CMR RFP Data Sheet 9-17-2025 Final.pdf

PDF 144 KB Posted

Attached to
New Allied Health Services Building Construction Manager at Risk
Solicitation number
113-09172025
Issued by
Person County, Greensboro City, North Carolina

About this file

This Request for Proposal (RFP) Data Sheet is issued by the State of North Carolina, specifically the State Construction Office (SCO) and Office of State Budget and Management (OSBM), for a new Allied Health Services Building at Pamlico Community College's Bayboro Campus. The project involves constructing a 20,000 square foot facility to expand allied health and science training programs, with classrooms, laboratories, and simulated health education spaces. The project is scheduled for CM @Risk Solicitation Advertisement from 9-17-2025 to 10-8-2025, with an expected design completion date of December 2026. The project will be designed by HH Architecture (lead), with additional consultants including Timmons Group, Stewart, Barton Associates, HERA Lab Planners, and 35 North.

The total project budget is $20,000,000, with $15,520,000 estimated as the Guaranteed Maximum Price (GMP), which includes construction costs, management fees, contingency, and bonds and insurance. The project will be funded through 2024 State Capital Improvement Funds (SCIF), administered by OSBM. Soft costs and owner reserves are estimated at $4,000,000, with an owner's contingency of 3% ($480,000). Interested parties can find additional information and reference documents on the NCDOA State Construction Office website, with a specific link provided for CMAR (Construction Manager At Risk) forms and documents.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP DATA SHEET

Item Datum

Short Description of Project New Allied Health Services Building, at Pamlico Community College’s Bayboro Campus, to house much needed classrooms and lab space to expand the number of allied health training programs.

SCO # 24-28765-01A

Issuing Office OSBM Administered 2024 SCIF Funds

Department, Agency/Institution, Location where the Project will be constructed

Pamlico Community College Bayboro Campus 705 Main Street Bayboro, NC 28515

Project Overview Construct a new 20,000 sq. ft. Allied Health Services building that houses classrooms, laboratories, and simulated health education spaces to support the College’s growing allied health and science programs. The building will also feature multi-purpose and f lexible spaces that will serve the College and community for years to come.

Website address (URL) for posting of notices regarding this project https://evp.nc.gov/solicitations/

Expected Date of Completion of Design

December 2026

Project Designer & Consultants Architect: HH Architecture (Lead) Civil Engineer/Landscape Architect: Timmons Group Structural Engineer: Stewart MEP Engineer: Barton Associates Lab Planner: HERA Lab Planners Cost Estimator: 35 North

Construction Manager at Risk Selection Schedule

CM @Risk Solicitation Advertisement 9-17-2025 to 10-8-2025

Construction Management Fee (Section II Paragraph E.2)

The Construction Management Fee will be a fixed number that will be reasonably negotiated between the CM at Rosk , the Owner, and the State Construction Office.

javascript:EO18323.f.abpl(null,%20'ctl00_SCOBodyTemplate_tabList_tabPageContent_gvGrid',%20'contract',%20[41,%203]);

Project Construction Cost

Total Project Budget: $20,000,000 Less:

Soft Costs and Owner Reserves -$4,000,000 Owner’s Contingency (3%) -$480,000

GMP: $15,520,000

(Estimated available for Construction Cost of Work + Estimated Construction Management Fee + Estimated CMR Contingency + Bonds and Insurance)

Reference Documents Links to the CMAR documents are listed on the State Construction Office website under the heading NCDOA Forms and Documents, Construction Manager At Risk (CMAR) Forms. The link to the NCDOA State Construction Office website is:

https://ncadmin.nc.gov/divisions/state-construction-office

Links to the specific CMAR documents from the State Construction website.

• Qualifications Questionnaire SEE BELOW-included in this document

File details come from the government source that posted it. Updated .