About this file
This document is a Task Assignment Notification Form and supporting fee proposal from the Florida Department of Environmental Protection (FDEP) for architectural and engineering services. The contract involves FDEP's Bureau of Design and Construction, the consultant firm Clemons, Rutherford & Associates, Incorporated (CRA), and the engineering partner H2Engineering, Incorporated. The FDEP contract number is CN211, with task assignment number 05, and the project is located at Silver Springs State Park in Florida. The project manager is Theresa Carron, and the FDEP contract manager is Ralph Perkins.
The contract scope encompasses design, permitting, and construction administration services for restroom upgrades at the Silver Springs Town Center. The work is structured in six subtasks: (1) preliminary documents and site investigation ($8,532.92); (2) 30% design development documents ($23,278.86); (3) 100% construction documents ($16,140.32); (4) bidding and pricing assistance ($3,240.56); (5) 50% construction administration ($7,435.85); and (6) 100% construction administration ($7,341.23). The total fixed price cost is $63,968.66, with reimbursable costs not to exceed $2,001.08, for an overall total task amount of $65,969.74. The project schedule extends 285 calendar days from kickoff through substantial completion, with start date upon execution and completion targeted for February 23, 2025. Services are funded through FDEP account codes and budget allocations as detailed in the FLAIR code breakdown.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-CN211-CMC3.pdf | ||
| CN-370000-CN211-T1.pdf | ||
| CN-370000-CN211-T4CO2.pdf | ||
| CN-370000-CN211-T5 CO1.pdf | ||
| CN-370000-CN211.pdf | ||
| CN-370000-CN211-T4.pdf | ||
| CN-370000-CN211-T4CO1.pdf | ||
| CN-370000-CN211-CMC2.pdf | ||
| CN-370000-CN211-T2CO1.pdf | ||
| CN-370000-CN211-T2CO3.pdf | ||
| CN-370000-CN211-T2CO5.pdf | ||
| CN-370000-CN211-T3.pdf | ||
| CN-370000-CN211-TA2CO4.pdf | ||
| CN-370000-CN211-A1.pdf | ||
| CN-370000-CN211-CMC1.pdf | ||
| CN-370000-CN211-T1CO1.pdf | ||
| CN-370000-CN211-T2.pdf | ||
| PC-370000-CN211.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN211 05 FDEP-BDC 61491C
Silver Springs State Park Upgrade Town Center Restrooms
Clemons, Rutherford & Associates (CRA)
James H. Lewis (850) 385-6153 jlewis@craarchitects.com
Ralph Perkins (850) 245-2460 Ralph.Perkins@FloridaDEP.gov
Design, permitting and construction administration for restroom upgrades per the attached proposal dated 2/22/2023.
Theresa Carron
Upon Execution $ 63,968.66 2/23/2025 $ 2,001.08
$ 65,969.74
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.02.27 13:49:00 -05'00'
Theresa Carron T.Carron Digitally signed by T.Carron Date: 2023.02.27 13:52:55 -05'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.02.27 17:06:03 -05'00'
James H. Lewis Digitally signed by: James Lewis Date: 2023.02.28 11:31:02 -05'00' Reason: I am approving this document
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2023.03.06 09:09:03 -05'00'
61491C 37503000203 080039/23 423001 U3200 131500 QK $ 65,969.74
$ 65,969.74
February 22, 2023
Theresa Carron Florida Department of Environmental Protection Bureau of Design and Construction Project Manager 3900 Commonwealth Blvd.
Tallahassee FL 32399
RE: DEP – CN 211
Project No. TA 5
Silver Springs - Town Center Restrooms Restroom Renovations
Fee Proposal
Dear Ms. Carron:
Thank you for considering Clemons, Rutherford & Associates for your architectural and engineering needs. We look forward to working with you on the proposed restroom renovations at the Silver Springs Town Center. The general scope of work is understood to include the following: Remove and replace existing plumbing fixtures, revise layout as necessary to meet current ADA requirements, and replace all existing finishes with new. Asbestos testing and abatement scope is currently not included in our scope. If an asbestos testing and abatement is determined to be required, these services may be provided as an additional service. It is recommended if an asbestos survey has not been completed one be completed at the earliest convenience so appropriate measure may be taken, if needed. It is also understood that structural engineering will not be required for this project. Any and all AHJ review fees have been excluded.
Sincerely, James H. Lewis Production Manager / Architect
Silver Springs - Town Center HVAC replacement
DEP – CN 211 Task Assignment Number – TA 02
Subtask 1: Preliminary Documents Description:
Kickoff Meeting (Tallahassee)
Site Visit & Field Investigation for base drawings (1) trip CRA, (1) trip H2
Preliminary Scoping Plan(s)
Provide recommendations for materials, fixtures, etc. to be utilized on project
Deliverable:
(2) hard copy sets of 24 x 36 prints and PDF version of scoping documents for review
Meeting minutes
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Subtask 1 - Preliminary Phase
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Clemons, Rutherford & Associates, Incorporated
President - CEO $203.28 1 $203.28
Project Manager $134.13 24 $3,219.12
Production VP $112.17 4 $448.68
CADD Technician $60.57 16 $969.12
Spec writer $102.90 $0.00
Admin $73.83 2 $147.66
H2Engineering, Incorporated
Principal $185.30 4 $741.20
Sr. Engineer $136.58 12 $1,638.96
Graduate Engineer $86.03 8 $688.24
Designer $67.50 0 $0.00
CADD Tech $44.05 0 $0.00
Administration $56.90 2 $113.80
Total $8,170.06
Carron_T Text Box
Postage Provide an estimated amount
$10.00
Printing - Plans
(2) 24 x 36 sets of Prints x 5 sheets x $2/sheet
$20.00
Printing - Specifications
(0) 8.5 x 11 set of Specifications 125 shts x 0.15
$0.00
Subsistence per FS 112.061 Not Allowed per DEP $0.00
Mileage (@ $0.445 per mile)
(2) trips x 374 miles x $.445/mile
$332.86
Subtask 1 - Total
Reimbursable Total Cost $362.86 $8,532.92
Subtask 2: 30% Documents Description:
Develop 30% mechanical plans
Provide cut sheets/data sheets of major material and equipment selections
Outline specifications
Meeting to review 30% documents (Tallahassee, FL)
Deliverable:
(2) hard copy sets of 24 x 36 prints of 30% documents for review and PDF version
Cut sheets of equipment
Meeting minutes
Preliminary cost estimate
Subtask 2 - 30% Documents
Total Fixed Price Cost
Project Manager $134.13 48 $6,438.24
Production VP $112.17 6 $673.02
CADD Technician $60.57 40 $2,422.80
Spec writer $102.90 16 $1,646.40
Admin $73.83 4 $295.32
Principal $185.30 12 $2,223.60
Sr. Engineer $136.58 20 $2,731.60
Graduate Engineer $86.03 20 $1,720.60
Designer $67.50 40 $2,700.00
CADD Tech $44.05 40 $1,762.00
Administration $56.90 5 $284.50
Total $23,101.36
Provide an estimated
$40.00
(2) 24 x 36 sets of Prints x 25 sheets x $2/sheet
$100.00
(1) 8.5 x 11 set of Specifications 250 shts x
$37.50
Subsistence per FS 112.061 Not Allowed $0.00
(0) trips x 374 miles x
Subtask 2 -
Reimbursable Total Cost $177.50 $23,278.86
Subtask 3: 100% Plans
Incorporate final comments and revisions from Owner review of 30% documents
Incorporate final comments and revisions from in house QC review
Submit signed and sealed documents to AHJ’s (Local building official and State Fire Marshal)
Submit 100% documents signed and sealed to Client
Deliverable:
(5) 24 x 36 sets of plans – (4 of 5 to be signed and sealed) & PDF
CADD files
Updated Cost estimate
Subtask 3 - 100% Documents
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Project Manager $134.13 40 $5,365.20
Production VP $112.17 8 $897.36
CADD Technician $60.57 40 $2,422.80
Spec writer $102.90 16 $1,646.40
Admin $73.83 6 $442.98
Principal $185.30 4 $741.20
Sr. Engineer $136.58 10 $1,365.80
Graduate Engineer $86.03 10 $860.30
Designer $67.50 10 $675.00
CADD Tech $44.05 10 $440.50
Administration $56.90 5 $284.50
Total $15,345.32
$220.00
(5) 24 x 36 sets of Prints x35 sheets x $2/sheet
$350.00
(5) 8.5 x 11 set of Specifications 300 shts x
$225.00
(0) trips x 374 miles x
Subtask 3 -
Reimbursable Total Cost $795.00 $16,140.32
Subtask 4: Bidding/GMP Assistance Description:
Respond to RFI’s
Review bids and/or GMP
Review substitution requests
Prepare addendum
No pre-bid meeting on site is included
Deliverable:
Copies of RFI’s, Substitutions, addendum, GMP review letter
Subtask 4 - Bidding/Pricing Assistance
Total Fixed Price Cost
Project Manager $134.13 10 $1,341.30
Production VP $112.17 1 $112.17
CADD Technician $60.57 1 $60.57
Spec writer $102.90 $0.00
Admin $73.83 2 $147.66
Principal $185.30 1 $185.30
Sr. Engineer $136.58 4 $546.32
Graduate Engineer $86.03 2 $172.06
Designer $67.50 4 $270.00
CADD Tech $44.05 2 $88.10
Total $3,240.56
(0) 24 x 36 sets of Prints x 10 sheets x $2/sheet
Specifications 200 shts x
(0) trips x 374 miles x
Subtask 4 -
Reimbursable Total Cost $0.00 $3,240.56
Subtask 5: 50% Construction Administration Services
RFI review and response
ASI preparation
Submittal review and response
On-site observation (1) during construction by H2, (1) by CRA
Progress reports
Deliverable:
Copy of all approved submittals
Copy of field reports
Subtask 5 - 50% Contract Administration
Total Fixed Price Cost
Project Manager $134.13 8 $1,073.04
Production VP $112.17 1 $112.17
CADD Technician $60.57 1 $60.57
Spec writer $102.90 $0.00
Contract Administration $91.86 24 $2,204.64
Admin $73.83 3 $221.49
Principal $185.30 5 $926.50
Sr. Engineer $136.58 10 $1,365.80
Graduate Engineer $86.03 5 $430.15
Designer $67.50 3 $202.50
CADD Tech $44.05 3 $132.15
Administration $56.90 3 $170.70
Total $7,102.99
Specifications 200 shts x
(2) trips x 374 miles x
Subtask 5 -
Reimbursable Total Cost $332.86 $7,435.85
Subtask 6: 100% Construction Administration Services
RFI review and response
ASI preparation
Submittal review and response
On-site observation (1) substantial by H2, (1) by CRA
Progress reports
Deliverable:
Copy of all approved submittals and other closeout documents
Copy of contractors red-lined record drawings
Copy of field reports and punch list
Subtask 6 - 100% Contract Administration
Total Fixed Price Cost
Project Manager $134.13 8 $1,073.04
Production VP $112.17 1 $112.17
CADD Technician $60.57 1 $60.57
Spec writer $102.90 $0.00
Contract Administration $91.86 24 $2,204.64
Admin $73.83 4 $295.32
Principal $185.30 5 $926.50
Sr. Engineer $136.58 10 $1,365.80
Graduate Engineer $86.03 5 $430.15
Designer $67.50 2 $135.00
CADD Tech $44.05 2 $88.10
Total $7,008.37
Specifications 200 shts x
(2) trips x 374 miles x
Subtask 6 -
Reimbursable Total Cost $332.86 $7,341.23
Total Basic Services
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1: Preliminary $8,170.06 $362.86
Subtask 2: 30% plans $23,101.36 $177.50
Subtask 3: 100% Plans $15,345.32 $795.00
Subtask 4: Bidding Assistance
$3,240.56 $0.00
Subtask 5: 50 % Construction Administration
$7,102.99 $332.86
Subtask 6: 100% Construction Administration
$7,008.37 $332.86
Total Fixed Price Cost: $63,968.66
Total Reimbursable Cost: $2,001.08
Overall Total Cost: $65,969.74
Project Schedule:
Activity Duration (Calendar Days) Dates
Subtask 1: Preliminary 30
Subtask 2: 30% plans 60
Subtask 3: 100% Plans 30
Subtask 4: Bidding Assistance 45
Subtask 5-6: Contract Administration
| RE: DEP – CN 211 |
| Project No. TA 5 |