This is a Non-Mandatory RFP Site Visit Summary prepared for the Parkrose School District CM/GC Russell Elementary School & Shaver Elementary School Geothermal RFP (RFP Number S-P26603-00018306) conducted on November 6, 2026. The project involves converting both Russell Elementary and Shaver Elementary from gas-fired boiler heating systems to closed-loop geothermal ground-source heat pump systems utilizing distributed water-source heat pumps connected to an ambient loop served by a geothermal wellfield. The site visit documented mechanical and geothermal field development strategies for both schools, including load calculations with an estimated cooling load of 80 tons for Russell Elementary, planned drilling depths of 400 feet with consideration for deeper exploration pending cost-effectiveness analysis, and the installation of geothermal vaults with main headers routed through existing utility tunnels. Delta Systems (Ainsworth) is designated as the controls contractor, with approval required for any alternative authorized Delta Control system installers. Pre-renovation asbestos inspection and testing are required due to potential hidden pipe wrap, and all drilling activities will require turf removal and restoration both on grass areas and in the parking lot.
The design strategy diverges between the two schools based on facility constraints: Russell Elementary is considering both distributed and centralized geothermal systems, while Shaver Elementary will utilize a distributed system with water-source heat pumps installed in relief tunnels to accommodate space limitations in the boiler room. Both projects will retain existing boilers to maintain geothermal loop temperatures and will utilize existing utility tunnels for piping and air distribution to reduce costs and avoid extensive new ductwork installation. Energy recovery units will be installed to address ventilation deficiencies and reduce system load. Bidders are responsible for confirming construction logistics including turf restoration following drilling operations and evaluating alternative field locations and pump placement options. The RFP was posted on October 30, 2026, with proposals due November 19, 2026.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NON-MANDATORY RFP SITE VISIT SUMMARY
Project Name: Parkrose S.D. CM/GC Russell ES & Shaver ES Geothermal RFP RFP Number: S-P26603-00018306 Date: 11/6/26 Location: Russell Elementary & Shaver Elementary Time: 10am Russell Elementary:
· Questions:
· Delta Systems (Ainsworth) is the designated controls contractor for the project. Approved control contractor is a School District. The controls contractor could be open to others as long as they are authorized Delta Control system installers.
· Regarding asbestos, pre-renovation inspection and testing will need to be conducted, as some hidden pipe wrap may still exist despite previous abatement.
· The question regarding whether tunnels interconnect throughout each site: Tunnels only connect throughout each site.
· The possibility of drilling deeper than 400 feet is under consideration, pending a cost-effectiveness analysis.
· The integration of the gym's existing heat pump is currently being evaluated for capacity; it may be excluded from the initial scope and reconnected later.
· Mechanical and Geothermal Strategy
· The project is moving toward a distributed geothermal system rather than a centralized one due, in part, to space limitations in the mechanical room. However, a central system is still being considered specifically for Russell.
· Existing boilers will be retained to maintain geothermal loop temperatures, and all pumps will be housed in the mechanical room. Alternate locations of pumps could be considered.
· Piping will be routed through existing tunnels, requiring the removal of existing undersized heating water piping.
· Energy recovery units will be installed to address ventilation deficiencies and reduce load.
· Geothermal Field Development
· The team is currently performing load calculations, with an estimated cooling load of 80 tons.
· Drilling plans target 400-foot depth bores, though 320-foot depths were initially considered.
· A vault will be installed in the field to collect laterals, with main headers routed back to the mechanical room via existing tunnels.
· Participants inquired about the feasibility of drilling on the grass, which was answered by a drilling contractor at the walk-thru. The driller said both sites turf will need to be scraped and gravel laid down. This would then need to be returned to grass after completion of the drilling. This is to be confirmed by the bidding contractor’s team.
Shaver Elementary:
· Questions:
· Participants inquired about the feasibility of drilling on the grass, which was answered by a drilling contractor at the walk-thru. The driller said both sites turf will need to be scraped and gravel laid down. This would then need to be returned to grass after completion of the drilling. This is to be confirmed by the bidding contractor’s team.
· Mechanical System Strategy
· The boiler room is insufficient for a centralized system, driving the design toward a distributed system utilizing water source heat pumps.
· The project plan involves removing the existing air handler and replacing it with a custom energy recovery unit.
· Existing utility tunnels will be utilized for air distribution and piping to avoid extensive new ductwork and achieve cost savings .
· Water source heat pumps are planned for installation within the relief tunnel, which has multiple access points.
· Geothermal Field Planning
· The geothermal field design features a central vault with branching lines, with capacity for 320’ deep bores and potential to go deeper if feasible.
· An alternative location on the property is available for the field, though it has not yet been fully vetted.
· Drilling access is planned through the parking lot to avoid the need for fence removal.