CN-370000-CN211-T4.pdf

PDF 2 MB Posted

Attached to
Master Agreement FL|CN211|4b7998480e7f8de3650dfd0117cc6681
Contract number
CN211
Issued by
Florida

About this file

This document consists of a Task Assignment Notification Form and detailed proposal from the Florida Department of Environmental Protection (FDEP) for an HVAC replacement project at the Ribault Clubhouse located at Fort George State Park in Jacksonville, Florida. The contract involves two primary consulting firms: Clemons, Rutherford & Associates, Inc. (CRA), serving as the architect, and H2Engineering, Incorporated, providing mechanical and HVAC engineering services. The FDEP Contract Number is CN211 with Project Number 61359C, and the contract manager is Jeffrey Whitfield. The initial task assignment (Task Assignment No. 4) was executed in May 2022 with a completion deadline of December 31, 2023.

The contract encompasses eight subtasks for providing comprehensive design and construction administration services for replacing the HVAC system at the Ribault Clubhouse. The first three subtasks—preliminary investigations, 30% design documents, and 100% contract documents—are currently encumbered with a combined fixed price cost of $115,267.02 and cost reimbursement not to exceed $1,949.35, totaling $117,216.37. Subtasks 4 through 8, covering bidding assistance, contract administration, site visit reviews, life cycle cost analysis, and HVAC commissioning, are marked as "not currently encumbered" but include detailed cost estimates totaling $55,637.00 in fixed price costs and $2,596.00 in reimbursable costs. Reimbursable expenses include postage, printing, and mileage at $0.445 per mile. Payment is contingent upon FDEP approval of deliverables for each subtask.

View the file

Other files

File Type Posted
CN-370000-CN211-CMC3.pdf PDF
CN-370000-CN211-T1.pdf PDF
CN-370000-CN211-T4CO2.pdf PDF
CN-370000-CN211-T5 CO1.pdf PDF
CN-370000-CN211.pdf PDF
CN-370000-CN211-T4CO1.pdf PDF
CN-370000-CN211-T5.pdf PDF
CN-370000-CN211-CMC2.pdf PDF
CN-370000-CN211-T2CO1.pdf PDF
CN-370000-CN211-T2CO3.pdf PDF
CN-370000-CN211-T2CO5.pdf PDF
CN-370000-CN211-T3.pdf PDF
CN-370000-CN211-TA2CO4.pdf PDF
CN-370000-CN211-A1.pdf PDF
CN-370000-CN211-CMC1.pdf PDF
CN-370000-CN211-T1CO1.pdf PDF
CN-370000-CN211-T2.pdf PDF
PC-370000-CN211.pdf PDF
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: I lask Assignment No.: Owner's Name: I Project No.:

CN21 I FDEP 61359C

Project Location: Project Name:

Fort George State Park Ribault Clubhouse HV AC Consultant Name:

CRA

Consultant Representative: Phone: Email:

James Lewis 850-545-0896 jlewis@craarchitects.com FDEP Contract Manager: Phone: Email:

Jeffrey Whitfieldor successor 850-245-2630 Jeffrrey. Whitfield@FloridaDEP.gov Description of Task:

Provide construction documents for the HV AC replacement system at the Ribault Clubhouse at Fo,t George State Park per the proposal dated 11/15/2021. (Subtasks I through 3 only will be included initially. Subtasks 4 through 8 will be tasked at a later date.)

Project Manager: Andrew Lippens

Start Date: I Uoon execution Completion Date: I 12/31/2023

Diane Langston

Budget Representative, FDEP Andrew Lippens

Project Manager, FDEP David Matson

Contract Manager,� James Lewis

Consultant Bryan Bradner

Contract Authority, FDEP

Project# Grant#

61359C

29 digit FLAIR Code:

Or2: Code 37502002227

Schedule

Fixed Price Cost: $115,267.02 Cost Reimbursement not to exceed: $1,949.35

Total Task Amount: $117,216.37 Approval Signatures:

Dl·ane Langston Digitally signed by Diane Langston Dale: 2022.05.11 16:26:06 -04'00'

Signature Andrew Lippens g��� ro;t���1%��:�;;�t:.;�.•

Signature Davl.d Matson

DigilallysignedbyDavidMalson Date: 2022.05.26 15:54:03-04'00'

Signature

Date

Date

Date

Date

Cat/Year Fund Module Obiect Code EO

080039/22 423001 U3200 131500 QK

Total:

Amount $117,216.37

$117,216.37

B ry an B ra dnerD igitally signed by B ryan B radner D ate:

2022.06 .23 13:57:1 4 -04'00'

Sr. Engineer $136.58 60 $8,19 0 Graduate Engineer $86.03 120 $10,32 . 0 Designer $67.50 80 $5,400.00 CADD Tech $44.05 80 $3,524.00 Administration $56.90 4 $22 . 0

Total $49,23 .

Reimbursable Cost: (if applicable provide for each task in which reimbursables are required)

Postage Provide an estimated amount

$100.00

Printing - Plans

(2) 24x36 sets of Prints x 25 sheets x $3/sheet

$150.00

Printing - Specifications

(2) 8.5 x 11 set of Draft Specifications 250 shts x 0.15

$75.00

Subsistence per FS 112.061

Not Allowed $0.00

Mileage (@ $0.445 per mile)

(1) trip x 380 miles x $.445/mile

$169.10

Reimbursable Total Cost $494.

Total for Subtask 2: (Fixed Price Cost + Reimbursable) $49,73 .

Subtask 3: 100% documents Description:

Complete contract documents, final plans, final details, schedules, and final specifications.

Submit for document review and approval by State Fire Marshalls Office Respond to comments from State Fire Marshalls Office

Deliverable:

Five Hard copies and pdf copy of 100% contract documents, signed and sealed.

Transmit AutoCAD files via eTransmit to the BDC project manger Updated cost estimate

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 3 - 100% Documents

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Clemons, Rutherford & Associates, Incorporated

President - CEO $203.28 4 $813.

Project Manager $134.13 40 $5,365. 0 Production VP $112.17 12 $1,346.0 CADD Technician $60.57 60 $3,634. 0 Spec writer $102.90 20 $2,058.00 Admin $73.83 10 $738. 0

H2Engineering, Incorporated

Principal $185.30 20 $3,706.00 Sr. Engineer $136.58 60 $8,19 . 0 Graduate Engineer $86.03 80 $6,882. 0 Designer $67.50 100 $6,750.00 CADD Tech $44.05 80 $3,524.00 Administration $56.90 10 $569.00

Total $43,58 .0

Reimbursable Cost: (if applicable provide for each task in which reimbursables are required)

Postage Provide an estimated amount

$250.00

Printing - Plans

(5) 24x36 sets of Prints x 35 sheets x $3/sheet

$525.00

Printing - Specifications

(5) 8.5 x 11 set of Specifications 350 shts x 0.15

$262.50

Subsistence per FS 112.061

Not Allowed $0.00

Mileage (@ $0.445 per mile)

(0) trips x 380 miles x $.445/mile

0.00

Reimbursable Total Cost $1,03 .0

Total for Subtask 3: (Fixed Price Cost + Reimbursable) $44,618.

Subtask 4: Bidding Description:

In-office consultation

Attend pre-bid conference Deliverable:

Copies of addenda, if applicable Copy of pre-bid meeting minutes

NOT CURRENTLY

ENCUMBERED

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 4 - Bidding/Pricing Assistance

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Clemons, Rutherford & Associates, Incorporated

President - CEO $203.28 1 $203.00 Project Manager $134.13 10 $1,341.00 Production VP $112.17 1 $112.00 CADD Technician $60.57 3 $182.00 Spec writer $102.90 3 $309.00 Contract Administration $91.86 8 $735.00 Admin $73.83 4 $295.00

H2Engineering, Incorporated

Principal $185.30 2 $371.00 Sr. Engineer $136.58 18 $2,458.00

Graduate Engineer $86.03 8 $688.00 Designer $67.50 8 $540.00 CADD Tech $44.05 8 $352.00

Administration $56.90 2 $114.00

Total $7,700.00

Reimbursable Cost:

Postage Provide an estimated amount

Printing - Plans

(0) 24x36 sets of Prints x 10 sheets x $2/sheet

$0.00

Printing - Specifications

(0) 8.5 x 11 set of Specifications 200 shts x 0.15

$0.00

Subsistence per FS 112.061

Not Allowed $0.00

Mileage (@ $0.445 per mile)

(2) trips x 380 miles x $.445/mile

$338.20

Reimbursable Total Cost $338.00

NOT CURRENTLY ENCUMBERED

Total for Subtask 4: (Fixed Price Cost + Reimbursable) $10,192.00

Subtask 5a: Contract Administration - Pre-construction and Shop Drawing Review Description:

Attend kickoff meeting.

Review shop drawings and product data.

Deliverable:

Meeting minutes Copies of shop drawings and product data

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 5a - Contract Administration - Pre-construction and Shop Drawing Review

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Clemons, Rutherford & Associates, Incorporated

President - CEO $203.28 2 $407.00 Project Manager $134.13 4 $537.00 Production VP $112.17 2 $224.00 CADD Technician $60.57 4 $242.00 Spec writer $102.90 $0.00 Contract Administration $91.86 24 $2,205.00 Admin $73.83 8 $591.00

H2Engineering, Incorporated

Principal $185.30 10 $1,853.00 Sr. Engineer $136.58 24 $3,278.00 Graduate Engineer $86.03 25 $2,151.00 Designer $67.50 12 $810.00 CADD Tech $44.05 12 $529.00 Administration $56.90 6 $341.00

Total $13,168.00

Reimbursable Cost:

Postage Provide an estimated amount

$0.00

Printing - Plans

(0) 24 x 36 sets of Prints x 10 sheets x $2/sheet

$0.00

Printing - Specifications

(0) 8.5 x 11 set of Specifications 200 shts x 0.15

$0.00

Subsistence per FS 112.061

Not Allowed $0.00

Mileage (@ $0.445 per mile)

(1) trips x 380 miles x $.445/mile

$338.20

Reimbursable Total Cost $338.00

Total for Subtask 5a: (Fixed Price Cost + Reimbursable) $13,506.00

Subtask 5b: Contract Administration - Site visits - Pay Application Review Description:

Complete progress site visits, H2 only Complete substantial completion site visit, H2, CRA.

Complete final completion site visit, H2 only

Deliverable:

Copies of field reports Substantial completion field report with punch list Final completion field report

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 5b - Contract Administration - Site visits - Pay Application Review

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Clemons, Rutherford & Associates, Incorporated

President - CEO $203.28 1 $203.00 Project Manager $134.13 1 $134.00 Production VP $112.17 1 $112.00 CADD Technician $60.57 1 $61.00 Spec writer $102.90 $0.00 Contract Administration $91.86 24 $2,205.00 Admin $73.83 6 $443.00

H2Engineering, Incorporated

Principal $185.30 10 $1,853.00

Sr. Engineer $136.58 24 $3,278.00 Graduate Engineer $86.03 35 $3,011.00 Designer $67.50 0 $0.00 CADD Tech $44.05 0 $0.00 Administration $56.90 6 $341.00

Total $11,641.00

Reimbursable Cost:

Postage Provide an estimated amount

Printing - Plans

(0) 24 x 36 sets of Prints x 10 sheets x $2/sheet

$0.00

Printing - Specifications

(0) 8.5 x 11 set of Specifications 200 shts x 0.15

$0.00

Subsistence per FS 112.061

Not Allowed $0.00

Mileage (@ $0.445 per mile)

(6) trips x 380 miles x $.445/mile

$1,352.80

Reimbursable Total Cost $1,353.00

Total for Subtask 6: (Fixed Price Cost + Reimbursable) $12,994.00

Subtask 7: Life Cycle Cost Analysis Description:

Life Cycle Cost Analysis as required by code Deliverable:

Copy of final Life Cycle Cost Analysis Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 7 - Life Cycle Cost Analysis

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Clemons, Rutherford & Associates, Incorporated

President - CEO $203.28 0.5 $102.00 Project Manager $134.13 4 $537.00 Production VP $112.17 1 $112.00 CADD Technician $60.57 $0.00

Spec writer $102.90 $0.00 Contract Administration $91.86 $0.00 Admin $73.83 1 $74.00

H2Engineering, Incorporated

Principal $185.30 2 $371.00 Sr. Engineer $136.58 5 $683.00 Graduate Engineer $86.03 40 $3,441.00 Designer $67.50 $0.00 CADD Tech $44.05 $0.00 Administration $56.90 $0.00

Total $5,320.00

Reimbursable Cost:

Postage Provide an estimated amount

Printing - Plans

(0) 24 x 36 sets of Prints x 10 sheets x $2/sheet

$0.00

Printing - Specifications

(0) 8.5 x 11 set of Specifications 200 shts x 0.15

$0.00

Subsistence per FS 112.061

Not Allowed $0.00

Mileage (@ $0.445 per mile)

(0) trips x 374 miles x $.445/mile

$0.00

Reimbursable Total Cost $0.00

Total for Subtask 8: (Fixed Price Cost + Reimbursable) $5,320.00 Subtask 8: HVAC Commissioning Description:

Commissioning of HVAC Systems. Minimum as required by code.

o 50% of AHU s o 100% of Chillers o 100% of Pumps

Commissioning of Building Automation System.

Deliverable:

Copy of commissioning plan Copy of commissioning report

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 8 - HVAC Commissioning

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Clemons, Rutherford & Associates, Incorporated

President - CEO $203.28 0.5 $102.00 Project Manager $134.13 4 $537.00 Production VP $112.17 1 $112.00 CADD Technician $60.57 $0.00 Spec writer $102.90 2 $206.00 Contract Administration $91.86 4 $367.00 Admin $73.83 2 $148.00

H2Engineering, Incorporated

Principal $185.30 12 $2,224.00 Sr. Engineer $136.58 60 $8,195.00 Graduate Engineer $86.03 40 $3,441.00 Designer $67.50 $0.00

CADD Tech $44.05 $0.00

Administration $56.90 40 $2,276.00

Total $17,608.00

Reimbursable Cost:

Postage Provide an estimated amount

Printing - Plans

(0) 24 x 36 sets of Prints x 10 sheets x $2/sheet

$0.00

Printing - Specifications

(0) 8.5 x 11 set of Specifications 200 shts x 0.15

$0.00

Subsistence per FS 112.061

Not Allowed $0.00

Mileage (@ $0.445 per mile)

(3) trips x 380 miles x $.445/mile

$507.00

Reimbursable Total Cost $507.00

Total for Subtask 8: (Fixed Price Cost + Reimbursable) $18,115.00

Project Schedule:

Activity Duration (Calendar Days) Subtask 1 - Preliminary 30 days from execution Subtask 2 30% plans 55 days from execution for Subtask 2 Subtask 3 100% Plans 55 days from execution for Subtask 3 Subtask 4 Bid Estimated 45 days Subtask 5a Contract Admin

- Pre-construction and Shop Drawing Review

Estimated 90 days from contractor Notice to Proceed

Subtask 5b Contract Admin

- Site visits - Pay App Review

Estimated 240 days from contractor Notice to Proceed

Subtask 7 Life Cycle Cost Analysis

70 days from Notice to Proceed for Subtask 2

Subtask 8 HVAC Commissioning Services

At Final Completion

Summary of Fees:

Subtask Subtask Fixed Price Cost Subtask Reimbursable

Subtask 1: Preliminary Subtask 2: 30% plans Subtask 3: 100% Plans

Subtask 4: Bidding Assistance $7,700.00 $338.00

Subtask 5: Contract Admin

- Pre-construction and Shop Drawing Review

$13,168.00 $338.00

Subtask 6: Contract Admin

- Site visits - Pay App Review

$11,641.00 $1,353.00

Subtask 7: Life Cycle Cost Analysis $5,320.00 $0.00

Subtask 8: HVAC Commissioning $17,608.00 $507.00

Total Fixed Price Cost:

Total Reimbursable Cost: $

Overall Total Cost:

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)