About this file

This Request for Qualifications (RFQ) is issued by Southeastern Community College for a Construction Manager at Risk (CMAR) position on the Health Science Building R Renovation and Addition project in Whiteville, North Carolina. The project consists of facility renovations to the existing Health Science building and an estimated 5,000 square foot addition. Responses are due by December 4, 2026, at 2:00 PM via the North Carolina electronic Vendor Portal (eVP). Requests for clarifications must be received by November 30, 2026, with addenda posted to eVP. The CMAR will provide professional construction management services during design and construction phases, including pre-construction services such as design coordination, estimating, schedule development, bid-package preparation, and value-analysis recommendations; construction phase services including supervision, site safety, subcontract administration, and progress monitoring; and project closeout services. A principal of the firm, project team leader, and key personnel are expected to attend interviews for selected proponents. The College reserves the right to verify past performance and will present final selections to its Board of Trustees for approval.

The construction management fee will be negotiated with the most qualified candidate as a fixed percentage of the Cost of Work. The total project budget is $9,839,354, funded through OSBM Directed Grant (Regional Economic Development Reserve) and SCIF funds under NCCCS project number 2863. Proposing firms must submit a Letter of Interest and current Standard Form 254 (SF 254) electronically and are required to hold a current North Carolina general contractor license. Evaluation criteria include firm qualifications and capacity, relevant experience demonstrating CMAR delivery methods and comparable project size and complexity, proposed personnel with experience on similar projects, project approach addressing preconstruction, cost control, schedule development, site safety on occupied campuses, and performance disclosures addressing contract terminations, construction claims, debarment status, convictions related to public contracting, and conflicts of interest. Community college experience is not mandatory, though North Carolina public-sector and community college experience is preferred. No current set-asides are specified in this procurement.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CM at RISK ADVERTISEMENT FOR SOUTHEASTERN COMMUNITY COLLEGE

HEALTH SCIENCE BUILDING R – RENOVATION AND ADDITION

Southeastern Community College invites responses to this Request for Qualifications for a

Construction Manager at Risk for the Health Science Building – R Renovation and Addition until December 4th, 2026, by 2:00PM. The project consists of facilities renovations to the existing building as well as an estimated 5,000 square foot addition to building.

For purposes of coordination, primary contact for project information is:

Capital Projects Coordinator Ashley Butler

Phone Number 910-788-6345

E-Mail Address Ashley.butler@sccnc.edu mailto:Ashley.butler@sccnc.edu

Project Description Renovation and Addition of existing Health Science Building on the campus of Southeastern Community College

Solicitation # SCC11122026

Issuing Office Southeastern Community College

Agency/Institution, Location where the Project will be constructed

Southeastern Community College, Main Campus

4564 Chadbourn Hwy, Whiteville, NC 28472

Project Overview

Southeastern Community College has initiated a project that consists of facility renovations to existing Health Science building as well as an estimated 5,000 square feet addition to building.

Project Delivery Method

The objective of this Request for Qualifications (RFQ) is for the

Owner to select a Construction Management-at-Risk firm to provide professional construction management services during the design and the construction of the Project as described in this Request for

Qualifications (RFQ).

Since the Construction Manager-at-Risk will be providing only professional services for the benefit of the Owner based on a fee for such services, this procurement will be made in accordance with provisions of North Carolina General Statute (N.C.G.S) 143-64.31 which require that firms qualified to provide such services be selected on the basis of demonstrated competence and qualification for the type of professional service required without regard to fee and thereafter negotiate a contract for those services at a fair and reasonable fee with the best qualified firm.

Requests for clarifications and questions to this RFQ must be received by Southeastern CC not later than 11/30/2026. An addendum to respond to the inquiries received will be posted the NC electronic Vendor Portal (eVP), at https://evp.nc.gov/solicitations/

Project Designer MPS Architects

Construction Management Fee

The Construction Management Fee will be a fixed number based on a percentage of the Cost of Work. For this project, the fee will be negotiated with the most qualified candidate.

Total Project Budget $9,839,354

Source of Funds OSBM – Directed Grant (Regional Economic Development

Reserve), SCIF funds

Approved OC-25# NCCCS#2863

Submit Letter of Interest and SF-

Electronic Vendor Portal (eVP) E-Bid https://evp.nc.gov/solicitations/

STATE OF NORTH CAROLINA

HEALTH SCIENCE BUILDING R – RENOVATION AND ADDITION

Due Date: December 4th, 2026, by 2:00 PM

Submit to: NC electronic Vendor Portal (eVP)

Address: Southeastern Community College

4564 Chadbourn Hwy

Whiteville, NC 28472

910-788-6345 ashley.butler@sccnc.edu

Project Title: Health Science Building R – Renovation and Addition

Proposing firms must submit the Letter of Interest and your current Standard Form 254 (SF 254) with the information package. The current SF 254 template is located at http://ncadmin.nc.gov/businesses/construction/forms-documents which is the State Building

Commission approved form.

E-mail and Fax submittals will not be accepted.

mailto:ashley.butler@sccnc.edu http://ncadmin.nc.gov/businesses/construction/forms-documents

I. SERVICES REQUIRED

General requirements include but are not limited to the following:

A. Pre-construction services:

1. Participate in design coordination meetings; review constructability, site logistics, phasing, materials, bid-package interfaces, and construction methods.

2. Prepare and update estimates at agreed design milestones, including applicable design-development and construction-document reviews; reconcile estimates with the designer and advise on budget alignment and cost-effective alternatives.

3. Develop and maintain an integrated design, procurement, construction, and closeout schedule, including coordination with the adjacent building project.

4. Develop bid packages that fully cover the construction documents and minimize gaps and overlaps.

5. Make recommendations for value added and cost-effective measures in conjunction with the design team continuously throughout the design phases.

6. Generate overall project schedule for approval by Southeastern Community

College and continuously monitor schedule adherence throughout duration of project.

7. Responsible for prequalification of subcontractors, advertisement and bidding of the subcontractor packages and preparing a Guaranteed Maximum Price – Post

Bidding.

8. Determine contractor bid packages. Responsible for coverage of all items shown in the construction documents and division into bid packages.

9. Conduct bid openings for each first-tier subcontractor.

B. Construction (listed for general reference only, final requirements will be developed during the Pre-Construction Services phase):

1. Provide construction management, supervision, site safety, sequencing, logistics, quality control, and trade coordination; maintain safe campus access and separation from occupied areas.

2. Administer subcontracts; manage RFIs and submittals; review shop drawings before forwarding them to the designer; maintain logs and track timely resolution.

3. Monitor schedule, costs, progress, and budget forecasts; prepare payment applications and supporting documentation; evaluate and document proposed changes.

4. Conduct weekly field coordination meetings and owner/designer progress meetings every two weeks unless otherwise agreed. Participate in monthly SCO meetings when required; prepare agendas and minutes for meetings managed by the CMAR.

5. Coordinate testing and inspections with the designer, College, and authorities having jurisdiction; maintain required records and promptly address deficiencies.

C. Project Completion and Close-out:

1. Certify when the project is ready for punch list walkthrough.

2. Schedule and conduct Final Inspection.

3. Submit all warranty, guarantee, compliance statements, operation manuals, release of liens, record drawings, etc. required for final completion.

II. EVALUATION PROCESS

A. The evaluation team will be comprised of representatives of Southeastern Community

College.

B. Proponents are deemed to understand and agree that the RFQ submitted by them will be used by the evaluation team in determining, according to the evaluation team's sole and best judgment and discretion, the Proponents who are best qualified to provide the required services.

III. SUPPLEMENTARY INFORMATION AND INTERVIEWS

A. Following the evaluation team's initial evaluation of the RFQs, Southeastern Community

College will invite some Proponents to attend an interview. Unsolicited supplementary or clarifying information received after the RFQ closing time will not be considered.

B. Interview Information:

1. The purpose of the interviews will be to obtain supplementary clarifying information in addition to the written RFQs.

2. The interviews will take place at a location and time determined by Southeastern

Community College.

3. Selected Proponents will receive supplemental information regarding the interview process with notification of selection.

4. A principal of the Proponent's firm, the Proponent's team leader for the project and key personnel of major disciplines and/or subconsultants should plan to attend.

C. Southeastern Community College reserves the right to independently verify the past performance of any Proponent or any member of the Proponent's project team.

D. Following the interviews, the evaluation team will make a selection based on a tabulation of the evaluation sheets from all of the team members. Final results of the evaluation and selections will be presented to The Board of Trustees of Southeastern Community

College for final approval.

IV. REQUIRED QUALIFICATIONS SUBMITTAL

A. Firm qualifications and capacity:

• Summarize corporate history, ownership/organizational structure, years in business, and authority to conduct business in North Carolina.

• Provide North Carolina general contractor license number, classification, limitation, status, and license documentation appropriate to the anticipated work.

• Describe current workload, major commitments, completion dates, and staffing capacity for this project. Identify relevant SCO-administered work.

• Describe familiarity with North Carolina public construction requirements and the ability to provide timely on-site service. A prior contract with the College is not required.

B. Relevant experience and references:

Provide three to five projects completed within the last five years that best demonstrate comparable size, scope, and complexity. Identify the delivery method and the firm’s actual role on each project. Emphasize CMAR experience, heavy-duty asphalt/concrete paving, transportation or public-safety training facilities, site development, drainage, exterior lighting, and work on occupied institutional campuses. Identify relevant North

Carolina public-sector and community college experience where available; community college experience is not a mandatory prerequisite.

For each example, provide the project name/location, owner, brief scope, services performed, proposed team members involved, original construction budget, GMP if applicable, final construction cost, planned and actual start/completion dates, and explanation of material cost or schedule deviations. Distinguish owner-directed scope changes from other variances. Include an owner reference with name, title, telephone, and email. Describe significant challenges, solutions, and performance outcomes.

C. Proposed personnel

Identify the project executive, project manager, superintendent, preconstruction lead, and other key personnel. Provide an organizational chart, roles in each phase, relevant experience, office location, anticipated availability and time commitment by phase, current commitments, and concise resumes. Identify experience together on the referenced projects. Explain how staffing will support the proposed schedule. Proposed key personnel may not be replaced without College approval under the executed agreement.

D. Project approach

Describe the firm’s approach, not project-specific design solutions, to preconstruction estimating and reconciliation; cost control and value analysis; constructability; schedule development; site safety and occupied-campus logistics; coordination with the adjacent building project; quality control, paving quality assurance, and testing coordination; RFIs and submittals; reporting and change management; subcontractor prequalification and competitive bidding; minority-business and small-business outreach; and closeout.

Identify principal delivery risks and the process for managing them.

E. Performance and eligibility disclosures

Provide a concise signed statement addressing each item below. If an item applies, explain the circumstances, project, dates, outcome/current status, and corrective action, and provide an owner contact where relevant. Do not attach lengthy legal filings unless requested. A disclosure will be evaluated in context and does not automatically disqualify a firm.

• Within the past five years, contract termination for default, failure to complete awarded construction work, or a project finishing more than 20% beyond the original contracted substantial-completion period. Explain approved time extensions and owner-directed changes.

• Within the past five years, construction-related claims filed with SCO, litigation, or arbitration involving the firm; identify material unresolved construction-related judgments or claims affecting its ability to perform.

• Any current suspension, debarment, or prohibition on public contracting applicable to the firm, and any such action within the past five years.

• Any conviction of the firm or its officers/owners relating to conflicts of interest, bribery, bid-rigging, or public-contracting fraud.

• Any actual or potential conflict of interest affecting this selection or performance of the project.