and information due to the scope being a visual evaluation and not an NHI/FDOT inspection.
o The final reports will be signed and sealed by the Engineer of Record, a licensed Florida P.E.
o A draft report will be submitted for each bridge for review by FDEP. We anticipate that the report can be reviewed with FDEP as a virtual meeting using Teams for video presentation of findings. Any additional presentations to other agencies are not included in this scope or budget.
o Review comments on the report from any other agencies, including FDOT, should be included in the initial review comments provided by FDEP. Responding to multiple reviews following the initial submission is not included. A final version of the report will be signed, sealed, and submitted to FDEP within 2 weeks of the review meeting and receipt of all comments.
• Subtask 3B – Report QC o The final evaluation report will be reviewed for quality control by a separate licensed Florida
Professional Engineer, not included in the evaluation and report preparation activities.
Page | 9
• Subtask 3A – Draft evaluation report for each bridge will be submitted in digital (pdf) format, including copies of representative photographs. Photographs and videos will be submitted in appropriate format (jpg, mov, etc.)
• Subtask 3B – Final sealed report and QC verification form will be provided, signed by the responsible PE.
Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection
Subtask 3A ‐ Bridge Evaluation Report Preparation
Hourly Rate Hours Total Fixed
Price Cost
Weres, John Structural Engineer (TL) $202.01 30 $6,060.30 Wells, Braden Engineer $117.95 40 $4,718.00 Horn, Ryan Engineer $117.95 140 $16,513.00 Yantis, Levi Engineer $117.95 72
$8,492.40
Hill, Josh Engineering Tech $90.98 24 $2,183.52 Serles, Amy Administrative $83.38 8 $667.04 Sub‐Total 306 $38,634.26
Subtask 3B – Report QC
Hourly Rate Hours Total Fixed
Price Cost Strickland, Tyler Chief Engineer $226.27 6 $1,357.62
Tran, Tom Chief Engineer $226.27 16 $3,620.32
Sub‐Total 22 $4,977.94
Total for Subtask 3: Fixed Price Cost (Labor Only) $43,612.20
Reimbursable Expenses (At Cost with Receipts) $0.00
Task 3 Total (Fixed Fee + Reimbursables) $43,612.20
Page | 10
Project Schedule: Contract Execution Date - TBD
Activity Duration
(Calendar Days) Dates
Task 1: Preparation, Mobilization and Project Management
30 TBD
Task 2: Bridge Field Evaluation 20 TBD Task 3: Bridge Evaluation Report 40 TBD
Summary of Fees:
Task Task Fixed Labor Cost Task Fixed Reimbursable Task 1: Preparation, Mobilization and Project Management $ 26,505.68 $ 2,670.00
Task 2: Bridge Field Evaluation $ 52,960.92 $ 24,118.00 Task 3: Bridge Evaluation Report $ 43,612.20 $ 0.00
Total Fixed Price Cost: $123,078.80
Total Reimbursables, Not to Exceed Budget: $ 26,788.00
Payment will be made upon approval of deliverables for each task by the FDEP in the amount specified. The agreement is a Lump Sum Agreement plus reimbursable expenses.
All expense costs are estimated. Expenses will be reimbursed at actual costs with receipts, except for the daily meals/subsistence costs specified as a daily rate noted above. The subsistence will be paid for all full days of travel and field work in accordance with FDEP and Florida travel regulations and prorated accordingly for partial travel days. Expenses will be submitted utilizing the FDEP Travel Voucher form.