CN-370000-CN215-T3CO1.pdf
PDF 929 KB Posted
- Contract number
- CN215
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form (Change Order No. CO1) issued by the Florida Department of Environmental Protection (FDEP) under FDEP Contract No. CN215 for the Lovers Key State Park Park Redevelopment project. The consultant performing the work is Gresham Smith, represented by Tyler Strickland (850.219.8404, tyler.strickland@greshamsmith.com). The FDEP Contract Manager is Ralph Perkins or successor (850.245.2460, Ralph.Perkins@FloridaDEP.gov). The change order was executed on March 3, 2023, with all required signatures from FDEP Budget Representative Tamika Bass, Project Manager Garland Sandel, Contract Manager David Matson, Consultant Tyler Strickland, and Contract Authority Michael W. Foster Jr., P.E.
This change order adds design, permit, and construction services for tram bridges repair in the amount of $8,901.81 in fixed fees with no reimbursable expenses, for a total task amount of $19,087.23. The scope includes two subtasks: Subtask 2A—Bridge Repair Sketches/Plan Sheets ($6,505.86) requiring 42 billable hours from project engineers and structural engineers to develop repair details for supporting the undermined approach slab of Tram Bridge 2 and concrete crack repairs, with deliverables of two sealed plan sheets; and Subtask 2B—RFI Technical Responses ($2,395.95) requiring 15 billable hours to provide up to two technical responses to contractor requests for information during the bid and construction phases. The original task execution date is February 8, 2024, with an original end date of June 30, 2025, which remains unchanged. The project addresses Hurricane Ian damage to Lovers Key State Park and specifically supports beach restoration requiring approximately 3,000 heavy dump truck loads to cross the tram bridge structures.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-CN215-CMC1.pdf | ||
| CN-370000-CN215-T6.pdf | ||
| CN-370000-CN215-A1.pdf | ||
| CN-370000-CN215-CMC2.pdf | ||
| CN-370000-CN215-T3CO2.pdf | ||
| CN-370000-CN215-T7.pdf | ||
| CN-370000-PL302-TA6.pdf | ||
| CN-370000-CN215-CMC3.pdf | ||
| CN-370000-CN215-T3CO3.pdf | ||
| CN-370000-CN215-T5.pdf | ||
| CN-370000-CN215.pdf | ||
| CN-370000-CN215-T1.pdf | ||
| CN-370000-CN215-T2.pdf | ||
| CN-370000-CN215-T2CO1.pdf | ||
| CN-370000-CN215-T3.pdf | ||
| CN-370000-CN215-T3CO2.pdf.crdownload | CRDOWNLOAD file | |
| CN-370000-CN215-T4.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN215 3 CO1 6I402C
Lovers Key State Park Park Redevelopment
Gresham Smith
Tyler Strickland 850.219.8404 tyler.strickland@greshamsmith.com
Ralph Perkins or successor 850.245.2460 Ralph.Perkins@FloridaDEP.gov
Added design, permit and construction for tram bridges repair. See proposal dated 3.3.23
$ 0.00 $ 10,185.42 $ 10,185.42 $ 0.00 $ 10,185.42 $ 10,185.42
$ 8,901.81 $ 8,901.81 $ 0.00 $ 19,087.23 $ 19,087.23
2.08.24
6.30.25
6.30.25
0.00
6.30.25
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.03.03 16:07:43 -05'00'
Garland Sandel Garland Sandel Digitally signed by Garland Sandel Date: 2023.03.03 16:12:56 -05'00'
David Matson for Ralph Perkins David Matson Digitally signed by David Matson Date: 2023.03.03 16:25:23 -05'00'
Tyler Strickland Strickland, Tyler Digitally signed by Strickland, Tyler Date: 2023.03.03 16:33:18 -05'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2023.03.06 09:55:39 -05'00'
6I402C FD091 37800000000 088040/23 408001 U3200 131500 PF $ 8,901.81
$ 8,901.81
Mr. Garland Sandel - FDEP March 3, 2023
Page | 1
Project Description: Lover’s Key State Park Change Order 1 – Bridge Repair Tram Bridges – Rev. 3
This Task Order Change Order 1 is to perform the necessary bridge repair detail plans and RFI Responses during construction; to allow for multiple daily dump truck loads to cross the existing concrete tram bridge structures to support the beach restoration at Lovers Key State Park. Approximately 3,000 loads during the project are anticipated at 21 Tons per loaded, 3-axle trucks.
On September 23, 2022, Hurricane Ian made landfall in Florida a affected many attractions within the state. One of these is Lover’s Key State Park. The damage was considered major with anticipated work needed for existing bridges, boardwalks, pavilions, roadways, utilities, tram stops, ranger stations, and residences, and beach restoration. The existing concrete bridges exhibited minor damage; but remained generally in-tack and operative. The Florida Department of Environmental Protection hired JGP Structural Group, Inc to inspect the two concrete tram bridges following Hurricane Ian.
This proposal includes developing repair details for supporting the undermined approach slab of Tram Bridge 2, and completing crack repairs to the substructure, and responding to contractor RFI’s during the CM and construction phase.
Task 2: Bridge Repair Details and RFI Responses
Description:
• 2A –Bridge Repair Plan Development – The Gresham Smith Team will develop sketches or plan sheets for anticipated permanent repairs to the Tram Bridge required to allow the sand-filled dump trucks to repeatedly cross the bridges for access to the beach. Repairs include slab jacking/grouting under approach slabs, and concrete/crack repairs to select bridge bents. Railing repairs and miscellaneous bridge repairs will be deferred until future tasks. Two, sealed plan sheets are anticipated.
• 2B – RFI Responses – The Gresham Smith Team will provide responses to technical RFI’s submitted by contractors during the bid and construction phase. A maximum of two RFI responses are anticipated.
Deliverables:
• 2A – Sketches/plan sheets of proposed repairs to provide to the Construction Manager with associated cost estimate.
• 2B – Technical response memos for a maximum of two RFIs, or a final repair memorandum will be submitted to confirm completion of these repairs.
Page | 2
Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection (FDEP) within two weeks of submittal to confirm they are complete, accurate, and timely.
Subtask 2A –Bridge Repair Sketches/Plan Sheets
Anticipated Staff Classification Hours Billable Rate Revenue Strickland Chief Engineer 0 $226.27 $0.00
Elvambuena Project Manager 0 $171.92 $0.00
Torres Project Engineer 14 $180.77 $2,530.78
Rome Engineer 20 $117.95 $2,359.00 Weres Structural Engineer 8 $202.01 $1,616.08 Sewell Administrative 0 $83.38 $0.00 42 $6,505.86 Subtask 2B – RFI Technical Responses
Anticipated Staff Classification Hours Billable Rate Revenue
Strickland Chief Engineer 1 $226.27 $226.27
Elvambuena Project Manager 0 $171.92 $0.00
Torres Project Engineer 4 $180.77 $723.08
Rome Engineer 4 $117.95 $471.80 Weres Structural Engineer 4 $202.01 $808.04 Sewell Administrative 2 $83.38 $166.76 15 $2,395.95 Subtotal Task 2 $8,901.81
Reimbursable Total Cost for Subtask 2 $0.00 Total for Subtask 5 $8,901.81
Project Schedule: Contract Execution Date – TBD
Activity Duration (Calendar Days Dates Subtask 2A –Bridge Repair Sketches/Plan Sheets 10 TBD Subtask 2B – RFI Technical Responses N/A TBD
Page | 3
Summary of Fees:
Task Task Fix Labor Costs Task Fix Reimbursable Subtask 2A –Bridge Repair Sketches/Plan Sheets $6,505.86 Subtask 2B – RFI Technical Responses $2,395.95
Total Fixed Price Cost $8,901.81 Total Reimbursables, Not to Exceed Budget $0.00
Total Budget (Labor and Expenses) $8,901.81
Payment will be made upon approval of deliverables for each task by the FDEP in the amount specified. The agreement is a Lump Sum Agreement plus reimbursable expenses.
All expense costs are estimated. Expenses will be reimbursed at actual costs with receipts, except for the daily meals/subsistence costs specified as a daily rate noted above. The subsistence will be paid for all full days of travel and field work in accordance with FDEP and Florida travel regulations and prorated accordingly for partial travel days. Expenses will be submitted utilizing the FDEP Travel Voucher form.
| CN215 TA3 CO1 A.pdf |
| CO1 Lovers Key Bridge Repair Scope-Fee -Rev3 3-3-23.pdf |
| Project Description: Lover’s Key State Park |
| Change Order 1 – Bridge Repair Tram Bridges – Rev. 3 |
| Task 2: Bridge Repair Details and RFI Responses |
| Deliverables: |
File details come from the government source that posted it. Updated .