This Request for Qualifications (RFQ) from Durham County, North Carolina, seeks a Construction Manager at Risk (CMAR) firm to provide professional construction management services for a new Durham County Animal Shelter located at 1117 Junction Road, Durham, North Carolina. The project involves construction of a new animal shelter facility programmed for approximately 37,253 square feet of interior conditioned space, 6,690 square feet of covered exterior spaces, 2,100 square feet of warehouse space, and 1,300 square feet of barn and paddock facilities to house 131 dogs and 132 cats, with clinic space, foster and volunteer program areas, staff offices, and a large training room. The facility will achieve LEED Bronze Certification. The work will be performed in two phases under separate contracts: Phase I includes pre-construction services and submission of a Guaranteed Maximum Price (GMP), and Phase II includes bidding, award, and management of principal and specialty trade contracts. The pre-proposal conference is scheduled for November 19, 2026, at 10:00 AM EST, with the last date for questions on December 3, 2026, at 3:00 PM EST, and proposals due on December 15, 2026, at 2:00 PM EST. Following proposal evaluation, the County will shortlist three firms for oral presentations before recommending the most qualified firm to the Board of County Commissioners for final approval. The anticipated design completion date is December 2027.
The project construction cost is estimated at $39.6 million, with the Construction Management Fee to be calculated as a fixed percentage of the Cost of Work, to be reasonably determined by the County following selection. Pre-Construction Phase fees will be paid in three equal portions during Design Development, Construction Document phases, and upon submission of a complete GMP package. All proposers must possess an unlimited general contractor's license in the building classification under North Carolina General Statutes Chapter 87 and maintain a minimum of five years of experience as a Construction Manager or General Contractor. The County requires compliance with its M/WBE Program Ordinance, including identification and definition of contract packages totaling at least 10 percent of the GMP to reduce barriers to participation by Historically Underutilized Businesses and Minority Business Enterprises. Proposals must be submitted as one original plus ten copies in a package not exceeding twenty double-sided pages, and proposers must provide financial statements, surety company letters verifying bonding capability, litigation history disclosures, key personnel resumes, and project organizational charts. North Carolina E-Verify compliance is mandatory for contractors employing 25 or more employees in the state.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DURHAM COUNTY
NORTH CAROLINA
Request for Qualifications
CONSTRUCTION MANAGER AT RISK (CMAR) FOR
NEW ANIMAL SHELTER
RFQ No. 27-014
Proposals Due Date:
December 15, 2026
2:00 P.M. Eastern Time
Table of Contents
PROPOSAL SCHEDULE
REQUEST FOR LETTERS OF INTEREST AND STATEMENTS OF QUALIFICATIONS FOR
PROFESSIONAL
LEGAL NOTICE
ANNOUNCEMENT
SCOPE OF SERVICES
QUALIFICATIONS
ADDENDUM ACKNOWLEDGEMENT………………………………………………………..……..28
EQUAL EMPLOYMENT OPPORTUNITY……………………………………………………………………………………29
PROPOSAL SCHEDULE
(Note: The dates below are subject to change)
Request for Letters of Interest and Statements of Qualifications for Construction Manager at Risk (CMAR) for New Animal Shelter
RFQ No. 27-014
Advertisement Date November 8, 2026
*Pre-Proposal Conference Date November 19, 2026, at 10:00AM EST
Last Date for Questions December 3, 2026, at 3:00PM EST
Proposal Due Date December 15, 2026, at 2:00PM EST
November 8, 2026
REQUEST FOR LETTERS OF INTEREST AND STATEMENTS OF QUALIFICATIONS
FOR PROFESSIONAL
ARCHITECTURAL/ENGINEERING SERVICES
CONSTRUCTION MANAGER AT RISK (CMAR) FOR
NEW ANIMAL SHELTER
RFQ No. 27-014
Dear Proposer:
Enclosed are copies of the following documents for RFQ No. 27-014 – Construction Manager at Risk (CMAR) for New Animal Shelter:
• Announcement of the Request for Letters of Interest and Statements of Qualifications for Consultants to provide requested services.
• Affidavit of Compliance - E-Verify Form.
You are invited to submit a sealed proposal to be received not later than 2:00 P.M., on December 15, 2026. This package includes a description of the project and other relevant information. Please submit proposal to:
Delta Farrington, Senior Procurement Specialist County of Durham Purchasing Division of Finance
201 East Main Street, 7th Floor, Room 703 Durham, North Carolina 27701
Sealed proposals shall be duly marked and/or identified with Proposer name, address and RFP number. NOTE: The United States Postal Service does not deliver directly to the proposed address. Alternative means of delivery (UPS, FedEx, etc.) are strongly suggested.
Should you have any questions concerning this Request for Qualifications, please do not hesitate to give me a call.
Sincerely, Delta Farrington
Senior Procurement Specialist Enclosures
LEGAL NOTICE
Request for Letters of Interest and Statements of Qualifications for Construction Manager at Risk (CMAR) for New Animal Shelter
RFQ No. 27-014
The County of Durham, North Carolina requests Letters of Interest and Statements of Qualifications for Construction Manager at Risk (CMAR) for a new Durham County Animal Shelter to be received on December 15, 2026, at 2:00 P.M., Eastern Time, in accordance with applicable provisions of North Carolina General Statutes and Durham
County Ordinances and policies.
PRE-PROPOSAL CONFERENCE:
A Pre-Proposal Conference will be held at 10:00 A.M. Eastern Time, on November 19, 2026, located in Durham County Administration Building, 201 East Main Street, 4th Floor, Room 466, Durham, North Carolina 27701.
An electronic copy of this Request for Proposal (RFP) and bid documents can be obtained by registering with Durham County’s eBid System located under Bid Opportunities https://dconc.gov/Finance/Purchasing/Bid-Opportunities.
The County reserves the right to accept or reject such proposals as appears in its judgment to be in the best interest of the County.
Publication Date: November 8, 2026 https://dconc.gov/Finance/Purchasing/Bid-Opportunities
ANNOUNCEMENT
REQUEST FOR LETTERS OF INTEREST AND STATEMENTS OF QUALIFICATIONS
FOR PROFESSIONAL
ARCHITECTURAL/ENGINEERING SERVICES
RFQ No. 27-014
The County of Durham, North Carolina requests letters of interest and statements of qualifications from individuals to provide Professional Architectural/Engineering Services.
SCOPE OF SERVICES
REQUEST FOR QUALIFICATIONS (RFQ) DATA SHEET
Item Data Sheet
Short Description of Project The Scope of Work includes the construction of a new Durham County Animal Shelter facility to be located at 1117 Junction Road, Durham, NC.
Issuing Office Delta Farrington, Procurement Specialist askprocurement@dconc.gov Telephone No. 919.560.0741
Department, Location where the Project will be constructed
The facility is managed by the Animal Protection Society of Durham runs the shelter on behalf of Durham County.
1117 Junction Road, Durham, NC
Project Overview The new facility will provide housing for 131 dogs and 132 cats. The building is programmed for ~37,253 sf interior conditioned space, ~6,690 sf covered exterior spaces for kennels and canopies, ~2,100 sf warehouse for food and supply storage, and a ~1,300 sf barn and paddock for large animals. It will include clinic space, foster and volunteer programs, offices for staff, and a large training room. The project is scheduled to receive LEED Bronze Certification upon completion.
This building will be LEED® Bronze Certified.
Website address (URL) for posting of notices regarding this project https://dconc.gov/Finance/Purchasing/Bid-Opportunities.
Expected Date of Completion of Design
The anticipated date of completion for the design is December 2027.
Project Designer & Consultants RND Architects – Design Architect of Record
Animal Care Facility Design Consultant Animal Arts mailto:askprocurement@dconc.gov https://dconc.gov/Finance/Purchasing/Bid-Opportunities
Civil Engineering | Landscape Architecture CLH Design, PA Structural Engineering IMEG Mechanical/Plumbing Engineering 20/20 Engineering Electrical Engineering AE Design Engineering Local MEP Engineering Consultant Engineered Designs LEED Accreditation Traci Rose Rider, LEED AP Interior Design Consultant Maria Lindqvist Design Building Enclosure Consultant REI Engineers AV/IT/Security Consultant J&A Engineering Cost Estimating Consultant 35North Acoustical Consultant Thorburn Civil Engineering/Surveyor McAdams
Construction Manager at Risk Selection Schedule
Advertisement – October 19, 2026
Pre-Proposal Conference– November 19, 2026, at 10:00 A.M.
Last Day for Questions – December 3, 2026, by 3:00 P.M.
Submittals Due – December 15, 2026, by 2:00 P.M.
Construction Management Fee The Construction Management Fee will be a fixed number based on a percentage of the Cost of Work. For this project, the maximum percentage of the Cost of Work will be reasonably determined by the County once a selection has been made.
Project Construction Cost $39.6 Million
DURHAM COUNTY
Qualifications Questionnaire for Construction Manager at Risk RFQ No. 27-014
The Proposal must include all of the information set forth in this Section and other Sections of this RFQ and should be organized and tabbed appropriately. Unnecessary elaborate brochures or other materials beyond those sufficient to present a complete and effective response to this solution are not desired and may be construed as an indication of the Proposer’s lack of cost consciousness. Therefore, elaborate artwork, expensive paper and bindings, etc., are strongly discouraged.
Proposals, less attachments, shall be limited to twenty (20) double-sided (or 40 single-sided) pages or less and must be signed by an authorized representative. Additional sales, marketing and requested supplemental information will be permitted as attachments, not limited to the twenty (20) double-sided page restriction.
One (1) original and Ten (10) copies of the Proposal shall be submitted to Durham County Purchasing Division of Finance at the time and at the addresses below:
Due Date: 2:00 PM EST on December 15, 2026
Submitted to: Delta Farrington, Senior Procurement Specialist Durham County Purchasing Division of Finance Durham County Administrative Building II 201 Est Main Street, 7th Floor, Room 703 Durham, NC 27701
Project Title: CONSTRUCTION MANAGER AT RISK (CMAR) FOR NEW ANIMAL
SHELTER
Tab 1: Proposer’s Name and Principal Office serving this project:
(Include Company Name and address along with the name of the contact person with telephone number and e-mail address)
Tab II: Profile of Proposer:
A. Give the corporate history of the company including organizational structure, years in business and evidence of authority to do business in North Carolina.
B. Provide annual workload for each of the last five (5) years; number of projects and total dollar value.
C. List projects for which the company is currently committed including name & location of each project, time frame to complete & dollar volume of each project.
D. Financials – Attach latest balance sheet and income statement if available, based on company type. Audited statements preferred. If not available, attach a copy of the latest annual renewal submission to the relevant licensing board. Indicate Dunn & Bradstreet rating if one exists. (Firms must submit financial data and may clearly indicate a request for confidentiality to avoid this item becoming part of a public record.)
E. Attach letter from Surety Company or its agent licensed to do business in North Carolina verifying Proposer’s capability of providing adequate performance and payment bonds for this project.
F. List all construction projects performed by the Proposer for public entities in North Carolina during the past 10 years.
G. Litigation/Claims. If yes to any of the questions below, list the project(s), dollar value, contact information for County and Designer and provide a full explanation with relevant documentation.
1. Has your Company ever failed to complete work awarded to it?
2. Has your company ever failed to substantially complete a project in a timely manner (i.e. more than 20% beyond the original contracted, scheduled completion date)?
3. Has your company filed any claims with the County of Durham within the last five years?
4. Has your company been involved in any suits or arbitration within the last five years?
5. Are there currently any judgments, claims, arbitration proceedings or suits pending or outstanding against your company, its officers, owners, or agents?
6. Has your present Company, its officers, owners, or agents ever been convicted of charges relating to conflicts of interest, bribery, or bid rigging?
7. Has your present company, its officers, owners, or agents ever been barred from bidding public work in North Carolina?
Tab 3: Project Experience
A. List three (3) projects of similar size, scope and complexity performed by the proposer.
B. For each of the three (3) projects, include specific details on the extent to which pre-construction & (3) projects listed above where CM services were provided, list the Guaranteed Maximum Price (if given), or if not given, the estimated cost provided by you, and the total cost of the project at completion.
C. For each of the three (3) projects above where CM services were provided, compare the number of days in the original schedule with the number of days taken for actual completion.
D. For each of the three (3) projects listed above, attach project owner references including the name, address, telephone and fax numbers, and e-mail address of the project owner representative.
Tab 4: Key Personnel
A. List of key personnel who will be assigned to the project. Attach a sworn statement that the above persons will be exclusively assigned to this project for its duration.
B. For each person listed above, list what aspects of pre-construction or construction the person will handle. For those persons who will divide their time between pre-construction and construction phases, indicate what percentage of their time will be devoted to each phase.
C. For each person listed in response to A & B above, list his/her experience with firm, other prior and relevant experience with projects of similar size and scope in construction/design, and the person’s location. Attach the resumes and references for each person listed.
D. Attach project organizational chart indicating the placement of each of the persons listed in response to A & B above.
Tab 5: Project Planning
A. Provide a brief, overall description of how the project will be organized and managed, and how the services will be performed in both Pre-Construction and Construction Phases. Project planning that offers the same project manager for pre-construction and construction phases shall be given preference.
a. Value Engineering
b. Constructability Issues
c. Cost Model/Estimates
d. Project Tracking/Reporting
e. Request for Information (RFI) and Shop Drawings
f. Quality Control
g. Schedule and Staffing Plan
Tab 6: Signed Forms
This Tab should include the following forms and information:
a. Verification Form (Notarized)
b. Addendum Acknowledgement Form
c. Affidavit of Compliance (E-Verify) (Notarized)
d. Vendor Application w/W-9 Form (Recommended, but not required at the time of bid submission)
I. SECTION I – PROPOSALS, EVALUATION, SELECTION AND AWARD
A. SUMMARY
The objective of this Request for Qualifications (RFQ) is for the County to select a Construction Management firm at risk (CMR) to provide professional construction management services during the design and the construction of the Project as described in this RFQ.
1. The work of the Construction Manager-at-Risk will be performed in two phases under separate contracts for each phase. Phase I will include the pre-construction phase services and the preparation and submission of the Preliminary Guaranteed Maximum Price (PGMP) or Guaranteed Maximum Price (GMP). Phase II will include the bidding, award and management of numerous principal and specialty trade contracts for others to provide the actual construction of the Project.
Since the Construction Manager-at-Risk will be providing only professional services for the benefit of the County based on a fee for such services, this procurement will be made in accordance with provisions of North Carolina General Statute (N.C.G.S) 143-64.31 which require that firms qualified to provide such services be selected on the basis of demonstrated competence and qualification for the type of professional service required without regard to fee and thereafter negotiate a contract for those services at a fair and reasonable fee with the best qualified firm.
All work performed under this contract shall be in accordance with the General Conditions of the Contract hereinafter set as modified or supplemented by any Contract Amendments, Special Conditions, or other Contract Documents as listed hereinafter any addenda, and other components of the Contract.
B. PRE-PROPOSAL CONFERENCE
A Pre-Proposal Conference inclusive of site tour will be held as set forth on the foregoing RFQ Data Sheet.
1. Should a Proposer find discrepancies in, or omissions from the documents, or should be in doubt as to their meaning, he/she should at once notify the County, and a written Addendum shall be issued.
The County will not be responsible for any oral instructions.
Acknowledgment of any Addendum received shall be noted on the Addendum Acknowledgement Form included in the RFQ. In closing of a contract, any Addendum issued shall become a part thereof.
All questions shall be received by the Purchasing Division no later than 3:00 PM EST, on December 3, 2026. NO EXCEPTIONS
2. Any addenda to the Request for Qualifications must be acknowledged on the Acknowledgement Form included in the Request for Qualifications.
C. PROPOSALS
1. All Proposals shall include the information requested by the Qualifications Questionnaire. One (1) original plus Ten (10) copies (for a total of eleven (11) of the Proposal must be received at the issuing office as set forth on the Data Sheet in order to be considered.
The County reserves the right to reject either all Proposals after the opening of the Proposals but before award, or any Proposal, in whole or part, when it is in the best interest of the County. For the same reason, the County reserves the right to waive any minor irregularity in a Proposal.
2. Proposers must possess all licenses required by North Carolina law, including, at a minimum, an unlimited general contractor’s license in the building classification under N.C.G.S. Chapter 87, and shall submit proof of current licensing with their Proposal.
3. If the Proposer is a joint venture firm or partnership, the Proposer must provide all identification information for all parties and all requirements for all parties (i.e., licenses, insurance, etc.) as requested. As part of the Proposal submission under the category of Project Planning - General, the Proposer must identify the responsibilities of each joint venture or partnership party with respect to the scope of services/work inclusive of the requirements for each entity based on such services as described in this RFQ document. All joint venture/partnership parties will be held responsible for the contract obligations jointly and severally.
4. Proposers should give specific attention to the identification of those portions of their Proposals which they deem to be confidential, proprietary information or trade secrets, and provide any justification of why such materials, upon request, should not be disclosed by the County under North Carolina public records laws. Proposers must clearly indicate each and every section that is deemed to be confidential, proprietary or a trade secret as required by statute. It is NOT sufficient to preface your entire Proposal with a proprietary statement.
D. PROPOSALS REQUIREMENTS
1. A Proposer, to be considered, must have a minimum of five (5) years of experience as a Construction Manager or General Contractor.
Construction management experience gained by key personnel proposed for this project during previous employment in providing Pre-Construction and Construction Phase Services may be considered in meeting this minimum experience requirement.
2. Each Proposer shall complete the Qualifications Questionnaire for
Construction Manager-at-Risk that is part of this Request for Qualifications.
3. In the interest of cost-savings, consistency of Proposals and more efficient use of time by the Evaluation Committee, the submitted information should not include any extra marketing materials. The format should be in 8-1/2” x11” pages. The package length should not exceed twenty (20) double-sided pages.
E. EVALUATION
1. After the closing date for receipt of the Proposals, the County’s Evaluation Committee shall open the Proposals. The County’s Evaluation Committee will evaluate the Proposals that are timely and properly submitted.
2. The Evaluation Committee will form a shortlist of three (3) firms whose Proposals, in the judgment of the committee, offer the most desirable plans for the provision of services considering, among other things, the experience, expertise, and reputation of the proposing firm, together with due consideration of proffered quality, performance and the time specified in the Proposals for the performance of the contract. The County reserves the right to request clarifying information from any and all Proposers at any time during the evaluation process. All Proposers will be notified in writing of those firms selected for the shortlist.
3. The County will receive an oral presentation from each firm that is short-listed by the Evaluation Committee. The purposes of the presentation are to allow the County to meet the Proposer’s key personnel assigned to the project and to allow the Proposer to highlight aspects of selected areas of its technical Proposal.
4. The Evaluation Committee will rank and present the top three (3) firms in priority order based on the selecting criteria listed below and will recommend the most qualified firm this slate of firms to the Board of County Commissioners for their consideration and final approval.
F. SELECTING CRITERIA
In selecting the most qualified firms to be presented to the Board of County
Commissioners, the Evaluation Committee should take into consideration in the evaluation of the Proposals such factors as:
1. Workload that is fully able to accommodate the addition of this project.
2. Record of successfully completed projects of similar scope without major legal or technical problems.
3. Previous experience with the County, a good working relationship with County representatives, have completed projects in a timely manner and have performed an acceptable quality of work.
4. Key personnel that have appropriate experience and qualifications.
5. Relevant and easily understood graphic or tabular presentations.
6. Completion of CM-at-Risk projects in which there was little differences between the GMP and final cost.
7. Projects that were completed on or ahead of schedule.
8. Recent experience with project costs and schedules.
9. Construction administration capabilities.
10. Proximity to and familiarity with the area where the project is located.
11. Quality of compliance plan for minority business participation as required by the County of Durham’s M/WBE Program Ordinance.
12. Other factors that may be appropriate for the project.
H. CONTRACT NEGOTIATION AND AWARD
1. After the three (3) firms have been notified of the selection action by the County, a representative from the County will discuss with the selected Construction Manager-at-Risk appropriate services and information about the project.
2. The County will request in writing a detailed fee proposal for Pre-construction Services from the selected Construction Manager-at- Risk. The County will attempt to negotiate a fair and equitable fee consistent with the project program and the professional services required for the specific project. In the event a fee cannot be agreed upon, the County shall terminate the negotiations and shall repeat the notification and negotiation process with the next ranked firm on the selection list. In the event a fee cannot be agreed upon with the second-ranked Construction Manager-at-Risk, the process will be repeated with the third-ranked Construction Manager-at-Risk. If a fee still cannot be agreed upon, the County shall review the history of negotiations and make appropriate determinations including program adjustments so as to lead to a negotiated contract with one of the original three (3) firms selected. Such renegotiation with the firms shall be carried out in the original selection order, or a call will be made for the Evaluation Committee to submit another list of three
(3) firms in priority order to the Board of County Commissioners for consideration and final approval. The negotiation process will continue until a fee has been determined that is agreed to by the County and the Construction Manager-at-Risk.
3. Following successful negotiation, the Board of County Commissioners as the final awarding authority shall award the Pre-Construction Services contract to authorize the Construction Manager-at-Risk to provide the services outlined in of this Request for Qualifications.
At the end of the Pre-construction Phase, and in accordance with the terms and conditions of this Request for Qualifications, the Construction Manager-at-Risk will ordinarily negotiate a Guaranteed Maximum Price to include Cost of the Work, Construction Manager-at-Risk Construction Management Fee, Construction Manager-at-Risk Contingency, and the cost of Bonds and Insurance. Following successful negotiation, the County will award the Guaranteed Maximum Price contract.
II. SECTION II -- GENERAL PROVISIONS
A. PROJECT OVERVIEW - See RFQ Data Sheet
B. COUNTY’S ROLE
1. DESIGN SERVICES - The County has retained the Project Designer named in the RFQ Data Sheet. The Project Designer will provide all design services throughout the duration of the Project. The CMR acknowledges that he has received a copy of the Design Contract between the County and Project Designer.
2. DESIGNATED REPRESENTATIVE - The County’s designated representative shall be the CMR’s contact point during both the Pre- Construction and Construction Phases. This County’s designated representative shall be the primary channel of communication to the County and shall act as the County’s liaison with the CMR. The County may designate multiple representatives responsible for defined aspects of the project, and may replace or re-designate any or all representatives in the County’s sole discretion.
3. DECISION MAKING AUTHORITY - In conformity with State laws the County, and the Project Designer have varying duties with respect to the several decisions required in this contract. Information from the CMR required or requested in aid of these decisions, and to the CMR with respect to the all such decisions shall be communicated either through or with the knowledge of the County’s designated representative. In the event of any disagreement or dispute between any members of the Project Team regarding the project, the County shall be the final decision making authority.
C. CONSTRUCTION MANAGER-AT-RISK CONTRACT OVERVIEW
1. The County is employing a Construction Manager-at-Risk contracting system to aid the County in the review and management of the design and to effect the construction of this project. In broad terms, the Construction Management firm selected will perform the following:
1.1 Pre-Construction Services run from the beginning of the
Construction Manager-at-Risk contract for such services (typically the beginning of the Design Development phase established by the contract between the County and the Designer unless an earlier or later time is elsewhere specified), through the approval by the County of the Guaranteed Maximum Price submitted by the Construction Manager-at-Risk. Upon agreement of the Construction Manager-at-Risk and the County, the Guaranteed Maximum Price may be submitted by the Construction Manager-at-Risk at any time after completion and approval of the Design Development Phase, but in no case later than ten (10) days after the Designer submits final review construction documents to the County for review.
1.2. Construction Services, with the Construction Manager-at-Risk General Conditions Services and Fee being provided on a lump sum basis, and all construction being accomplished through Principal Trade and Specialty Contractors selected as provided herein. The County may require, based on discussions with the Construction Manager-at-Risk and Designer, the work of the project be broken into two or more phases and require a Guaranteed Maximum Price for each phase. The use of Fast Track Contracting is not authorized.
1.3 The Construction Manager-at-Risk shall contract directly with the public entity for all construction; shall publicly advertise as prescribed in N.C.G.S. 143-129; and shall prequalify and accept bids from first-tier subcontractors for all construction work.
1.4 The requirements for the Construction Manager-at-Risk set forth in this section supplement the requirements of the General
Conditions of the Contract that are included as Section III in this
RFQ.
D. RELATIONSHIP OF COUNTY AND CONSTRUCTION MANAGER
While the Construction Manager-at-Risk accepts financial risk in providing a Guaranteed Maximum Price for delivery of the Project, the Guaranteed Maximum Price will contain a contingency for (or in certain circumstances may be amended because of) conditions or circumstances which a prudent Construction Manager-at-Risk could not have reasonably detected at the time the Guaranteed Maximum Price was given. Accordingly, without limiting the guaranty given by the Construction Manager-at-Risk with respect to the maximum price, the primary duties of the Construction Manager-at-Risk also include the proper and timely completion of the design and construction of the Project through the employment of the best construction management practices. The Construction Manager-at-Risk project records will be an “open book”. The County may attend any and all meetings and the County or its designated auditors or accountants shall have access to any and all records maintained by the Construction Manager-at-Risk that relate to the project.
E. CONSTRUCTION MANAGER-AT-RISK GENERAL CONDITIONS
ALLOWANCE AND FEESP
1. Pre-Construction Phase (Herein sometimes referred to as Design Phase) The Construction Manager-at-Risk Pre-Construction Phase Fee shall be an all inclusive lump sum fee for providing all required services as hereinafter set forth for the Design Phases, established by the contract between the County and the Designer.
2. The Construction Manager-at-Risk General Conditions Allowance &
Construction Phase Fee shall be an all inclusive lump sum management fee which will include all Construction Manager-at-Risk home office, project site and project related costs, including all Construction Manager-at-Risk overhead costs and profit. This fee will be hereinafter referred to as the Construction Management Fee and shall be calculated as a percentage of the Cost of the Work as stated on the RFQ Data Sheet. Project site costs in the Construction Management Fee should include:
a. Project staff costs – direct salary plus customary labor burden, transportation and/or subsistence, communications, computers & travel expenses related to equipment/material survey & inspections.
b. Mobilization – establishment of job site including office & storage trailer set-up & utility connections, site fencing and identification signage.
c. Temporary Facilities – rental of field office trailer(s) including an independent office for the County’s representative and Project Designer and a conference room for about twenty (20) people;
utilities costs for field office trailer(s); rental (or purchase) of field office furniture & equipment; field office telephone(s) with voice mail, dedicated fax lines and high speed internet connections; field office operation cost (i.e. stationary, postage shipping, equipment maintenance, etc.); temporary construction utilities (if required);
small tools, storage yard rental, parking lot rental, and parking fees.
d. Plans/Surveys/Permits – reproduction of Construction Documents during the construction phases; surveyor’s services as required; all required permits, all appropriate contractor and equipment licenses.
e. Safety/Cleanup – establishment and maintenance of an on-site safety program; installation and maintenance of temporary facilities (safety barricades, partitions, ladders, stairs, safety signage, first aid, traffic control devices, etc.); daily site clean-up, trash collection and removal; maintenance of site security; site snow removal as required; temporary weather and/or dust protection as required, vehicle wash stations as may be required;
fire extinguishers and fire watch as required; safety harnesses, lanyards and fall arrest equipment as required.
f. Close-out/Demobilization – final site/facility clean-up; final release of liens for all sub-contracts; an as-built set of drawings in hard copy to the Project Designer for preparation of record as-built drawings; multiple copies (# determined by County) of project files and records for the County’s archives.
g. Quality Control – monthly reports, photographs, inspection reports, logs (RFIs, Proposals, change orders, etc.)
h. All costs in this section shall be paid by the Construction Manager-at-Risk and shall not be passed down to the Principal Trade Contractors or any subcontractor.
3. The cost of Bonds and Insurance as required by Article 34 of The General Conditions of the Contract shall be carried in the GMP as a separate line item, not part of the Construction Management Fee.
F. PAYMENTS TO THE CONSTRUCTION MANAGER-AT-RISK
1. Payment of the Construction Manager-at-Risk Pre-Construction Fee shall be made in an agreed monthly sum upon the evaluation by the County, after consultation with the Project Designer of work accomplished by the Construction Manager-at-Risk, but in no event exceeding the following schedule:
a. One-third of the Fee during the Design Development Phase of the Project;
b. One-third of the Fee during the Construction Document Phase of the Project;
c. One-third of the Fee within fifteen (15) days after the
Construction Manager-at-Risk submits a complete Guaranteed Maximum Price package for the Project.
2. Payments of the Construction Management Fee shall be made in conformance with the General Conditions to the Contract included as Section III of this Request for Qualifications.
G. PRE-CONSTRUCTION SERVICES
2. The Construction Manager-at-Risk shall meet with the County, the Project Designer and any other design team members to fully understand the Program, the design documents, the Project scope and all other pertinent aspects of the Project. The Construction Manager-at-Risk shall become an integral part of the Project Team and shall develop written project procedures in cooperation with the County that will be used as a guide for the management and coordination of this project throughout the life of the project.
3. Consultation During Project Development
The Construction Manager-at-Risk shall attend regularly scheduled meetings with the Project Designer and consultants during the Design Phases to advise them on matters relating to site use, improvements, selection of materials, building methods, construction details, building systems and equipment, phasing and sequencing. The Construction Manager-at-Risk shall provide written recommendations on construction feasibility.
3. Value Analysis
3.1 The Construction Manager-at-Risk shall provide continuous value analysis studies as the project design is developed to offer suggestions that provide the most effective in first costs as well as long term operational costs relative to issues of energy use and facility maintainability. Value analysis studies shall include life cycle cost analysis as may be required to assist the Project Designer to achieve an appropriate balance between costs, aesthetics and function. All recommendations shall be in writing and must be fully reviewed with the Project Designer and County and approved by the County prior to implementation.
3.2 The Construction Manager-at-Risk shall conduct a major value analysis study at 100% Design Development utilizing the 100% Design Development documents.
3.3 The Construction Manager-at-Risk shall promptly notify the
County and Project Designer in writing upon observing any features in the design that appear to be ambiguous, confusing, conflicting or erroneous.
3.4 The Construction Manager-at-Risk shall conduct a major value analysis study at 100% Design Development (utilizing the 100% Design Development documents) which shall include, but not be limited to, the items noted below:
a. Develop value analysis concepts for consideration in brainstorming sessions with the Design Team.
b. Written cost studies shall be produced and submitted to the County within two (2) weeks of the final brainstorming session. Written pro/con evaluation of the cost studies shall be provided to the County within two (2) weeks after submission of the cost studies.
c. A formal written value analysis study document including a summary of value analysis items, applicable cost savings, selected items and their corresponding cost savings shall be presented to the County & Project Designer.
d. The Construction Manager-at-Risk shall also conduct value analysis studies during each of the Construction Document Phases to evaluate specific items as requested by the County.
4. Schedule
The Construction Manager-at-Risk shall schedule Pre-Construction Services in accordance with the design schedule established in the agreement between the County and Project Designer. The Construction Manager-at-Risk is responsible to monitor this schedule during the pre-construction/design phase, insure that this schedule is updated, and advise the County of any deficiencies in adhering to this schedule by any party.
5. Constructability Review
The Construction Manager-at-Risk shall review the design continuously throughout the Pre-Construction Phase as to constructability. With respect to each such issue, the Construction Manager-at-Risk shall submit a written report to both the County and the Project Designer. At a minimum, each such written report shall contain: (1) a description of the constructability issue with background information; (2) a summary of the in-depth study/research conducted by the Construction Manager-at-Risk;
and, (3) written recommendations for addressing the issue.
6. Construction Cost Model/Estimates
6.1 The Construction Manager-at-Risk shall develop a project
budget/cost model, independent from any similar cost estimates required of the Project Designer, which shall be updated as needed but at a minimum at the end of each design phase during which the Construction Manager-at-Risk is performing Pre- Construction Services. (Hereinafter: CM Cost Model Update.) Prior to the development of the cost model, the Construction Manager-at-Risk will meet with the Project Designer and establish a common cost estimating format so that project cost estimates prepared by the Designer and Construction Manager-at-Risk may be directly compared.
6.2 Each CM Cost Model Update must set forth the total construction costs for the facility including alternates, Construction Manager-at-Risk Construction Management Fee, Bonds, Insurance and Contingency.
6.3 In the event that the Project Designer’s Statement of Probable Construction Costs exceed the Amount Available for Construction, the County may to direct the Construction Manager-at-Risk to (and the Construction Manager-at-Risk shall without additional compensation) work in conjunction with the Project Designer to redesign the facility as necessary to maintain the Project Program within the Amount Available for Construction as set forth on the RFQ Data Sheet.
6.4 Each CM Cost Model Update and the Designer’s Probable
Construction Costs will be reviewed by the Project Designer and the County for reasonableness and compatibility with the Amount Available for Construction. Meetings and negotiations between the County, Project Designer and the Construction Manager-at- Risk will be held to resolve questions and differences that may occur between the Designer’s Probable Construction Costs and the CM Cost Model Update. The Construction Manager-at-Risk shall work with the County and Project Designer to reach a mutually acceptable joint Probable Construction Cost.
7. Coordination of Contract Documents
7.1 The Construction Manager-at-Risk shall review the plans and specification for features that may be ambiguous, confusing, conflicting or erroneous and shall notify the Project Designer and the County in writing when such features are observed.
7.2 The Construction Manager-at-Risk shall provide a thorough interdisciplinary coordination review of the Construction Drawings and Specifications submitted for review to the County.
The review shall be performed utilizing a structured and industry accepted process by a qualified firm or personnel. The Construction Manager-at-Risk shall review the final documents to see that all comments have been incorporated.
7.3 All ambiguous, confusing, conflicting and/or erroneous features discovered in the plans or specifications by the Construction Manager-at-Risk during the review process shall be deemed to be corrected, and any associated costs shall be included in the Guaranteed Maximum Price (GMP) unless the Construction Manager-at-Risk notifies the County otherwise in writing prior to the advertisement for bids.
8. Construction Guaranteed Maximum Price (GMP)
8.1 Upon agreement of the County and Construction Manager-at-Risk, the GMP may be submitted at any time after completion and approval of the Design Development Phase, but in no case later than 10 days after final review submission of the construction documents to the County.
The Construction Manager-at-Risk will develop and provide to the
County a GMP which will include all construction costs, and all other projected costs including without limitation the Construction Manager-at-Risk Construction Management Fee and Contingency but not including the County's Construction Contingency. The GMP shall set out each anticipated trade contract amount. The GMP must not exceed the Amount Available for Construction as set forth on the RFQ Data Sheet.
8.2 In the event that the GMP exceeds the Project Construction
Budget, the County reserves the right to direct the Construction Manager-at-Risk to (and the Construction Manager-at-Risk shall, without additional compensation) work in conjunction with the Project Designer to redesign the Project as necessary to and meet the Project Construction Budget. The Construction Manager-at- Risk shall work with the Project Team to alter and redraft Construction Documents as necessary to accomplish the required reduction in cost and shall provide the County with a revised GMP based on the altered and redrafted documents.
8.3 Upon acceptance by the County of a GMP, the County shall prepare and the Construction Manager-at-Risk shall execute a contract to reflect the GMP. Within ten (10) days after the County has provided a contract to the Construction Manager-at-Risk shall return to the County a signed contract including a Performance Bond, a Labor and Material Payment Bond and evidence of insurance in accordance with provisions of the General Conditions of the Contract.
9. Preliminary Guaranteed Maximum Price (PGMP)
At the option of the County, a Preliminary Guaranteed Maximum Price (PGMP) may be requested from the Construction Manager-at-Risk.
The purpose of the PGMP would be to authorize the Construction Manager-at-Risk to accept bids from Principal Trade and Specialty Contractors for the Cost of The Work for the project and for the County to share financial risk with the Construction Manager-at-Risk.
After receipt and acceptance of the Principal Trade and Specialty Contract bids, a final Guaranteed Maximum Price will be established.
In establishing the final Guaranteed Maximum Price, no changes will be made to the Construction Management Fee or Construction Manager-at-Risk Contingency. The cost for Bonds and Insurance will be adjusted as required.
10. Non-Acceptance of the GMP
10.1 The County, at its sole discretion, may decline to accept the
GMP
submitted by the Construction Manager-at-Risk for any
Construction Phase and thereupon without penalty, the Construction Manager-at-Risk work will end upon completion of the Pre-Construction Phase contract.
10.2 The Construction Manager-at-Risk shall accept the amount negotiated for Pre-Construction Services as full and complete reimbursement of all costs and services performed by the Construction Manager-at-Risk for Pre-Construction Services.
Thereafter, the County shall have the right to continue its activities to place the project under construction with no obligation or restriction regarding the Construction Manager-at- Risk and with full ownership and use of any data and information written or electronic developed during Pre-Construction activities.
11. Contingencies
11.1 Owner's Contingency: An Owner's Construction Contingency will be established. Expenditures against this contingency will be available to cover all costs resulting from changes in scope not specifically covered in Paragraph 11.2 below and initiated by the County's designated representative with the County's written approval via a change order amendment issued by the County.
11.2 Construction Manager-at-Risk GMP Contingency:
a. The GMP shall include a Construction Manager-at-Risk
Contingency in an amount approved by the County, to help reduce the risks assumed by the Construction Manager-at-Risk in providing the GMP for the Project.
The County and the Construction Manager-at-Risk acknowledge that the contingency is included to adjust the estimate for eventualities which have not been taken into precise account in the establishment of the GMP, including (1) scope gaps between trade contractors, (2) contract default by trade contractors,
(3) unforeseen field conditions and (4) design omissions which a prudent Construction Manager-at- Risk could not have reasonably detected during the discharge of his Pre-Construction Services. It is understood that the amount of the Construction Manager-at-Risk Contingency is the maximum sum available to cover costs incurred as a result of such unanticipated causes and that cost overruns in excess of the amount of this Contingency will be borne by the Construction Manager-at-Risk.
b. The Construction Manager-at-Risk Contingency may be applied to any items within the Cost of the Work without the necessity of a change order, without constituting a change in the Work, and without resulting in any change in the GMP. The Construction Manager-at-Risk will notify the County and Project Designer in writing of the intent to apply any part of this contingency to any item within the Cost of the Work prior to any such application. The Construction Manager-at-Risk shall fully document the change on its copy of the construction documents.
c. The amount of the Construction Manager-at-Risk Contingency is to be reviewed by the County as part of the review of the GMP. The County retains the right to specifically request revisions to the amount of the Construction Manager-at-Risk Contingency prior to the County's acceptance and approval of the GMP.
12. Ownership of Documents
All data information, material and matter of any nature and all copies thereof in any and all forms whatsoever developed by the Construction Manager-at- Risk or in the possession or control of the Construction Manager-at-Risk relating to the Project are the property of the County and shall be turned over to the County within ten (10) days after the County’s request.
13. Principal Trade and Specialty Contractor Pre-Qualification
13.1 All Principal Trade and Specialty Contractors shall be pre-qualified by the Construction Manager-at-Risk in accordance with the General Conditions of the Contract.
13.2 The Construction Manager-at-Risk shall identify and define contract packages (the value of which shall total to at least 10% of the GMP) that remove barriers to participation commonly experienced by Historically Underutilized Businesses and Minority Business Enterprises (as those terms are defined in N.C.G.S. 143-128.2, Hereinafter: Reduced Barrier Packages (RBP).
Such contract packages will be submitted to the County for review. As an example, RBP’s may require no performance or payment bonds, or may offer the participation of the Construction Manager-at-Risk as a guarantor or surety in the financing of materials purchases by the Principal Trade and/or Specialty Contractors, provided that the Construction Manager-at-Risk may condition such financing participation upon the issuance of joint checks or other similar arrangements to allow the Construction Manager-at-Risk to verify that timely payments are made to suppliers furnishing credit. The Construction Manager-at-Risk may propose other or additional provisions for reducing barriers to participation.
H. CONSTRUCTION PHASE SERVICES
Construction Phase services provided by the Construction Manager-at-Risk shall be as required to effect the complete construction of the Project and to maintain the established GMP of the Project.
1. Consultation During Continuing Project Development:
Upon acceptance of the GMP, the Construction Manager-at-Risk shall continue to advise and assist the County and Project Designer during any continuing Design Activities.
2. Project Construction Costs:
2.1 The Construction Manager-at-Risk will publicly bid Principal Trade & Specialty Subcontracts in accordance with the established project schedule. Upon completion of the award process for subcontracts the Construction Manager-at-Risk will summarize the values of all of the subcontracts and compare this total with the budgeted amount within the GMP cost summary.
Should the value of the awarded subcontracts be less than the GMP trade contract budget, a reserve fund will be established.
The Construction Manager-at-Risk may utilize the Reserve Fund as follows:
a. There are certain uses for the Construction Manager-at- Risk Contingency delineated in Paragraph F.11.2 above.
The Construction Manager-at-Risk can only utilize the Reserve Fund for these uses after the Construction Manager-at-Risk Contingency has been expended and upon prior written approval of the County.
b. The Construction Manager-at-Risk shall be authorized to use or allocate Reserve Funds for other purposes only upon mutual agreement that the purpose is appropriate to the project and to the contract, and only with the prior written approval of the County.
3.2 Upon completion of work any and all non-expended funds
remaining in the GMP will be retained by the County via a change order.
4. Principal Trade & Specialty Contracts
3.1 One or more Principal Trade Contract packages shall be prepared for each of the General Construction, Electrical, Mechanical, Fire Protection, and Plumbing divisions of the work of the Project. The Construction Manager-at-Risk may at any time prior to the prequalification of bidders, identify and define other Specialty Contract packages which the Construction Manager-at-Risk determines may be helpful in the timely, cost-effective construction of the Project, with or without barrier reduction.
Each Principal Trade Contractor shall provide such bonds and insurance as the Construction Manager-at-Risk may require in the contract package.
3.2 In addition to Principal Trade and Specialty Contract packages including general, plumbing, HVAC, and electrical divisions of the work, a Construction Manager-at-Risk, in conjunction with the public agency with whom the Construction Manager-at-Risk has contracted, may advertise for one or more combinations of one or more Principal Trade and/or Specialty contract packages, and may prequalify and accept bids from first-tier subcontractors who wish to submit such combined bids which fully and completely incorporate the specifications for two or more of the bid packages advertised to bid at a single bid opening. All requirements of N.C.G.S Sections 143-128, 143-128.1, 143-128.2, and 143-129, as well as all advertised conditions for bidding, must be satisfied for such a combination bid to be considered responsive.
3.3 In conformity with the public policy set forth in N.C.G.S. 143-128, no Trade Contract Package, including RBP’s, may be awarded other than to the bidder submitting the lowest verified bid.
3.4 After the Construction Manager-at-Risk…